RG-KA-56428 · RERA PRM/KA/RERA/1272/394/PR/260825/008036 · Last updated on RERA Karnataka portal: 14 Aug 2025
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
B KRISHNAIAH ENCLAVE is a Plotted Development project by RUKMINAMMA in Tumakuru, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1272/394/PR/260825/008036 on 26 Aug 2025. Possession is promised by 31 Dec 2030.
At a glance
Project
- NameB KRISHNAIAH ENCLAVE
- TypePlotted Development
- Location
- Tumakuru
- PincodeNot stated
- RERA no.PRM/KA/RERA/1272/394/PR/260825/008036
- ReraGenie IDRG-KA-56428
Builder
- NameRUKMINAMMA
- Entity typeOther ( INDIVIDUAL LAND OWNER )
- Authorized SignatoryRUKMINAMMA
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on26 Aug 2025
- Promised completion31 Dec 2030
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed75 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RUKMINAMMA | - | - |
| RUKMINAMMA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 1.06 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | R G YEDAMALE |
| Chartered Accountant | SUPRIYA B |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed75
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1272/394/PR/260825/008036 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| AFFIDAVIT BANK for RERAFile: AFFIDAVIT BANK.pdf | 14 Aug 2025 |
| CDP PLAN demarcatedFile: CDP PLAN demarcated.pdf | 14 Aug 2025 |
| CONVERSION ORDERFile: CONVERSION ORDER.pdf | 14 Aug 2025 |
| DRAFT AGREEMENT FOR SALE NEW FORMAT - KA RERA - B KRISHNAIAH ENCLAVEFile: DRAFT AGREEMENT FOR SALE NEW FORMAT - KA RERA - B KRISHNAIAH ENCLAVE.pdf | 14 Aug 2025 |
| DRAFT ALLOTMENT LETTER NEW FORMAT - KA RERA - B KRISHNAIAH ENCLAVEFile: DRAFT ALLOTMENT LETTER NEW FORMAT - KA RERA - B KRISHNAIAH ENCLAVE.pdf | 14 Aug 2025 |
| ELECTRICAL NOCFile: ELECTRICAL NOC.pdf | 14 Aug 2025 |
| ENGR REG Self Attested Copy of AMIE & CHARTERED ENGINEER CERTIFICATEFile: ENGR REG Self Attested Copy of AMIE & CHARTERED ENGINEER CERTIFICATE.pdf | 14 Aug 2025 |
| F1 CA - REGISTRATION - RUKMINAMMA_signedFile: F1 CA - REGISTRATION - RUKMINAMMA_signed.pdf | 14 Aug 2025 |
| APPROVED LAYOUT PLAN - GULUR TUMKUR TUDA PLANFile: GULUR TUMKUR TUDA PLAN.PDF | 14 Aug 2025 |
| MUTATION EXTRACT MR & KHATHA TRANSFERFile: MUTATION EXTRACT MR & KHATHA TRANSFER.pdf | 14 Aug 2025 |
| MR for both Sy No.sFile: MR.pdf | 14 Aug 2025 |
| Networth Declaration RUKMINAMMAFile: Networth Declaration RUKMINAMMA.pdf | 14 Aug 2025 |
| NOC ELECTRICALFile: NOC ELECTRICAL.pdf | 14 Aug 2025 |
| NOC PANCHAYATHFile: NOC PANCHAYATH.pdf | 14 Aug 2025 |
| PANCHAYATH NOCFile: PANCHAYATH NOC.pdf | 14 Aug 2025 |
| PLAN APPROVAL LETTERFile: PLAN APPROVAL LETTER.pdf | 14 Aug 2025 |
| RECENT EC for both Sy No.sFile: RECENT EC.pdf | 14 Aug 2025 |
| RECENT RTC for both Sy No.sFile: RECENT RTC.pdf | 14 Aug 2025 |
| RWSSB NOCFile: RWSSB NOC.pdf | 14 Aug 2025 |
| SALE DEED to RUKMINAMMA Husband with FAMILY TREE & DEATH CERTIFICATEFile: SALE DEED to RUKMINAMMA Husband with FAMILY TREE & DEATH CERTIFICATE.pdf | 14 Aug 2025 |
| STP DRAWINGS with Project Details & Engineer SignFile: STP DRAWINGS with Project Details & Engineer Sign.pdf | 14 Aug 2025 |
| SURVEY SKETCH OLDFile: SURVEY SKETCH OLD.pdf | 14 Aug 2025 |
| NEW SURVEY SKETCH signed copyFile: SURVEY SKETCH signed copy.pdf | 14 Aug 2025 |
| TUDA WORK ORDERFile: TUDA WORK ORDER.pdf | 14 Aug 2025 |
| Tumkur ZR CopyFile: Tumkur ZR Copy.pdf | 14 Aug 2025 |
| VILLAGE MAP demarcatedFile: VILLAGE MAP demarcated.pdf | 14 Aug 2025 |
| WATER NOC PANCHAYATHFile: WATER NOC PANCHAYATH.pdf | 14 Aug 2025 |
| RTC, survey 129/1 | - |
| Mutation, survey 129/1 | - |
| Encumbrance Certificate, survey 129/1 | - |
| Conversion/Alienation Order, survey 129/1 | - |
| Sale/Title/Gift Deed, survey 129/1 | - |
| Khatha, survey 129/1 | - |
| RTC, survey 129/5 | - |
| Mutation, survey 129/5 | - |
| Encumbrance Certificate, survey 129/5 | - |
| Conversion/Alienation Order, survey 129/5 | - |
| Sale/Title/Gift Deed, survey 129/5 | - |
| Khatha, survey 129/5 | - |
| GST Certificate | - |
| Certificate issued by CA Form 1File: F1 CA - REGISTRATION - RUKMINAMMA_signed.pdf | - |
| Certificate issued by Engineer Form 3File: F3 ENGR - REGISTRATION - RUKMINAMMA_signed copy.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: AFFIDAVIT NON LITIGATION.pdf | - |
| Balance Sheet 2023 - 2024File: PAN.pdf | - |
| Balance Sheet 2022 - 2023File: PAN.pdf | - |
| Balance Sheet 2021 - 2022File: PAN.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: PAN.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: PAN.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: PAN.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: PAN.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: PAN.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: PAN.pdf | - |
| PLAN LETTER | - |
| GULUR TUMKUR TUDA PLAN | - |
| Project Specifications - RUKMINAMMA | - |
| AFFIDAVIT FORM B | - |
| AFFIDAVIT SECTION 3 | - |
| LAWYER LEGAL OPINION | - |
| NOC ELECTRICAL | - |
| NOC PANCHAYATH | - |
| Unnamed document | - |
| Unnamed document | - |
| NOC PANCHAYATH | - |
| NOC PWD | - |
| TUDA WORK ORDER | - |
| ABSTRACT ESTIMATE | - |
| CDP PLAN | - |
| F6 ENGR - REGISTRATION - RUKMINAMMA_signed copy | - |
| Guidance Value signed by Promoter - RUKMINAMMA | - |
| STP DRAWING | - |
| VILLAGE MAP | - |
| AKARBAND TIPPANI & OTHER SURVEY DOCUMENTS | - |
| Plot Excel SheetFile: B KRISHNAIAH ENCLAVE.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Tumakuru
Computed across the 220+ Tumakuru projects on ReraGenie, from their own filings.
Keep B KRISHNAIAH ENCLAVE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tumakuru220+ in Tumakuru
Swarna Griha - 2
FELICITY ADOBE LLP
Sairam Asare
Sairam Housing Project
Swarna Griha
Tumkur Nivas LLP
A J MAJID GARDEN
ABDUL MAJID, MOHSIN AHAMED AND MUJAHID AHA
A J S ENCLAVE
ASHOK BHATI, SESHA RAM C AND JAGADISH RATH
A R LAYOUT
NOOR JAHAN AHMED
See every Tumakuru project, with the district possession charts
Builder: RUKMINAMMA
RUKMINAMMA has 1 registration on RERA Karnataka, including B KRISHNAIAH ENCLAVE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Tumakuru district page.
Frequently asked questions
What are my rights if B KRISHNAIAH ENCLAVE is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of B KRISHNAIAH ENCLAVE?
The registered promoter entity is RUKMINAMMA, an other ( individual land owner ) as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in B KRISHNAIAH ENCLAVE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at B KRISHNAIAH ENCLAVE?
The professionals named in the filing: Engineer: R G YEDAMALE; Chartered Accountant: SUPRIYA B. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in B KRISHNAIAH ENCLAVE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback