DSR THE ADDRESS
RG-KA-21894 · RERA PRM/KA/RERA/1251/308/PR/050924/006996 · Last updated on RERA Karnataka portal: 2 Sep 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
DSR THE ADDRESS is a Residential/Group Housing project by DSR INFRAPROJECTS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/050924/006996 on 5 Sep 2024. Possession is promised by 12 Jun 2029. 290 of the 702 units on this registration are recorded sold or booked, and 1 of 19 construction stages are filed complete.
At a glance
Project
- NameDSR THE ADDRESS
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 562125
- Pincode562125
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/050924/006996
- ReraGenie IDRG-KA-21894
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Sep 2024
- Promised completion12 Jun 2029
- Revised completionNone
- Buildings6 building records
- Documents filed261 files
Current status
Figures as on 2 Sep 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER 1 | - | - | - | 275 | 0 | 275 |
| TOWER 2 | - | - | - | 275 | 0 | 275 |
| TOWER 3 | - | - | - | 120 | 0 | 120 |
| TOWER 4 | - | - | - | 275 | 0 | 275 |
| TOWER 5 | - | - | - | 275 | 0 | 275 |
| TOWER 6 | - | - | - | 152 | 0 | 152 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 2 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 19 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 60%.
Building: 21% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 0% |
| Foundation footing work | 0% |
| Retaining wall (All types) | 0% |
| Plinth level Beam | 0% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| RCC or MS Framed structure | 60% |
| Masonry construction: Bricks, Concrete blocks etc | 60% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 35% |
| Basic work of Water supply, Sanitary and Electrification | 40% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 40% |
| Railing and Grill fixing | 40% |
| Electrification, Water supply and Sanitary Finishing | 30% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Painting | 0% |
| Elevation work | 0% |
| Internal and External work including landscapes as per santioned drawings | 0% |
Progress on shared amenities41
As on 2 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Water conservation | No | Not applicable |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | 0% |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 20% |
| Lifts | Yes | 0% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 10% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership22
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M VASU | - | - |
| M VASU | - | - |
| MOHAN BABU D M | - | - |
| SHASHI KUMAR | - | - |
| NAGARAJU D M | - | - |
| ASHOKA M | - | - |
| RAMACHENGAREDDY V | - | - |
| AKSHITHA V S | - | - |
| SAHITH REDDY PELLAKURU | - | - |
| DODDLA KRITHI | - | - |
| AMULYA REDDY DEVIREDDY | - | - |
| NAGADURGESHWARI K | - | - |
| SAHITH REDDY PELLAKURU | - | - |
| DODDALA KRITHI | - | - |
| AMULYA DEVIREDDY | - | - |
| NAGADURGESHWARI K | - | - |
| SAHITH REDDY PELLAKURU | - | - |
| AMULA REDDY DEVINENI | - | - |
| DODDLA KRITHI | - | - |
| NAGADURGESHWARI K | - | - |
| VAMSI KRISHNA | - | - |
| C DIVYASHREE | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 1,002.00 cr | Rs 400.33 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GENESIS PLANNERS PVT LTD REP BY IMAM AKTHAR |
| Engineer | DesignTree Service Consultants Pvt Ltd rep By Srinivasa Rao Bollimunta |
| Chartered Accountant | MUKKERA RAVI TEJA REDDY |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed261
As listed on the registration, under the names the promoter filed them with; the newest 80 of 261 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/050924/006996 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: DSR THE ADDRESS CERTIFICATE.pdf | 2 Sep 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARC The Address Quaterly Rera certificate_.pdf | 2 Sep 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 THE ADDRESS RERA Q1 2026-27.pdf | 2 Sep 2026 |
| Q1 2026-27 Water supply and sewage board | 2 Sep 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 2 Sep 2026 |
| Q1 2026-27 KPTCL- BESCOM | 2 Sep 2026 |
| Q1 2026-27 Fire and Safety | 2 Sep 2026 |
| Q1 2026-27 Airport Authority of India | 2 Sep 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 2 Sep 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 THE ADDRESS Q4 MAR 26.pdf | 26 Aug 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5 Architect2026.pdf | 26 Aug 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 Q4 DSR THE ADDRESS 3132026.pdf | 26 Aug 2026 |
| Q4 2025-26 Water supply and sewage board | 26 Aug 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 26 Aug 2026 |
| Q4 2025-26 KPTCL- BESCOM | 26 Aug 2026 |
| Q4 2025-26 Fire and Safety | 26 Aug 2026 |
| Q4 2025-26 Airport Authority of India | 26 Aug 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 26 Aug 2026 |
| structural stability certificate pertaining to modificationFile: STRUCTURE STABILITY CERTIFICATE new.pdf | 6 Apr 2026 |
| structural engineer licenceFile: Structural Engineer LICENCE.pdf | 6 Apr 2026 |
| consent letters explanation FOR TOWER 01 AND TOWER 02 SPECIFICFile: Consent letter explanation.pdf | 6 Apr 2026 |
| upload 2/3rd consent forms (allotees list of tower 1 and tower 2 and their consent formsFile: TOWER 1 AND 2 CONSENT LETTERS.pdf | 6 Apr 2026 |
| Allotees list of tower 1 and tower 2File: List of Allotees TOWER 1 AND TOWER 2.pdf | 6 Apr 2026 |
| Affidavit for renewal of BESCOM NOCFile: Notarized Affidavit.pdf | 6 Apr 2026 |
| Consent Letters - DSR THE ADDRESS - Tower-3File: Consent Letters - DSR THE ADDRESS - Tower-3 final.pdf | 6 Apr 2026 |
| CONSENT LETTERS TOWER 4 - PART 1File: CONSENT LETTERS TOWER 4 01 FINAL.pdf | 6 Apr 2026 |
| CONSENT LETTER TOWER 4 - PART 2File: CONSENT LETTER TOWER 4 02 FINAL.pdf | 6 Apr 2026 |
| Consent Letters - DSR THE ADDRESS - Tower - 5File: Consent Letters - DSR THE ADDRESS - Tower - 5 Final.pdf | 6 Apr 2026 |
| Clarification about number of units /inventories considered at the time of project registrationFile: Clarification on Principal Approval, Plan Modification, and Amendment to Modified.pdf | 1 Apr 2026 |
| development PlanFile: DSR THE ADDRESS DP PLAN.pdf | 1 Apr 2026 |
| sold and unsold details, list of allottees with project name along with signatureFile: SOLD AND UN SOLD DETAILS DSR THE ADDRESS new.pdf | 1 Apr 2026 |
| Engineer licence, who has signed the Form-6File: Engineer Licence copy - DSR THE ADDRESS.pdf | 1 Apr 2026 |
| Structural stability certificateFile: Structural Stability certificate DSR Dommasandra.pdf | 1 Apr 2026 |
| AIRPORT AUTHORITY OF INDIA NOCFile: AIRPORT AUTHORITY OF INDIA.pdf | 1 Apr 2026 |
| BSNL NOCFile: BSNL.pdf | 1 Apr 2026 |
| KSPCB NOCFile: cfe.pdf | 1 Apr 2026 |
| FIRE NOCFile: FIRE.pdf | 1 Apr 2026 |
| HAL NOCFile: HAL.pdf | 1 Apr 2026 |
| PANCHAYAT NOC FOR WATERS NOCFile: PANCHAYAT NOC FOR WATERS.pdf | 1 Apr 2026 |
| consent 01File: Scanned Consent Letter - Address - Batch-1 (1).pdf | 1 Apr 2026 |
| consent 02File: Scanned Consent Letter - Address - Batch-2 (1).pdf | 1 Apr 2026 |
| consent 03File: Scanned Consent Letter - Address - Batch-3 (1).pdf | 1 Apr 2026 |
| consent 04File: Scanned Consent Letter - Address - Batch-4.pdf | 1 Apr 2026 |
| DSR THE ADDRESS PROJECT BDA SANCTIOND PLANSFile: DSR THE ADDRESS PROJECT BDA PFAR SANCTIOND PLANS.pdf | 1 Apr 2026 |
| Dsr The Address project BDA Licence copyFile: Dsr The Address project PFAR BDA Licence copy.pdf | 1 Apr 2026 |
| profit and loss account and balance sheet, 2020-21 with CA UDIN along with scheduleFile: ITR 20-21 WITH CA UDIN.pdf | 5 Aug 2024 |
| Upload profit and loss account and balance sheet, 2021-22 with CA UDIN along with scheduleFile: ITR 21-22 WITH CA UDIN.pdf | 5 Aug 2024 |
| Upload profit and loss account and balance sheet, 2022-23 with CA UDIN along with scheduleFile: ITR 22-23 WITH CA UDIN.pdf | 5 Aug 2024 |
| sources of funds to complete the project With supporting documents.File: EXPLANATION SOURCE OF FUNDS AND ICICI BANK LOAN OFFER LETTER.pdf | 5 Aug 2024 |
| Bank affidavitFile: Bank Affidavit.pdf | 5 Aug 2024 |
| EC from 2-1-2024 to till date For Survey Number 65/3 66/5, 66/1 66/3 66/2 66/4File: EC from 2 1 2024 to till date For Survey Number 65 3 66 5, 661 66 3 66 2 66 4.pdf | 5 Aug 2024 |
| title deed of the land owner For Survey Number 65/3 , 66/5 , 66/1, 66/3 66/2 66/4, 69/1 ,113/6 ,11File: Title deeds - DSR THE ADDRESS final.pdf | 5 Aug 2024 |
| current year RTC, For Survey Number 66/4File: RTC SY NO 66 4.pdf | 5 Aug 2024 |
| EC from 24/11/2023 to till date For Survey Number 69/1File: EC for sy no 69 1 till date.pdf | 5 Aug 2024 |
| EC from 1-4-2008 to till date for sno 113/5,113/6 ,113/7,File: EC for sy no 113 till date.pdf | 5 Aug 2024 |
| EC from 20-4-2023 to till date for sno 114/11 , 114/7,114/10File: EC for sy no 114 till date.pdf | 5 Aug 2024 |
| latest dated self attested copy of the Engineer LicenseFile: ENGINEER LICENCE AND CERTIFICATE.pdf | 5 Aug 2024 |
| Amenities certified by the Engineer.File: AMENITIES CERTIFIED BY ENGINEER - DSR THE ADDRESS.pdf | 5 Aug 2024 |
| Common area details calculation sheet certified by the Engineer.File: Common Area Details Certified By Engineer - DSR THE ADDRESS FINAL.pdf | 5 Aug 2024 |
| project specification by incorporating the project Name and Project Address certified by the EngineeFile: SPECIFICATIONS - DSR THE ADDRESS CERTIFIED BY ENGINEER.pdf | 5 Aug 2024 |
| STP design drawing certified by the Engineer as per the guidelines of KSPCB NOCFile: STP DESIGN AND SPECIFICATION - DSR THE ADDRESS - CERTIFIED BY ENGINEER.pdf | 5 Aug 2024 |
| source of water supply to the project along with the supporting documentsFile: Explanation on Water Source - DSR The Address.pdf | 5 Aug 2024 |
| Land cost calculation sheet as per the guidance valueFile: Land Cost Calculation - Self attested.pdf | 5 Aug 2024 |
| mention 30 days instead of 90 days in the defect liability clause and upload the proforma of agreemeFile: Agreement draft updated.pdf | 5 Aug 2024 |
| HAL NOC - DSR THE ADDRESSFile: HAL NOC.pdf | 5 Aug 2024 |
| DP PLAN IN COLOUR -- DSR THE ADDRESSFile: Dp plan colour DSR THE ADDRESS new.pdf | 5 Aug 2024 |
| DP PLAN IN BLACK AND WHITE - - DSR THE ADDRESSFile: DSR THE ADDRESS DP PLAN.pdf | 5 Aug 2024 |
| WORK ORDER BDA - DSR THE ADDRESSFile: Work Order.pdf | 5 Aug 2024 |
| UNIT DETAILS DSR THE ADDRESS CERTIFIED BY ENGINEERFile: UNIT DETAILS DSR THE ADDRESS CERTIFIED BY ENGINEER.pdf | 5 Aug 2024 |
| Detailed cost of construction cost - engineer certifiedFile: Detailed cost of construction engineer certified.pdf | 5 Aug 2024 |
| RTC, survey 65/3 | - |
| Mutation, survey 65/3 | - |
| Encumbrance Certificate, survey 65/3 | - |
| Conversion/Alienation Order, survey 65/3 | - |
| JDA, survey 65/3 | - |
| Khatha, survey 65/3 | - |
| RTC, survey 66/5 | - |
| Mutation, survey 66/5 | - |
| Encumbrance Certificate, survey 66/5 | - |
| Conversion/Alienation Order, survey 66/5 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep DSR THE ADDRESS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 22 registered projects within 2 km.
Nambiar District 25 Phase 3
Nambiar EnsembleResidential Projects LLP
Meridian Park Phase II @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase I @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase III @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Nambiar District 25 Phase 2
Nambiar EnsembleResidential Projects LLP
SEVEN SARJAPUR
FORTUNE PRIMERO LLP
See every Bengaluru Urban project, with the district possession charts
Builder: DSR INFRAPROJECTS
DSR INFRAPROJECTS has 3 registrations on RERA Karnataka, including DSR THE ADDRESS and DSR GREEN WATERS. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if DSR THE ADDRESS is delayed beyond 12 Jun 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of DSR THE ADDRESS?
The registered promoter entity is DSR INFRAPROJECTS, a partnership firm as per the filing. Its GSTIN 29AAPFD6671B1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in DSR THE ADDRESS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at DSR THE ADDRESS?
The professionals named in the filing: Architect: GENESIS PLANNERS PVT LTD REP BY IMAM AKTHAR; Engineer: DesignTree Service Consultants Pvt Ltd rep By Srinivasa Rao Bollimunta; Chartered Accountant: MUKKERA RAVI TEJA REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DSR THE ADDRESS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.