Axis Niran

By Axis Concept Construction Pvt Ltd

RG-KA-62012 · RERA PRM/KA/RERA/1251/308/PR/161225/008341 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2028Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 90%
36 of 49Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 106 documents Report an error

Axis Niran is a Residential/Group Housing project by Axis Concept Construction Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/161225/008341 on 16 Dec 2025. Possession is promised by 30 Sep 2028. 13 of the 49 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameAxis Niran
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/161225/008341
  • ReraGenie IDRG-KA-62012

Builder

  • NameAxis Concept Construction Pvt Ltd
  • Entity typeCompany
  • CINU45201KA2007PTC043841
  • GSTIN29AAHCA0685P1Z1
  • Authorized SignatoryR HARISH BABU
  • Managing DirectorR HARISH BABU
  • DirectorsR HARISH BABU, A N Jayanthi
  • Project HeadNava Kishore Tulimalli
  • Other registrations4 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredDec 2025PromisedSep 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Dec 2025
  • Promised completion30 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed106 files

Current status

27%13 of 49 units booked
9.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Axis Niran---49049

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 90%.

Building: 18% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work90%
Foundation footing work85%
Upto Plinth Level80%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes5%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes25%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes5%
LiftsYes5%
Corridor/LobbiesYes1%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,046 sq m
Named landowners4
LandownerVillageDistrict
B. SAVITHRI--
MADHUSUDAN V--
DIVYA CHETANA G V--
G VENKATESH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 22.90 cr
Cost incurredRs 2.25 cr
Spent of the estimate9.81%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 22.51 crRs 2.11 cr
On-site expenditure-Consultants FeesRs 39.01 lakhRs 13.42 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVEENA H
EngineerJAFAR IMAM SAJID
Chartered AccountantG. Pattabhi Reddy

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed106

As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/161225/008341 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Axis Niran.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Niran Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Niran Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Axis Niran Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Axis Niran Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Axis Niran Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_CA_Certificate.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5_Architect_Certificate.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6_Engineer_Certificate.pdf14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 NIRAN Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 NIRAN Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 NIRAN Q3 25-26.pdf15 Jan 2026
Plan Sanctions [Color] NiranFile: 1 Plan Sanctions [Color] Niran.pdf15 Dec 2025
Commencement Certificate - NiranFile: 2 Commencement Certificate - Niran.pdf15 Dec 2025
Niran_Amenities_Common Area DetailsFile: 4 Niran_Amenities_Common Area Details.pdf15 Dec 2025
NIran_Unit Area details-Architect-SignedFile: 5 NIran_Unit Area details-Architect-Signed.pdf15 Dec 2025
Niran_Form-3-Engineer signedFile: 6 Niran_Form-3-Engineer signed.pdf15 Dec 2025
Niran_Stability Certificate-EngineerFile: 7 Niran_Stability Certificate-Engineer.pdf15 Dec 2025
Proforma Allotment Letter - NiranFile: 8 Proforma Allotment Letter - Niran.pdf15 Dec 2025
Proforma Sale Agreement - NiranFile: 9 Proforma Sale Agreement - Niran.pdf15 Dec 2025
Clarification on Building License NiranFile: 10 Clarification on Building License Niran.pdf15 Dec 2025
Axis Niran STP DrawingFile: 11 Axis Niran STP Drawing.pdf15 Dec 2025
GPA NiranFile: GPA Niran.pdf15 Dec 2025
Land cost calculation - Axis NiranFile: 1 Land cost calculation - Axis Niran.pdf22 Sep 2025
Village map demarcated-NiranFile: 3 Village map demarcated-Niran.pdf22 Sep 2025
CLU CopyFile: 4 CLU Copy.pdf22 Sep 2025
CDP Demarcation BMRDAFile: 5 CDP Demarcation BMRDA.pdf22 Sep 2025
Proforma Sale Agreement - NiranFile: 1 Proforma Sale Agreement - Niran.pdf14 Aug 2025
Proforma Allotment Letter - NiranFile: 2 Proforma Allotment Letter - Niran.pdf14 Aug 2025
LAND COST CALCULATION SHEETFile: 3 LAND COST CALCULATION SHEET.pdf14 Aug 2025
RTC, survey 60-
Mutation, survey 60-
Encumbrance Certificate, survey 60-
Conversion/Alienation Order, survey 60-
Sale/Title/Gift Deed, survey 60-
JDA, survey 60-
Khatha, survey 60-
Registration CertificateFile: Certificate of Incorporation.pdf-
Memorandum of AssociationFile: MOA.pdf-
Article of AssociationFile: AOA.pdf-
GST CertificateFile: GST CERTIFICATE - Axis concept.pdf-
Organization StructureFile: Organizational Chart Axis.pdf-
Certificate issued by CA Form 1File: Form 1 CA Cert - Niran.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificates.pdf-
Certificate issued by Engineer Form 3File: Niran_Form-3-Engineer signed.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation Affidavit.pdf-
Balance Sheet 2023 - 2024File: Axis Concept Financials FY 2023-24.pdf-
Balance Sheet 2022 - 2023File: 3 Balance Sheet 202223.pdf-
Balance Sheet 2021 - 2022File: 1 Balance Sheet FY 202122.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Axis Concept Financials FY 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: 5 Profit and Loss FY 202223.pdf-
Audited Profit and Loss Statement 2021 - 2022File: 2 Profit and Loss FY 202122.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Axis Concept Financials FY 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: 7 ITR ACK 202223.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: 3 ITR FY 202122.pdf-
Director's Report 2023 - 2024File: Boards Report Axis Concept - 2024.pdf-
Director's Report 2022 - 2023File: 1 Board Report FY 202223.pdf-
Director's Report 2021 - 2022File: 5 Boards Report FY 202122.pdf-
Cash Flow Statement 2023 - 2024File: Axis Concept Financials FY 2023-24.pdf-
Cash Flow Statement 2022 - 2023File: 4 Cashflow Statement FY 202223.pdf-
Auditor's Report 2023 - 2024File: Axis Concept Financials FY 2023-24.pdf-
Auditor's Report 2022 - 2023File: 2 Audit report FY 202223.pdf-
Auditor's Report 2021 - 2022File: 4 Audit report FY 202122.pdf-
Axis Niran - RERA_Engineer_Stability Certificate-
Project specifications - RERA Niran-
Proforma Sale Agreement - Niran-
Proforma Allotment Letter - Niran-
Form B Affidavit - Axis Niran-
Sec 3(1) Affidavit - Axis Niran-
JDA Affidavit-
Legal Opinion-

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 under way, not due yet3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
AXIS AMARISSASy. No. 288/1 (Old Survey No. 132), Village Panchayath Khatha No. 288/1 , E-Khata No. 150200302202001256, Kanakapura Road, Badamanavarthe Kaval Village (B.M. Kaval) , Bengaluru South , Bengaluru Urban, Karnataka -OngoingDec 2029Not due yet
AXIS OAKLYNSy No 46(P) in Sonnappanahalli Village, Jala Hobli , Yelahanka Taluk , Yelahanka , Bengaluru Urban, Karnataka - 562157OngoingMar 2027Not due yet
BOCHS AkshayaSy No.24,Begur Village, Begur Hobli, , Bangalore South , Bengaluru South , Bengaluru UrbanCompleted-No date filed
Axis VanamSy No 127/A,Katha No - 111/127/A, Kothanur Village, Uttarahalli Hobli,Completed-No date filed
AXIS ANTARAKatha No 106, Sy 27/1 and 27/2, yelenahalli villageCompleted-No date filed

How this compares with Bengaluru Urban

27%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Axis Niran on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAxis NiranOther 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 48 registered projects within 2 km.

Builder: Axis Concept Construction Pvt Ltd

Axis Concept Construction Pvt Ltd has 5 registrations on RERA Karnataka, including Axis Niran and Axis Vanam. Its filings declare 7 earlier projects, 5 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Axis Niran is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Axis Niran?

The registered promoter entity is Axis Concept Construction Pvt Ltd, a company as per the filing. Its CIN U45201KA2007PTC043841 and GSTIN 29AAHCA0685P1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Axis Niran?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Axis Niran?

The professionals named in the filing: Architect: VEENA H; Engineer: JAFAR IMAM SAJID; Chartered Accountant: G. Pattabhi Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Axis Niran?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Axis Niran. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Axis Niran to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.