ReraGenieLog inGet a buyer report

Home / Browse projects / Belagavi, Karnataka / BHANDARE RESIDENCY

Registration approved Residential/Group Housing project

BHANDARE RESIDENCY

By NAVCHAITANYA DEVELOPERS

RG-KA-32155 · RERA PRM/KA/RERA/1249/447/PR/190829/002836 · Last updated on RERA Karnataka portal: 6 Mar 2021

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 50 documents Report an error

BHANDARE RESIDENCY is a Residential/Group Housing project by NAVCHAITANYA DEVELOPERS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/190829/002836 on 29 Aug 2019. Possession is promised by 30 Sep 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameBHANDARE RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Belagavi
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1249/447/PR/190829/002836
  • ReraGenie IDRG-KA-32155

Builder

  • NameNAVCHAITANYA DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryLAXMAN MARUTI NILAJAKAR
  • Board MembersSWAPNIL KALLAPPA NILAJKAR, SUDHAKAR GAJANAN CHAVAN, PRAVEEN BHARMA PATIL, LAXMAN SOMANNA KANABARGI, PUNDALIK MARUTI PATIL
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2019First promiseDec 2021Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Aug 2019
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Dec 2021)
  • Buildings1 building record
  • Documents filed50 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BHANDARE RESEIDENCY---19019

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 6 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 6 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area678 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.11 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARUN NETAJI KURADE
EngineerShrijay Kalghatgi

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2021 → not stated

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed50

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/190829/002836 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA CERTIFICATEFile: QU-CA- 31-12-2020.pdf6 Mar 2021
CertificateFile: REG CER.jpg-
Modified plan details site plan, floor plans, Plan Licence LetterFile: MODIFIED APPROVED PLAN.pdf-
Elevation, Sections, Specifications ( If changes are there )File: MODIFIED APPROVED PLAN.pdf-
Chartered Accountant CertificateFile: CA MODIFICATIONS.pdf-
Notarized AffidavitFile: Affidavit modification.pdf-
Engineer CertificateFile: ENGG MODIFIED CERTIFICATE.pdf-
Architect CertificateFile: ENGG MODIFIED CERTIFICATE.pdf-
Structural Engineer Certificate for stability of structureFile: stability certificate-converted.pdf-
Modification of Plan DetailsFile: PERMISSION PLAN-01.pdf-
Modification of Plan DetailsFile: MODIFIED APROVED PLAN-02.pdf-
Modification of Plan DetailsFile: PERMISSION ORDER LATTER -OLD.pdf-
Modification of Plan DetailsFile: PERMISIION CERTIFICATE.pdf-
ORDER LATTER-
Floor Plan Apartment-
sale of deed_0001-converted-compressed-
scan1638-
scan1638-
SALE OF DEED-
Floor Plan Apartment-
Floor Plan Apartment-
ORDER LATTER_compressed-
APARTMENT-
NOC RERA-
DETAILED SPECIFICATION-
ENCOMBRANCE CERTIFICATE_compressed-
AFFIDAVIT-
AFFIDAVIT CUM DECALARATION-
CTS COPY-
DEVELOPMENT AGREEMENT_compressed-
rera recipt-
scan1638-
scan1638-
Balance Sheet 2017 - 2018File: PNL_compressed (1).pdf-
Audited Profit and Loss Statement 2017 - 2018File: PNL_compressed (1).pdf-
FORM B_compressed (1)-
Prospectus/BrochureFile: BHANDARE RESIDENCY BROCHER.pdf-
Advertisement Copy 1File: ADVERTISEMENT.jpg-
Tower Excel SheetFile: PRMKARERA1249447PR190829002836.xlsx-
Loan raised documentFile: LOAN DOCUMENTS_compressed.pdf-
Stability CertificateFile: stability certificate-converted.pdf-
Occupancy CertificateFile: COMPLITION AND OCCUPANCY.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: LIFT LICENCE.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Electrical Certificate.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: city coroporation water supply.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: architect complition certificate form no-04.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: architect complition certificate form no-04.pdf-
Architect certificate for having completed the work(in format no 5)File: architect complition certificate form no-04.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA CERT 31032021.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFIDAVIT.pdf-

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one moved by 9 months
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep BHANDARE RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

2 kmBHANDARE RESIDENCYOther 64Dot size: filed unitsN

Filed coordinates, straight-line distance. 64 registered projects within 2 km.

Builder: NAVCHAITANYA DEVELOPERS

NAVCHAITANYA DEVELOPERS has 3 registrations on RERA Karnataka, including NAVCHAITANYA RESIDENCY and BHANDARE RESIDENCY. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if BHANDARE RESIDENCY is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of BHANDARE RESIDENCY?

The registered promoter entity is NAVCHAITANYA DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in BHANDARE RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at BHANDARE RESIDENCY?

The professionals named in the filing: Architect: ARUN NETAJI KURADE; Engineer: Shrijay Kalghatgi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHANDARE RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHANDARE RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHANDARE RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.