Home / Browse projects / Bengaluru Urban, Karnataka / CANDADE KAY ARR SIGNATURE
CANDADE KAY ARR SIGNATURE
By KAY ARR & CO
RG-KA-82697 · RERA PRM/KA/RERA/1251/309/PR/031022/005291 · Last updated on RERA Karnataka portal: 25 Jun 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
CANDADE KAY ARR SIGNATURE is a Mixed Development project by KAY ARR & CO in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/031022/005291 on 3 Oct 2022. Possession is promised by 30 Jun 2026. 5 of the 14 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.
At a glance
Project
- NameCANDADE KAY ARR SIGNATURE
- TypeMixed Development
- Location
- Bengaluru North
- Bengaluru Urban
- 560004
- Pincode560004
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/031022/005291
- ReraGenie IDRG-KA-82697
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on3 Oct 2022
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings1 building record
- Documents filed106 files
Current status
Figures as on 25 Jun 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CANDADE KAY ARR SIGNATURE | - | - | - | - | - | 14 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 25 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 17 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Retaining wall (All types) | 100% |
| Plinth level Beam | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry construction: Bricks, Concrete blocks etc | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Other Miscellaneous Works | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 100% |
| Painting | 100% |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | 100% |
Progress on shared amenities41
As on 25 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | 100% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | 100% |
| Electricity supply transformer and substation | Yes | 100% |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 100% |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 100% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas and common storage spaces | Yes | 100% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 100% |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MR. AJAY BHARAT CANDADE GPA HOLDER OF Mr. VIJAY BHARAT CANDADE | - | - |
| MR. AJAY BHARAT CANDADE | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 7.50 cr | Rs 5.99 cr |
| On-site expenditure-Salaries of workers | Rs 2.00 cr | Rs 1.65 cr |
| On-site expenditure-Consultants Fees | Rs 10.00 lakh | Rs 85.30 lakh |
| On-site expenditure-Site Overhead | Rs 10.00 lakh | Rs 9.70 lakh |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 6.00 lakh | Rs 5.00 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SRINIVASAN R |
| Engineer | KISHORE KUMAR |
| Chartered Accountant | A.S. SREEKANTH |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed106
As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/031022/005291 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: quarter 1 26-27.pdf | 25 Jun 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Adobe Scan 25 Jun 2026 (1) (2).pdf | 25 Jun 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: engineers certificate (3)q1 26-27.pdf | 25 Jun 2026 |
| Q1 2026-27 Water supply and sewage board | 25 Jun 2026 |
| Q1 2026-27 KPTCL- BESCOM | 25 Jun 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ca Rera Certificate (3) (1).pdf | 13 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: architect ceretificate q425-26.pdf | 13 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer certificate q425-26.pdf | 13 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 13 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 13 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Rera Certificate (10).pdf | 30 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: architect certificate q3 25-26.pdf | 30 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer certificate q325-26.pdf | 30 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 30 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 30 Jan 2026 |
| BESCOM DECLARATIONFile: BESCOM DECLARATION.pdf | 9 Aug 2023 |
| BWSSB DECLARATIONFile: BWSSB DECLARATION.pdf | 9 Aug 2023 |
| BESCOM AFFIDAVITFile: bescom affidivait.pdf | 9 Aug 2023 |
| BWSSB AFFIDAVITFile: bwssb affidavit.pdf | 9 Aug 2023 |
| Structural Engineer CertificateFile: Structurl Stability Certificate.pdf | 9 Aug 2023 |
| GST CertificateFile: Kay Arr GST Certificate.pdf | 28 Sep 2022 |
| Registered GPAFile: Reg GPA- Candade Kay Arr Signature.pdf | 28 Sep 2022 |
| Registered JDAFile: REG-JDA- Candade Kay Arr Signature.pdf | 28 Sep 2022 |
| POAFile: Ajay Vijay POA.pdf | 28 Sep 2022 |
| Sharing AgreementFile: Sharing Agreement- candade kay arr signature.pdf | 28 Sep 2022 |
| GPA JDA FEE receiptFile: jda gpa registration fee receipt.pdf | 28 Sep 2022 |
| CDP MapFile: CDP MARKED.pdf | 28 Sep 2022 |
| Village MapFile: Village Map.jpeg | 28 Sep 2022 |
| BWSSB DeclarationFile: BWSSB DECLARATION.pdf | 28 Sep 2022 |
| BESCOM DeclarationFile: BESCOM DECLARATION.pdf | 28 Sep 2022 |
| BWSSB AffidavitFile: bwssb affidavit.pdf | 28 Sep 2022 |
| BESCOM AffidavitFile: bescom affidivait.pdf | 28 Sep 2022 |
| Form BFile: Affidavit cum Declaration .pdf | 28 Sep 2022 |
| AOSFile: AGREEMENT DRAFT.pdf | 28 Sep 2022 |
| Registration CertificateFile: Kay Arr GST Certificate.pdf | - |
| Certificate issued by CA Form 1File: CA.pdf | - |
| Certificate issued by Architect Form 2File: ARCH.pdf | - |
| Certificate issued by Engineer Form 3File: ENGG.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: AFFIDAVIT NON LITIGATION.pdf | - |
| Certificate from Chartered AccountFile: FORM 1 CA.pdf | - |
| Balance Sheet 2020 - 2021File: BS 2020-21 UDIN.pdf | - |
| Balance Sheet 2019 - 2020File: BS 2019-20 UDIN.pdf | - |
| Balance Sheet 2018 - 2019File: BS 2018-19 UDIN.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: PL 2020-21 UDIN.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: PL 2019-20 UDIN.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: PL 2018-19 UDIN.pdf | - |
| Auditor's Report 2020 - 2021File: AUDIT REPORT 2020-21 UDIN.pdf | - |
| Auditor's Report 2019 - 2020File: AUDIT REPORT 2019-20 UDIN.pdf | - |
| Auditor's Report 2018 - 2019File: AUDIT REPORT 2018-19 UDIN.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR ACK 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITR ACK 2019-20.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: ITR ACK 2018-19.pdf | - |
| BUILDING LICENCE | - |
| BESCOM DECLARATION | - |
| BWSSB DECLARATION | - |
| APPROVED SANCTION PLAN COPY | - |
| BUILDING LICENCE with Fee Paid | - |
| APPROVED SANCTION PLAN COPY | - |
| APPROVED SANCTION PLAN COPY | - |
| APPROVED SANCTION PLAN COPY | - |
| PROJECT SPECIFICATIONS | - |
| APPROVED SANCTION PLAN COPY | - |
| CDP | - |
| STABILITY CERTIFICATE | - |
| LEGAL OPINION | - |
| JDA GPA PA SHARING | - |
| GUIDANCE VALUE | - |
| AGREEMENT DRAFT | - |
| BOOKING FORM DRAFT | - |
| BROCHURE DECLARATION | - |
| AFFIDAVIT FORM B | - |
| AFFIDAVIT SECTION 3 | - |
| AFFIDAVIT JDA | - |
| BESCOM DECLARATION | - |
| BWSSB DECLARATION | - |
| STP Declaration KSPCB | - |
| GOOGLE LOCATION | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| KAY ARR MAVERICK | BBMP Khatha No.1470/1437/1356, Site No.1356, Yelahanka New Town Judicial layout, Judicial Department Employees House, Building Co-operative Society, BDA, Allalasandra, Chikkabommasandra, Jakkur Plantation Village, Yelahanka Hobli Bangaluru North Taluk, Bengaluru Ward No.4 | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep CANDADE KAY ARR SIGNATURE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 18 registered projects within 2 km.
The Minerva
Countryside Minerva LLP
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: KAY ARR & CO
KAY ARR & CO has 2 registrations on RERA Karnataka, including CANDADE KAY ARR SIGNATURE and KAY ARR MAVERICK. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if CANDADE KAY ARR SIGNATURE is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of CANDADE KAY ARR SIGNATURE?
The registered promoter entity is KAY ARR & CO, a proprietorship firm as per the filing. Its GSTIN 29AFAPR1455B1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in CANDADE KAY ARR SIGNATURE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at CANDADE KAY ARR SIGNATURE?
The professionals named in the filing: Architect: SRINIVASAN R; Engineer: KISHORE KUMAR; Chartered Accountant: A.S. SREEKANTH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CANDADE KAY ARR SIGNATURE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback