Home / Browse projects / Bengaluru Urban, Karnataka / CHARTERED 1956
CHARTERED 1956
By CHARTERED HOUSING PRIVATE LIMITED
RG-KA-51883 · RERA PRM/KA/RERA/1251/446/PR/060924/007005 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
CHARTERED 1956 is a Residential/Group Housing project by CHARTERED HOUSING PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/060924/007005 on 6 Sep 2024. Possession is promised by 30 Jun 2028. 1 of the 7 units on this registration are recorded sold or booked, and 8 of 19 construction stages are filed complete.
At a glance
Project
- NameCHARTERED 1956
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560052
- Pincode560052
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/060924/007005
- ReraGenie IDRG-KA-51883
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on6 Sep 2024
- Promised completion30 Jun 2028
- Revised completionNone
- Buildings1 building record
- Documents filed145 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CHARTERED 1956 | - | - | - | 7 | 0 | 7 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 19 construction stages are filed complete. The stage furthest along is Elevation work, at 90%.
Building: 72% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 10% |
| Basic work of Water supply, Sanitary and Electrification | 70% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 70% |
| Railing and Grill fixing | 30% |
| Electrification, Water supply and Sanitary Finishing | 70% |
| Painting | 50% |
| Fire prevention and fire fighting fitting and fixture with network | 50% |
| Weather Proof work(tile,concrete) | 50% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 90% |
| Internal and External work including landscapes as per sanctioned drawings | 30% |
| Authority approvals | 50% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 70% |
| Sewage and Drainage System | Yes | 70% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 60% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 30% |
| Solid waste management and disposal | Yes | 20% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 30% |
| Storm water drains | Yes | 70% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 30% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 20% |
| Club House | Yes | 50% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 30% |
| Gym | Yes | 0% |
| Parks | No | Not applicable |
| Power Backup | Yes | 20% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 70% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 95% |
| Lifts | Yes | 90% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 90% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 85% |
| Basement | Yes | 90% |
| Terrace | Yes | 90% |
| Outer Wall | Yes | 100% |
| Open parking areas | Yes | 60% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| UMA RAO & OTHERS | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 27.75 cr | Rs 1.74 cr |
| Payment of taxes | Rs 5.00 cr | Rs 27.00 lakh |
| On-site expenditure-Consultants Fees | Rs 1.85 cr | Rs 81,644 |
| On-site expenditure-Site Overhead | Rs 1.50 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJENDRAN RAMARAJ |
| Engineer | PRATHITH HEGDE |
| Chartered Accountant | B.L SHASTRY |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed145
As listed on the registration, under the names the promoter filed them with; the newest 80 of 145 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/060924/007005 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Chartered 1956 Rera CA Certificate Q2 141026.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: CH 1956 Architect certificate Q2 141026.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: CH 1956 Engineer Certificate Q2 141026.pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CH 1956 FORM 4 CA Q1 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: CH 1956 Architect Certificate Q1 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: CH 1956 Engineer Certificate Q1 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA CERTIFICATE - FORM 4.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: CH1956 Architect Certificate Q4.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate Q4.pdf | 14 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 14 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 14 Apr 2026 |
| Q4 2025-26 Fire and Safety | 14 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Chartered Rera Certificate Form 4.pdf | 23 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: CH 1956 Architect Certificte.pdf | 23 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: CH 1956 Engineer Certificate.pdf | 23 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 23 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 23 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 23 Jan 2026 |
| Q3 2025-26 Fire and Safety | 23 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 23 Jan 2026 |
| VEDA CLARIFICATION WITH DOCUMENTFile: project veda-clarification with document.pdf | 2 Aug 2024 |
| CLARIFICATION VEDAFile: 1 clarification .pdf | 2 Aug 2024 |
| APPLICATION COPY FOR FINAL ORDER VEDAFile: 1 application copy for final order.pdf | 2 Aug 2024 |
| FINAL ORDER COPY VEDAFile: 1 final Realse order.pdf | 2 Aug 2024 |
| COMPLETION STATUS VEDAFile: 1 completion status.pdf | 2 Aug 2024 |
| HUMMING BIRD CLARIFICATION WITH DOCUMENTFile: project hummingbird-clarification with document.pdf | 2 Aug 2024 |
| OC HUMMING BIRDFile: 2 OC-hummingbird.pdf | 2 Aug 2024 |
| COMPLAINT DETAILS OF SRIRANJAN HUMMING BIRDFile: 2 Complaint Details - Sriranjan.pdf | 2 Aug 2024 |
| COMPLAINT DETAILS OF SHAHIKANTH HUMMING BIRDFile: 2 Complaint Details - Shashikanth.pdf | 2 Aug 2024 |
| REPLY LETTER HUMMING BIRDFile: 2 CHPL Reply Letter.pdf | 2 Aug 2024 |
| CLARIFICATION HUMMING BIRDFile: 2 clarification.pdf | 2 Aug 2024 |
| village mapFile: 1 village map.pdf | 24 Jun 2024 |
| commencement certificateFile: 2 Commencement certificate-clarification.pdf | 24 Jun 2024 |
| BUILDING LICENCEFile: 2 building licence.pdf | 24 Jun 2024 |
| UGD CLARIFICATION WITH DOCUMENTFile: 4 UGD with clarification.pdf | 24 Jun 2024 |
| BWSSB NOCFile: 3 BWSSB.pdf | 24 Jun 2024 |
| BWSSB NOTIFICATIONFile: 3 BWSSB Notification.pdf | 24 Jun 2024 |
| all sanctioned drawings floor plan, sectional drawings and elevationsFile: 4 all sanctioned drawings.pdf | 24 Jun 2024 |
| CLARIFICATIONFile: Clarification on Notice.pdf | 24 Jun 2024 |
| CA KYCFile: CA kyc self attested.pdf | 11 Jun 2024 |
| bank affidavitFile: Bank Affidavit.pdf | 11 Jun 2024 |
| FORM 1 CA CERTIFICATEFile: CA certificate revised.pdf | 11 Jun 2024 |
| SOURCE OF FUNDFile: source of fund.pdf | 11 Jun 2024 |
| CDP mapFile: CDP plan.pdf | 11 Jun 2024 |
| village map CLARIFICATIONFile: village map.pdf | 11 Jun 2024 |
| commencement certificateFile: commencement certificate.pdf | 11 Jun 2024 |
| KSPCB CLARIFICATION WITH NOTIFICATION COPYFile: clarificatuion on pollution noc along with notification copy.pdf | 11 Jun 2024 |
| all sanctioned drawingsFile: all sanctioned drawings.pdf | 11 Jun 2024 |
| Certified common area & amenitiesFile: amenities & common area certified by engineer.pdf | 11 Jun 2024 |
| Airport NOCFile: airport noc.pdf | 11 Jun 2024 |
| HAL NOCFile: HAL NOC.pdf | 11 Jun 2024 |
| ALLOTMENT LETTER OF SITEFile: allotment letter site .pdf | 11 Jun 2024 |
| allottment letter of BDA site and other related documentFile: allottment of site and other document.pdf | 11 Jun 2024 |
| clarificationFile: RERA clarification letter.pdf | 11 Jun 2024 |
| Registration CertificateFile: Copy of Reg Certificate.pdf | - |
| Memorandum of AssociationFile: Memorondum of Association_compressed.pdf | - |
| Article of AssociationFile: Articles of Association.pdf | - |
| Organization StructureFile: Organization chart.pdf | - |
| Certificate issued by CA Form 1File: CA certificate revised.pdf | - |
| Certificate issued by Architect Form 2File: Architect Certificate signed.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit for non litigation on land.pdf | - |
| Certificate from Chartered AccountFile: CA certificate revised.pdf | - |
| Balance Sheet 2022 - 2023File: Balance Sheet 2023 with notes.pdf | - |
| Balance Sheet 2021 - 2022File: Balance sheet 2022 with notes.pdf | - |
| Balance Sheet 2020 - 2021File: Balance sheet 2021 with notes.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf | - |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Chartered Woodpecker | Sy no 156/1,156/4,229/1 &229/3, Bidalur Village, Off Dodaballapur Road, Devanahalli, Bangalore, Karnataka | Completed | - | No date filed |
| Chartered Veda | SY. NO. 130, 131, 132 & 133 OF MYLANAHALLI VILLAGE,KASABA HOBLI, NELAMANGALA TALUK,BANGALORE RURAL | Completed | - | No date filed |
| Chartered Hummingbird | BALAJI LAYOUT, VAJARAHALLI BWSB SERVICE ROAD, RAGHUVANAHALLI BANGALORE | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep CHARTERED 1956 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 19 registered projects within 2 km.
Century Regalia (Project 1)
Suruchi Properties Private Limited
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: CHARTERED HOUSING PRIVATE LIMITED
CHARTERED HOUSING PRIVATE LIMITED has 2 registrations on RERA Karnataka, including CHARTERED GULMOHAR and CHARTERED 1956. Its filings declare 4 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if CHARTERED 1956 is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of CHARTERED 1956?
The registered promoter entity is CHARTERED HOUSING PRIVATE LIMITED, a company as per the filing. Its GSTIN 29AABCC0044N1ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in CHARTERED 1956?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at CHARTERED 1956?
The professionals named in the filing: Architect: RAJENDRAN RAMARAJ; Engineer: PRATHITH HEGDE; Chartered Accountant: B.L SHASTRY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CHARTERED 1956?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback