ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / DSR THE ADDRESS

Registration approved No litigation declared Residential/Group Housing project

DSR THE ADDRESS

By DSR INFRAPROJECTS

RG-KA-21894 · RERA PRM/KA/RERA/1251/308/PR/050924/006996 · Last updated on RERA Karnataka portal: 2 Sep 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2029Possession promisedno revision filed
1 of 19Construction stages donefurthest along: RCC or MS Framed structure, 60%
412 of 702Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 261 documents Report an error

DSR THE ADDRESS is a Residential/Group Housing project by DSR INFRAPROJECTS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/050924/006996 on 5 Sep 2024. Possession is promised by 12 Jun 2029. 290 of the 702 units on this registration are recorded sold or booked, and 1 of 19 construction stages are filed complete.

At a glance

Project

  • NameDSR THE ADDRESS
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/050924/006996
  • ReraGenie IDRG-KA-21894

Builder

  • NameDSR INFRAPROJECTS
  • Entity typePartnership Firm
  • GSTIN29AAPFD6671B1Z7
  • Authorized SignatoryK S SATYANARAYA REDDY
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2024PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Sep 2024
  • Promised completion12 Jun 2029
  • Revised completionNone
  • Buildings6 building records
  • Documents filed261 files

Current status

41%290 of 702 units booked
40.0%Of the estimated cost spent so far

Figures as on 2 Sep 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1---2750275
TOWER 2---2750275
TOWER 3---1200120
TOWER 4---2750275
TOWER 5---2750275
TOWER 6---1520152

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 2 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 19 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 60%.

Building: 21% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work0%
Foundation footing work0%
Retaining wall (All types)0%
Plinth level Beam0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
RCC or MS Framed structure60%
Masonry construction: Bricks, Concrete blocks etc60%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc35%
Basic work of Water supply, Sanitary and Electrification40%
Dadoing, Skirting, Flooring, Tiles work (All types)40%
Railing and Grill fixing40%
Electrification, Water supply and Sanitary Finishing30%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Painting0%
Elevation work0%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities41

As on 2 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes0%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservationNoNot applicable
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes20%
LiftsYes0%
Staircases and Lift lobbies, corridor,lobbies, corridorYes10%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable

Land and ownership22

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area55,341 sq m
Named landowners22
LandownerVillageDistrict
M VASU--
M VASU--
MOHAN BABU D M--
SHASHI KUMAR--
NAGARAJU D M--
ASHOKA M--
RAMACHENGAREDDY V--
AKSHITHA V S--
SAHITH REDDY PELLAKURU--
DODDLA KRITHI--
AMULYA REDDY DEVIREDDY--
NAGADURGESHWARI K--
SAHITH REDDY PELLAKURU--
DODDALA KRITHI--
AMULYA DEVIREDDY--
NAGADURGESHWARI K--
SAHITH REDDY PELLAKURU--
AMULA REDDY DEVINENI--
DODDLA KRITHI--
NAGADURGESHWARI K--
VAMSI KRISHNA--
C DIVYASHREE--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1,002.00 cr
Cost incurredRs 400.33 cr
Spent of the estimate39.95%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 1,002.00 crRs 400.33 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGENESIS PLANNERS PVT LTD REP BY IMAM AKTHAR
EngineerDesignTree Service Consultants Pvt Ltd rep By Srinivasa Rao Bollimunta
Chartered AccountantMUKKERA RAVI TEJA REDDY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed261

As listed on the registration, under the names the promoter filed them with; the newest 80 of 261 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/050924/006996 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: DSR THE ADDRESS CERTIFICATE.pdf2 Sep 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARC The Address Quaterly Rera certificate_.pdf2 Sep 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 THE ADDRESS RERA Q1 2026-27.pdf2 Sep 2026
Q1 2026-27 Water supply and sewage board2 Sep 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)2 Sep 2026
Q1 2026-27 KPTCL- BESCOM2 Sep 2026
Q1 2026-27 Fire and Safety2 Sep 2026
Q1 2026-27 Airport Authority of India2 Sep 2026
Q1 2026-27 BSNL/Telecommunication Department2 Sep 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 THE ADDRESS Q4 MAR 26.pdf26 Aug 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5 Architect2026.pdf26 Aug 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 Q4 DSR THE ADDRESS 3132026.pdf26 Aug 2026
Q4 2025-26 Water supply and sewage board26 Aug 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)26 Aug 2026
Q4 2025-26 KPTCL- BESCOM26 Aug 2026
Q4 2025-26 Fire and Safety26 Aug 2026
Q4 2025-26 Airport Authority of India26 Aug 2026
Q4 2025-26 BSNL/Telecommunication Department26 Aug 2026
structural stability certificate pertaining to modificationFile: STRUCTURE STABILITY CERTIFICATE new.pdf6 Apr 2026
structural engineer licenceFile: Structural Engineer LICENCE.pdf6 Apr 2026
consent letters explanation FOR TOWER 01 AND TOWER 02 SPECIFICFile: Consent letter explanation.pdf6 Apr 2026
upload 2/3rd consent forms (allotees list of tower 1 and tower 2 and their consent formsFile: TOWER 1 AND 2 CONSENT LETTERS.pdf6 Apr 2026
Allotees list of tower 1 and tower 2File: List of Allotees TOWER 1 AND TOWER 2.pdf6 Apr 2026
Affidavit for renewal of BESCOM NOCFile: Notarized Affidavit.pdf6 Apr 2026
Consent Letters - DSR THE ADDRESS - Tower-3File: Consent Letters - DSR THE ADDRESS - Tower-3 final.pdf6 Apr 2026
CONSENT LETTERS TOWER 4 - PART 1File: CONSENT LETTERS TOWER 4 01 FINAL.pdf6 Apr 2026
CONSENT LETTER TOWER 4 - PART 2File: CONSENT LETTER TOWER 4 02 FINAL.pdf6 Apr 2026
Consent Letters - DSR THE ADDRESS - Tower - 5File: Consent Letters - DSR THE ADDRESS - Tower - 5 Final.pdf6 Apr 2026
Clarification about number of units /inventories considered at the time of project registrationFile: Clarification on Principal Approval, Plan Modification, and Amendment to Modified.pdf1 Apr 2026
development PlanFile: DSR THE ADDRESS DP PLAN.pdf1 Apr 2026
sold and unsold details, list of allottees with project name along with signatureFile: SOLD AND UN SOLD DETAILS DSR THE ADDRESS new.pdf1 Apr 2026
Engineer licence, who has signed the Form-6File: Engineer Licence copy - DSR THE ADDRESS.pdf1 Apr 2026
Structural stability certificateFile: Structural Stability certificate DSR Dommasandra.pdf1 Apr 2026
AIRPORT AUTHORITY OF INDIA NOCFile: AIRPORT AUTHORITY OF INDIA.pdf1 Apr 2026
BSNL NOCFile: BSNL.pdf1 Apr 2026
KSPCB NOCFile: cfe.pdf1 Apr 2026
FIRE NOCFile: FIRE.pdf1 Apr 2026
HAL NOCFile: HAL.pdf1 Apr 2026
PANCHAYAT NOC FOR WATERS NOCFile: PANCHAYAT NOC FOR WATERS.pdf1 Apr 2026
consent 01File: Scanned Consent Letter - Address - Batch-1 (1).pdf1 Apr 2026
consent 02File: Scanned Consent Letter - Address - Batch-2 (1).pdf1 Apr 2026
consent 03File: Scanned Consent Letter - Address - Batch-3 (1).pdf1 Apr 2026
consent 04File: Scanned Consent Letter - Address - Batch-4.pdf1 Apr 2026
DSR THE ADDRESS PROJECT BDA SANCTIOND PLANSFile: DSR THE ADDRESS PROJECT BDA PFAR SANCTIOND PLANS.pdf1 Apr 2026
Dsr The Address project BDA Licence copyFile: Dsr The Address project PFAR BDA Licence copy.pdf1 Apr 2026
profit and loss account and balance sheet, 2020-21 with CA UDIN along with scheduleFile: ITR 20-21 WITH CA UDIN.pdf5 Aug 2024
Upload profit and loss account and balance sheet, 2021-22 with CA UDIN along with scheduleFile: ITR 21-22 WITH CA UDIN.pdf5 Aug 2024
Upload profit and loss account and balance sheet, 2022-23 with CA UDIN along with scheduleFile: ITR 22-23 WITH CA UDIN.pdf5 Aug 2024
sources of funds to complete the project With supporting documents.File: EXPLANATION SOURCE OF FUNDS AND ICICI BANK LOAN OFFER LETTER.pdf5 Aug 2024
Bank affidavitFile: Bank Affidavit.pdf5 Aug 2024
EC from 2-1-2024 to till date For Survey Number 65/3 66/5, 66/1 66/3 66/2 66/4File: EC from 2 1 2024 to till date For Survey Number 65 3 66 5, 661 66 3 66 2 66 4.pdf5 Aug 2024
title deed of the land owner For Survey Number 65/3 , 66/5 , 66/1, 66/3 66/2 66/4, 69/1 ,113/6 ,11File: Title deeds - DSR THE ADDRESS final.pdf5 Aug 2024
current year RTC, For Survey Number 66/4File: RTC SY NO 66 4.pdf5 Aug 2024
EC from 24/11/2023 to till date For Survey Number 69/1File: EC for sy no 69 1 till date.pdf5 Aug 2024
EC from 1-4-2008 to till date for sno 113/5,113/6 ,113/7,File: EC for sy no 113 till date.pdf5 Aug 2024
EC from 20-4-2023 to till date for sno 114/11 , 114/7,114/10File: EC for sy no 114 till date.pdf5 Aug 2024
latest dated self attested copy of the Engineer LicenseFile: ENGINEER LICENCE AND CERTIFICATE.pdf5 Aug 2024
Amenities certified by the Engineer.File: AMENITIES CERTIFIED BY ENGINEER - DSR THE ADDRESS.pdf5 Aug 2024
Common area details calculation sheet certified by the Engineer.File: Common Area Details Certified By Engineer - DSR THE ADDRESS FINAL.pdf5 Aug 2024
project specification by incorporating the project Name and Project Address certified by the EngineeFile: SPECIFICATIONS - DSR THE ADDRESS CERTIFIED BY ENGINEER.pdf5 Aug 2024
STP design drawing certified by the Engineer as per the guidelines of KSPCB NOCFile: STP DESIGN AND SPECIFICATION - DSR THE ADDRESS - CERTIFIED BY ENGINEER.pdf5 Aug 2024
source of water supply to the project along with the supporting documentsFile: Explanation on Water Source - DSR The Address.pdf5 Aug 2024
Land cost calculation sheet as per the guidance valueFile: Land Cost Calculation - Self attested.pdf5 Aug 2024
mention 30 days instead of 90 days in the defect liability clause and upload the proforma of agreemeFile: Agreement draft updated.pdf5 Aug 2024
HAL NOC - DSR THE ADDRESSFile: HAL NOC.pdf5 Aug 2024
DP PLAN IN COLOUR -- DSR THE ADDRESSFile: Dp plan colour DSR THE ADDRESS new.pdf5 Aug 2024
DP PLAN IN BLACK AND WHITE - - DSR THE ADDRESSFile: DSR THE ADDRESS DP PLAN.pdf5 Aug 2024
WORK ORDER BDA - DSR THE ADDRESSFile: Work Order.pdf5 Aug 2024
UNIT DETAILS DSR THE ADDRESS CERTIFIED BY ENGINEERFile: UNIT DETAILS DSR THE ADDRESS CERTIFIED BY ENGINEER.pdf5 Aug 2024
Detailed cost of construction cost - engineer certifiedFile: Detailed cost of construction engineer certified.pdf5 Aug 2024
RTC, survey 65/3-
Mutation, survey 65/3-
Encumbrance Certificate, survey 65/3-
Conversion/Alienation Order, survey 65/3-
JDA, survey 65/3-
Khatha, survey 65/3-
RTC, survey 66/5-
Mutation, survey 66/5-
Encumbrance Certificate, survey 66/5-
Conversion/Alienation Order, survey 66/5-

How this compares with Bengaluru Urban

41%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep DSR THE ADDRESS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmDSR THE ADDRESSOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: DSR INFRAPROJECTS

DSR INFRAPROJECTS has 3 registrations on RERA Karnataka, including DSR THE ADDRESS and DSR GREEN WATERS. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if DSR THE ADDRESS is delayed beyond 12 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of DSR THE ADDRESS?

The registered promoter entity is DSR INFRAPROJECTS, a partnership firm as per the filing. Its GSTIN 29AAPFD6671B1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in DSR THE ADDRESS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at DSR THE ADDRESS?

The professionals named in the filing: Architect: GENESIS PLANNERS PVT LTD REP BY IMAM AKTHAR; Engineer: DesignTree Service Consultants Pvt Ltd rep By Srinivasa Rao Bollimunta; Chartered Accountant: MUKKERA RAVI TEJA REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DSR THE ADDRESS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DSR THE ADDRESS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DSR THE ADDRESS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.