Home / Browse projects / Bengaluru Urban, Karnataka / CAMELLIA VITAL
CAMELLIA VITAL
RG-KA-46588 · RERA PRM/KA/RERA/1251/446/PR/300926/008983 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
CAMELLIA VITAL is a Residential/Group Housing project by Camellia Infrastructures in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/300926/008983 on 30 Sep 2026. Possession is promised by 15 Mar 2028. 0 of the 24 units on this registration are recorded sold or booked, and 4 of 16 construction stages are filed complete.
At a glance
Project
- NameCAMELLIA VITAL
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560087
- Pincode560087
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/300926/008983
- ReraGenie IDRG-KA-46588
Builder
- NameCamellia Infrastructures
- Entity typePartnership Firm
- GSTIN29AAGFC4959G2Z3
- Authorized SignatorySridhar Reddy Talamati
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on30 Sep 2026
- Promised completion15 Mar 2028
- Revised completionNone
- Buildings1 building record
- Documents filed88 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Camellia1 | - | - | - | 24 | 0 | 24 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 16 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 60%.
Building: 30% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 60% |
| Masonry Construction | 20% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 10% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 40% |
| Lifts | Yes | 10% |
| Corridor/Lobbies | Yes | 20% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 40% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Sankarsh Rajeev | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 10.00 cr | Rs 2.58 cr |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 50.00 lakh | - |
| Payment of taxes | Rs 40.00 lakh | Rs 18.58 lakh |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 40.00 lakh | Rs 18.58 lakh |
| On-site expenditure-Salaries of workers | Rs 20.00 lakh | Rs 26.52 lakh |
| On-site expenditure-Consultants Fees | Rs 20.00 lakh | Rs 19.72 lakh |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 10.00 lakh | - |
| Payment of charges | Rs 10.00 lakh | - |
| Payment of cess | Rs 7.00 lakh | - |
| On-site expenditure-Site Overhead | Rs 5.00 lakh | - |
| Payment of fees | Rs 5.00 lakh | Rs 17.51 lakh |
| Payment of Premiums | Rs 2.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kumar Ramakrishnappa |
| Engineer | Yella Mallikarjuna |
| Chartered Accountant | Madhusudhana Reddy M |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed88
As listed on the registration, under the names the promoter filed them with; the newest 80 of 88 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/300926/008983 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q2 CA (2).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: arct Form -5 Q2.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2 2026 Form 6 Engineer Certificate.pdf | 14 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| GBA ClarificationFile: GBA letter.pdf | 11 Sep 2026 |
| Conversion not applicableFile: Rera query answer.pdf | 19 Aug 2026 |
| Encumbrance certificateFile: EC 1968 2004.pdf | 19 Aug 2026 |
| Encumbrance certificateFile: EC 2004 2026.pdf | 19 Aug 2026 |
| e - khataFile: e khata.pdf | 19 Aug 2026 |
| Agreement for SaleFile: Agmt For Sale.pdf | 28 Jul 2026 |
| Allottment LetterFile: Allottment Letter.pdf | 28 Jul 2026 |
| Water NOC AffidavitFile: Water NOC Affidavit.pdf | 28 Jul 2026 |
| Changed the land value in the portal which was not matchedFile: Guidance value cert for Land value_compressed.pdf | 28 Jul 2026 |
| Single site layout development not applicableFile: RERA(Camellia Vital)- SRLAW (08 07 2026).pdf | 17 Jul 2026 |
| Building licenceFile: Building Licence.pdf | 17 Jul 2026 |
| Commencement CertificateFile: Commencement Certificate.pdf | 17 Jul 2026 |
| Demarcation of proposed land in master planFile: Demarcation of land on master plan.pdf | 17 Jul 2026 |
| Demarcation of land in village mapFile: demarcation of land on Village map.pdf | 17 Jul 2026 |
| details of facilities and amenitiesFile: Details of Ameneties.pdf | 17 Jul 2026 |
| GBA plan approvel matching survey number with survey sketchFile: GBA - Plan Approval.pdf | 17 Jul 2026 |
| project address Sy.No as per approved planFile: GBA - Plan Approval.pdf | 17 Jul 2026 |
| Bifurcated Flat detailsFile: Flat Area Stmt.pdf | 17 Jul 2026 |
| Agreement for sale with correctionsFile: SALE AGMT- Camellia Vital.pdf | 17 Jul 2026 |
| Allottment letter with possession dateFile: Allottment Letter.pdf | 17 Jul 2026 |
| BESCOM NOCFile: BESCOM NOC.pdf | 17 Jul 2026 |
| Land cost calculation self attested with Guidance value certificateFile: Guidance value cert for Land value_compressed.pdf | 17 Jul 2026 |
| Brief estimated cost of construction certified by registered civil engineerFile: Camellia Vital Breakup Estimate Certificate.pdf | 17 Jul 2026 |
| Drinking Water supply by providing water softening system with bore wellFile: water source.pdf | 17 Jul 2026 |
| designated depositFile: Bank account Affidavit.pdf | 6 Jun 2026 |
| CA certificateFile: CA Registration.pdf | 6 Jun 2026 |
| partner IT returnsFile: PR IT Returns_compressed.pdf | 6 Jun 2026 |
| partner IT returnsFile: TSR IT Returns.pdf | 6 Jun 2026 |
| RTCFile: RTC latest.pdf | 6 Jun 2026 |
| explanation for MR, Conversion, single siteFile: MR, Convertion, single plot.pdf | 6 Jun 2026 |
| ECFile: ECC-02062026.pdf | 6 Jun 2026 |
| Affidavit non - litigationFile: Affidavit Non Litigation.pdf | 6 Jun 2026 |
| building licenceFile: Building Licence.pdf | 6 Jun 2026 |
| survey sketchFile: Survey Sketch.pdf | 6 Jun 2026 |
| original sanction planFile: GBA Approved Plan.pdf | 6 Jun 2026 |
| reason for delay of registrationFile: Reason for delay.pdf | 6 Jun 2026 |
| bifercated flat detailsFile: Flat Area details.pdf | 6 Jun 2026 |
| elaborated structural reportFile: Camellia Vital DBR Report_compressed.pdf | 6 Jun 2026 |
| soil reportFile: Soil Report.pdf | 6 Jun 2026 |
| project specificationsFile: Specifications.pdf | 6 Jun 2026 |
| allotment letter witH annexure A detailsFile: Allottment Letter.pdf | 6 Jun 2026 |
| guidance value certificateFile: Guidence value certificate_compressed.pdf | 6 Jun 2026 |
| water sourceFile: water source.pdf | 6 Jun 2026 |
| cost of construction estimated by reg.civil engineerFile: Form 3 Engineer Certificate.pdf | 6 Jun 2026 |
| amenitiesFile: Amenities.pdf | 6 Jun 2026 |
| STP design reportFile: 20260606130539.pdf | 6 Jun 2026 |
| Registration CertificateFile: Firm Reg 2026.pdf | - |
| GST CertificateFile: GST Certificate.pdf | - |
| Partnership DeedFile: Partenership deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: Form 2 Architect certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Form 3 Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit Non Litigation.pdf | - |
| Balance Sheet 2024 - 2025File: IT RETURNS2025-26.pdf | - |
| Balance Sheet 2023 - 2024File: IT RETURNS 2024-25.pdf | - |
| Balance Sheet 2022 - 2023File: IT RETURNS 2023-24.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: IT RETURNS2025-26.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: IT RETURNS 2024-25.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: IT RETURNS 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: IT RETURNS2025-26.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: IT RETURNS 2024-25.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: IT RETURNS 2023-24.pdf | - |
| GBA Approved Plan | - |
| GBA Approved Plan | - |
| Structural Stability Certificate | - |
| Camellia Vital Project Specifications | - |
| Camellia Vital Brochure | - |
| SALE AGMT | - |
| AllotmentLetter | - |
| Form B Affidavit cum declaration | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep CAMELLIA VITAL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 35 registered projects within 2 km.
Prestige Lavender Fields
Prestige Office Ventures
Brigade Sanctuary
Brigade Enterprises Ltd
MYHNA VISTARA
MYHNA PROPERTIES PRIVATE LIMITED
ABHEE AARIA
ABHEE VENTURES PRIVATE LIMITED
ABHEE CITY URBAN GLENN PHASE II
ABHEE VENTURES PRIVATE LIMITED
GODREJ PARK RETREAT
Godrej Properties Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Camellia Infrastructures
Camellia Infrastructures has 2 registrations on RERA Karnataka, including CAMELLIA PRIDE and CAMELLIA VITAL. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if CAMELLIA VITAL is delayed beyond 15 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of CAMELLIA VITAL?
The registered promoter entity is Camellia Infrastructures, a partnership firm as per the filing. Its GSTIN 29AAGFC4959G2Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in CAMELLIA VITAL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at CAMELLIA VITAL?
The professionals named in the filing: Architect: Kumar Ramakrishnappa; Engineer: Yella Mallikarjuna; Chartered Accountant: Madhusudhana Reddy M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CAMELLIA VITAL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback