Home / Browse projects / Bengaluru Urban, Karnataka / Chourasia Revanta
Chourasia Revanta
RG-KA-56903 · RERA PRM/KA/RERA/1251/446/PR/030922/005214 · Last updated on RERA Karnataka portal: 27 May 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
Chourasia Revanta is a Residential/Group Housing project by Prominent Infra in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/030922/005214 on 3 Sep 2022. Possession is promised by 31 Dec 2025. The completion date has moved by 12 months from the original filing. 25 of the 50 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.
At a glance
Project
- NameChourasia Revanta
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560049
- Pincode560049
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/030922/005214
- ReraGenie IDRG-KA-56903
Builder
- NameProminent Infra
- Entity typePartnership Firm
- GSTIN29AAYFP8670P1ZQ
- Authorized SignatoryMohammed Waseem
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on3 Sep 2022
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed141 files
Current status
Figures as on 27 May 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Chourasia Revanta | - | - | - | 50 | 0 | 50 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 18 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | 100% |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
| Other Completion Works | 100% |
Progress on shared amenities40
As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Emergency Evacuation services | Yes | 100% |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 100% |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | Yes | 100% |
| Community Hall | Yes | 100% |
| Outdoor Sports facility | Yes | 100% |
| Indoor Sports facility | Yes | 100% |
| Swimming Pool | Yes | 100% |
| Gym | Yes | 100% |
| Parks | Yes | 100% |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | 100% |
| Terrace | No | Not applicable |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 100% |
| Common storage spaces | No | Not applicable |
Land and ownership3
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Sourav Raj Chourasia | - | - |
| Gaurav Raj Chourasia | - | - |
| Rajani Chourasia | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 13.00 cr | Rs 4.55 cr |
| On-site expenditure-Salaries of workers | - | Rs 34.49 lakh |
| Payment of taxes | - | Rs 10.48 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | B V Narendranath Reddy |
| Engineer | Neminath P Parigond |
| Chartered Accountant | V. Raveendra Reddy |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in Approvals; Shortage of Labour; others; Delay in getting loan
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed141
As listed on the registration, under the names the promoter filed them with; the newest 80 of 141 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/030922/005214 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA REVANTA DEC 25.pdf | 27 May 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH REVANTA DEC 25.pdf | 27 May 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR REVANTA DEC 25.pdf | 27 May 2026 |
| ALL PLANS valid till 30 03 2026File: ALL PLANS valid till 30 03 2026.pdf | 31 Mar 2025 |
| BESCOM NOCFile: BESCOM NOC.pdf | 31 Mar 2025 |
| WATER NOCFile: WATER NOC.pdf | 31 Mar 2025 |
| Commencement Certificate 03 03 2023File: Commencement Certificate 03 03 2023.pdf | 31 Mar 2025 |
| Plan Copies valid till 30 03 2026File: Plan Copies valid till 30 03 2026.pdf | 31 Mar 2025 |
| Plan Licence Letter 31 03 2021File: Plan Licence Letter 31 03 2021.pdf | 31 Mar 2025 |
| CA CertificateFile: CA Certificate Revanta.pdf | 26 Aug 2022 |
| AFSFile: AOS Revanta.pdf | 26 Aug 2022 |
| Water NOCFile: WATER NOC.pdf | 26 Aug 2022 |
| RERA Bank AccountFile: RERA ACCT.pdf | 26 Aug 2022 |
| Supplementary Partnership DeedFile: Supplementary Partnership Deed.pdf | 26 Aug 2022 |
| Profit and loss account and balance sheetFile: P and L.pdf | 24 Jul 2022 |
| CA CERTIFICATE FORM 1File: 02 RERA From 1.pdf | 24 Jul 2022 |
| BANK ACCOUNTFile: BANK ACCT PROMINENT.pdf | 24 Jul 2022 |
| SANCTIONED PLAN 1File: Plan 01.pdf | 24 Jul 2022 |
| SANCTIONED PLAN 2File: Plan 02.pdf | 24 Jul 2022 |
| SANCTIONED PLAN 3File: Plan 03.pdf | 24 Jul 2022 |
| Sectional and Elevation DrawingsFile: Plan 04.pdf | 24 Jul 2022 |
| EXCHANGE DEEDFile: 01 Exchange Deed_compressed.pdf | 24 Jul 2022 |
| GIFT DEEDFile: 02 Gift Deed.pdf | 24 Jul 2022 |
| TILTE DEED OF 36 GUNTASFile: 03 Title Deed.pdf | 24 Jul 2022 |
| TILTE DEED OF 1 ACRE TO BABUFile: 04 Title Deed 1 Acre Babu.pdf | 24 Jul 2022 |
| ALN CONVERSION ORDERFile: 05 ALN 11-12-09.pdf | 24 Jul 2022 |
| ALN DATED 06012010File: 06 ALn Dt 6-1-10.pdf | 24 Jul 2022 |
| CLARIFICATIONFile: 07 Clarification.pdf | 24 Jul 2022 |
| PARTNERSHIP DEEDFile: 09 Infra Partnership Deed.pdf | 24 Jul 2022 |
| FORM BFile: 010 RERA Form B.pdf | 24 Jul 2022 |
| JDA CUM DECLARATIONFile: 011 RERA JD Affidavite.pdf | 24 Jul 2022 |
| CERTIFIED COPYFile: 012 Sub Reg Clarification.pdf | 24 Jul 2022 |
| NON LITIGATION AFFIDAVITFile: 013 RERA No Litigationa Affidavite.pdf | 24 Jul 2022 |
| CLARIFICATION12File: 012 Clrification.pdf | 24 Jul 2022 |
| BUILDING LICENSEFile: 01 Plan Liecence Copy.pdf | 24 Jul 2022 |
| KSPCB NOCFile: 03 KSPCB.pdf | 24 Jul 2022 |
| ALL LEVEL FLOOR PLANFile: 04 All Level Floor Plan.pdf | 24 Jul 2022 |
| SINGLE PLAN AND ORDER 1File: 05 Single Layout Plan.pdf | 24 Jul 2022 |
| SINGLE PLAN AND ORDER 2File: NAKSHE MANJURATI.pdf | 24 Jul 2022 |
| ENGINEER CERTIFICATEFile: Form - 3 Engineer.pdf | 24 Jul 2022 |
| SECTION 3 AFFIDAVITFile: 04 From 3(1).pdf | 24 Jul 2022 |
| SPECIFICATIONSFile: 05 RERA Specification.pdf | 24 Jul 2022 |
| PROVISION OF STPFile: 08 STP Position.pdf | 24 Jul 2022 |
| AOSFile: 07 Sale Agreement Draft RERA.pdf | 24 Jul 2022 |
| NOC BESCOMFile: 010 Infra BESCOM NOC.pdf | 24 Jul 2022 |
| RTC, survey 105/B | - |
| Mutation, survey 105/B | - |
| Encumbrance Certificate, survey 105/B | - |
| Conversion/Alienation Order, survey 105/B | - |
| Sale/Title/Gift Deed, survey 105/B | - |
| JDA, survey 105/B | - |
| Khatha, survey 105/B | - |
| Registration CertificateFile: Company Reg Cert.pdf | - |
| Partnership DeedFile: Infra Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: N Available.pdf | - |
| Certificate issued by Architect Form 2File: N Available.pdf | - |
| Certificate issued by Engineer Form 3File: N Available.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavite.pdf | - |
| Certificate from Chartered AccountFile: N Available.pdf | - |
| Balance Sheet 2020 - 2021File: Infra IT Returns.pdf | - |
| Balance Sheet 2019 - 2020File: N Applicable.pdf | - |
| Balance Sheet 2018 - 2019File: N Applicable.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: Infra IT Returns.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: N Applicable.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: N Applicable.pdf | - |
| Director's Report 2020 - 2021File: Infra IT Returns.pdf | - |
| Director's Report 2019 - 2020File: N Applicable.pdf | - |
| Director's Report 2018 - 2019File: N Applicable.pdf | - |
| Cash Flow Statement 2020 - 2021File: Infra IT Returns.pdf | - |
| Cash Flow Statement 2019 - 2020File: N Applicable.pdf | - |
| Auditor's Report 2020 - 2021File: Infra IT Returns.pdf | - |
| Auditor's Report 2019 - 2020File: N Applicable.pdf | - |
| Auditor's Report 2018 - 2019File: N Applicable.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: Infra IT Returns.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Chourasia Revanta on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 49 registered projects within 2 km.
Floris & Commercial at Brigade Autograph
Ananthay Properties Private Limited
Godrej Woodscapes
Godrej Properties Limited
Sattva Songbird
Sattva Resi Private Limited
Godrej Splendour
Godrej Properties Limited
PAVANI MIRABILIA PHASE I
Sai Sravanthi Infra Projects Pvt Ltd
Godrej Splendour Phase II
Godrej Properties Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Prominent Infra
Prominent Infra has 1 registration on RERA Karnataka, including Chourasia Revanta. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Chourasia Revanta is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Chourasia Revanta?
The registered promoter entity is Prominent Infra, a partnership firm as per the filing. Its GSTIN 29AAYFP8670P1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Chourasia Revanta?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Chourasia Revanta?
The professionals named in the filing: Architect: B V Narendranath Reddy; Engineer: Neminath P Parigond; Chartered Accountant: V. Raveendra Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Chourasia Revanta?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.