Home / Browse projects / Vadodara, Gujarat / Casa Lakeside Phase 2

Valid until 30 Jun 2023 Residential/Group Housing project

Casa Lakeside Phase 2

By PACIFICA LAKESIDE DEVELOPERS LLP

RG-GJ-84181 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA00704/EX3/130723 · Last updated on GujRERA portal: 30 Jun 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Jun 2023Possession promisedmoved 42 months from the original
14 of 42Construction stages doneacross 6 buildings; furthest along: External plumbing and external plaster, 90%
28 of 88Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

Casa Lakeside Phase 2 is a Residential/Group Housing project by PACIFICA LAKESIDE DEVELOPERS LLP in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA00704/EX3/130723 on 14 Nov 2017. Possession is promised by 30 Jun 2023. The completion date has moved by 42 months from the original filing. 60 of the 88 units on this registration are recorded sold or booked, and 14 of 42 construction stages are filed complete.

At a glance

Project

  • NameCasa Lakeside Phase 2
  • TypeResidential/Group Housing
  • Location
    • Nr.Bil Village
    • Bil-Chapad Road
    • B/h Banco Company
    • Bill
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA00704/EX3/130723
  • ReraGenie IDRG-GJ-84181

Builder

  • NamePACIFICA LAKESIDE DEVELOPERS LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredNov 2017First promiseDec 2019Revised toJun 2023

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2023
  • Registered on14 Nov 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 31 Dec 2019)
  • Buildings6 building records
  • Documents filed43 files

Current status

68%60 of 88 units booked
29.7%Of the estimated cost spent so far

Figures as on 30 Jun 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---404
D---101
E---35035
F---404
A---34034
B---10010

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 30 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 42 construction stages are filed complete across 6 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

C70%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
D72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth50%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
E75%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure88%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing66%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
F50%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure50%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
A96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
B55%
ActivityProgress
Excavation82%
Podiums (if any)Not applicable
Plinth80%
Stilt FloorNot applicable
Slabs of Super Structure60%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats5%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 30 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes70%
Water supplyYes70%
Sewerage (chamber, lines, septic tank, STP)Yes70%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes25%
Street lightingYes15%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area104,991 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 21.84 cr
Cost incurredRs 6.48 cr
Spent of the estimate29.68%
BuildingWingEstimatedIncurred
ANARs 3.64 crRs 1.08 cr
BNARs 3.64 crRs 1.08 cr
CNARs 3.64 crRs 1.08 cr
DNARs 3.64 crRs 1.08 cr
ENARs 3.64 crRs 1.08 cr
FNARs 3.64 crRs 1.08 cr

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA00704/EX1/270219Applied Nov 2018; approved Feb 2019
PR/GJ/VADODARA/VADODARA/Others/RAA00704/EX2/281221Applied May 2021; approved Dec 2021
PR/GJ/VADODARA/VADODARA/Others/RAA00704/EX3/130723Applied Jul 2023; approved Jul 2023

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA00704/EX3/130723 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)30 Jun 2023
Site photograph, C30 Jun 2023
Site photograph, D30 Jun 2023
Site photograph, E30 Jun 2023
Site photograph, F30 Jun 2023
Site photograph, A30 Jun 2023
Site photograph, B30 Jun 2023
Accountant's certificate (Form 3)7 Jun 2022
Engineer's certificate (Form 2)6 Jun 2022
Engineer's certificate annexure6 Jun 2022
RERA registration certificate14 Nov 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

68%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 42 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep Casa Lakeside Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bill2,900+ in Vadodara

2 kmCasa Lakeside Phase 2Other 204Dot size: filed unitsN

Filed coordinates, straight-line distance. 204 registered projects within 2 km.

Builder: PACIFICA LAKESIDE DEVELOPERS LLP

PACIFICA LAKESIDE DEVELOPERS LLP has 2 registrations on GujRERA, including Casa Lakeside Phase 1 and Casa Lakeside Phase 2. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if Casa Lakeside Phase 2 is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Casa Lakeside Phase 2?

The registered promoter entity is PACIFICA LAKESIDE DEVELOPERS LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Casa Lakeside Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Casa Lakeside Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Casa Lakeside Phase 2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Casa Lakeside Phase 2 to a free account