casa bellevue

By Blue Lotus Properties

RG-GJ-66064 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA01065/EX1/280519 · Last updated on GujRERA portal: 6 Oct 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Separate project account declared
Apr 2020Possession promisedmoved 11 months from the original
0 of 336Construction stages doneacross 42 buildings; furthest along: Slabs of Super Structure, 98%
18 of 42Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

casa bellevue is a Residential/Group Housing project by Blue Lotus Properties in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA01065/EX1/280519 on 20 Dec 2017. Possession is promised by 30 Apr 2020. The completion date has moved by 11 months from the original filing. 24 of the 42 units on this registration are recorded sold or booked, and 0 of 336 construction stages are filed complete.

At a glance

Project

  • Namecasa bellevue
  • TypeResidential/Group Housing
  • Location
    • Opp. Narayani Hotel
    • B/H Essar Petrol Pump
    • Bhat
    • Bhat
    • Gandhinagar
    • 382428
  • Pincode382428
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA01065/EX1/280519
  • ReraGenie IDRG-GJ-66064

Builder

  • NameBlue Lotus Properties
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2017First promiseMay 2019Revised toApr 2020

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2020
  • Registered on20 Dec 2017
  • Promised completion30 Apr 2020
  • Revised completionRevised to 30 Apr 2020 (originally 12 May 2019)
  • Buildings42 building records
  • Documents filed37 files

Current status

57%24 of 42 units booked
91.9%Of the estimated cost spent so far

Figures as on 6 Oct 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
11---101
12---101
13---101
14---101
15---101
16---101
17---101
18---101
19---101
20---101
21---101
22---101
23---101
24---101
25---101
26---101
27---101
28---101
29---101
30---101
31---101
32---101
33---101
34---101
35---101
36---101
37---101
38---101
39---101
40---101
41---101
42---101
1---101
2---101
3---101
4---101
5---101
6---101
7---101
8---101
9---101
10---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 6 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 42 buildings; the table lists the first 20.

0 of 336 construction stages are filed complete across 42 buildings. The stage furthest along is Slabs of Super Structure, at 98%.

1173%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1273%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1373%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1473%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1573%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1673%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1773%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1873%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
1973%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats77%
Sanitary fittings within the flats37%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing87%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing33%
2091%
ActivityProgress
Excavation98%
Podiums (if any)Not applicable
Plinth98%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flats82%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
2191%
ActivityProgress
Excavation98%
Podiums (if any)Not applicable
Plinth98%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flats82%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
2291%
ActivityProgress
Excavation98%
Podiums (if any)Not applicable
Plinth98%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flats82%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
2391%
ActivityProgress
Excavation98%
Podiums (if any)Not applicable
Plinth98%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flats82%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
2491%
ActivityProgress
Excavation98%
Podiums (if any)Not applicable
Plinth98%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flats82%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
2591%
ActivityProgress
Excavation98%
Podiums (if any)Not applicable
Plinth98%
Stilt FloorNot applicable
Slabs of Super Structure98%
Internal walls, internal plaster, floorings, doors and windows within flats92%
Sanitary fittings within the flats82%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
2673%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing67%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing43%
2773%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing67%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing43%
2873%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing67%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing43%
2973%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing67%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing43%
3073%
ActivityProgress
Excavation95%
Podiums (if any)Not applicable
Plinth95%
Stilt FloorNot applicable
Slabs of Super Structure95%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing67%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing43%

Progress on shared amenities19

As on 6 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes75%
Water supplyYes80%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes70%
Street lightingYes60%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,880 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.28 cr
Cost incurredRs 18.65 cr
Spent of the estimate91.92%
BuildingWingEstimatedIncurred
1NARs 48.29 lakhRs 44.39 lakh
2NARs 48.29 lakhRs 44.39 lakh
3NARs 48.29 lakhRs 44.39 lakh
4NARs 48.29 lakhRs 44.39 lakh
5NARs 48.29 lakhRs 44.39 lakh
6NARs 48.29 lakhRs 44.39 lakh
7NARs 48.29 lakhRs 44.39 lakh
8NARs 48.29 lakhRs 44.39 lakh
9NARs 48.29 lakhRs 44.39 lakh
10NARs 48.29 lakhRs 44.39 lakh
11NARs 48.29 lakhRs 44.39 lakh
12NARs 48.29 lakhRs 44.39 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj. L. Kanani
EngineerKetan. K. Patel

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA01065/EX1/280519Applied May 2019; approved May 2019

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA01065/EX1/280519 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)6 Oct 2020
Engineer's certificate (Form 2)6 Oct 2020
Engineer's certificate annexure6 Oct 2020
Accountant's certificate (Form 3)6 Oct 2020
RERA registration certificate20 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

57%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 11 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep casa bellevue on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhat1,600+ in Gandhinagar

2 kmcasa bellevueOther 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: Blue Lotus Properties

Blue Lotus Properties has 1 registration on GujRERA, including casa bellevue. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if casa bellevue is delayed beyond 30 Apr 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of casa bellevue?

The registered promoter entity is Blue Lotus Properties, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in casa bellevue?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at casa bellevue?

The professionals named in the filing: Architect: Manoj. L. Kanani; Engineer: Ketan. K. Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in casa bellevue?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About casa bellevue. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save casa bellevue to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.