Home / Browse projects / Bengaluru Urban, Karnataka / ARS ZURICH PHASE-2

Registration approved No litigation declared Residential/Group Housing project

ARS ZURICH PHASE-2

By ARS INFRAA

RG-KA-13496 · RERA PRM/KA/RERA/1251/308/PR/050225/007482

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jump to the 106 documents Report an error

ARS ZURICH PHASE-2 is a Residential/Group Housing project by ARS INFRAA in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/050225/007482 on 5 Feb 2025. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameARS ZURICH PHASE-2
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/050225/007482
  • ReraGenie IDRG-KA-13496

Builder

  • NameARS INFRAA
  • Entity typePartnership Firm
  • GSTIN29ABQFA3420K1Z7
  • Authorized SignatorySURINENI PRASAD NAIDU
  • Other registrations3 more →

Key dates

this monthRegisteredFeb 2025PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Feb 2025
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed106 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RIVA---1280128
ZIVA---1280128

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership11

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,091 sq m
Named landowners11
LandownerVillageDistrict
GOPAL REDDY M--
AMRISH REDDY H--
SRINIVAS REDDY--
ARS INFRAA--
NAGAMMA--
SUMA RANI.S.H--
SUMA RANI S H--
GOVINDA REDDY S K--
ARS INFRAA--
NAGAMMA--
GOPAL REDDY M--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 138.00 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 138.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAMESH BABU J P
EngineerRAMESG D B
Chartered AccountantVINUTH HEGDE AND CO

Documents filed106

As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/050225/007482 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RTC, survey 104/2-
Mutation, survey 104/2-
Encumbrance Certificate, survey 104/2-
Conversion/Alienation Order, survey 104/2-
JDA, survey 104/2-
Khatha, survey 104/2-
RTC, survey 104/3-
Mutation, survey 104/3-
Encumbrance Certificate, survey 104/3-
Conversion/Alienation Order, survey 104/3-
JDA, survey 104/3-
Khatha, survey 104/3-
RTC, survey 104/5-
Mutation, survey 104/5-
Encumbrance Certificate, survey 104/5-
Conversion/Alienation Order, survey 104/5-
JDA, survey 104/5-
Khatha, survey 104/5-
RTC, survey 104/6-
Mutation, survey 104/6-
Encumbrance Certificate, survey 104/6-
Conversion/Alienation Order, survey 104/6-
Sale/Title/Gift Deed, survey 104/6-
Khatha, survey 104/6-
RTC, survey 104/7-
Mutation, survey 104/7-
Encumbrance Certificate, survey 104/7-
Conversion/Alienation Order, survey 104/7-
JDA, survey 104/7-
Khatha, survey 104/7-
RTC, survey 104/8-
Mutation, survey 104/8-
Encumbrance Certificate, survey 104/8-
Conversion/Alienation Order, survey 104/8-
JDA, survey 104/8-
Khatha, survey 104/8-
RTC, survey 104/9-
Mutation, survey 104/9-
Encumbrance Certificate, survey 104/9-
Conversion/Alienation Order, survey 104/9-
JDA, survey 104/9-
Khatha, survey 104/9-
RTC, survey 104/10-
Mutation, survey 104/10-
Encumbrance Certificate, survey 104/10-
Conversion/Alienation Order, survey 104/10-
JDA, survey 104/10-
Khatha, survey 104/10-
RTC, survey 104/11-
Mutation, survey 104/11-
Encumbrance Certificate, survey 104/11-
Conversion/Alienation Order, survey 104/11-
Sale/Title/Gift Deed, survey 104/11-
Khatha, survey 104/11-
RTC, survey 104/12-
Mutation, survey 104/12-
Encumbrance Certificate, survey 104/12-
Conversion/Alienation Order, survey 104/12-
JDA, survey 104/12-
Khatha, survey 104/12-
RTC, survey 104/13-
Mutation, survey 104/13-
Encumbrance Certificate, survey 104/13-
Conversion/Alienation Order, survey 104/13-
JDA, survey 104/13-
Khatha, survey 104/13-
Registration CertificateFile: Registration certificate 5 (1).pdf-
GST CertificateFile: ARS INFRAA 3.pdf-
Partnership DeedFile: PARTNERSHIP DEED (2).pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form-1 Zurich Phase 2.pdf-
Certificate issued by Architect Form 2File: rera registration Form 2 (1) (1).pdf-
Certificate issued by Engineer Form 3File: rera registration Form 3 (1).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: non litigation (2).pdf-
Balance Sheet 2023 - 2024File: INFRAA - Financials AY-23-24.pdf-
Balance Sheet 2022 - 2023File: ARSFinancialsFY 2223.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ARS ZURICH PHASE-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmARS ZURICH PHASE-2Other 84Dot size: filed unitsN

Filed coordinates, straight-line distance. 84 registered projects within 2 km.

Builder: ARS INFRAA

ARS INFRAA has 4 registrations on RERA Karnataka, including ARS ZURICH PHASE-2 and ARS ZURICH PHASE-1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ARS ZURICH PHASE-2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ARS ZURICH PHASE-2?

The registered promoter entity is ARS INFRAA, a partnership firm as per the filing. Its GSTIN 29ABQFA3420K1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ARS ZURICH PHASE-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ARS ZURICH PHASE-2?

The professionals named in the filing: Architect: RAMESH BABU J P; Engineer: RAMESG D B; Chartered Accountant: VINUTH HEGDE AND CO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARS ZURICH PHASE-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARS ZURICH PHASE-2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARS ZURICH PHASE-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.