Home / Browse projects / Belagavi, Karnataka / ARINJAY EMPIRE

Registration approved No litigation declared Residential/Group Housing project

ARINJAY EMPIRE

By ARINJAY CONSTRUCTIONS

RG-KA-78187 · RERA PRM/KA/RERA/1249/447/PR/161123/006412 · Last updated on RERA Karnataka portal: 2 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2026Possession promisedno revision filed
14 of 14Construction stages doneevery applicable stage filed complete
5 of 24Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 112 documents Report an error

ARINJAY EMPIRE is a Residential/Group Housing project by ARINJAY CONSTRUCTIONS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/161123/006412 on 16 Nov 2023. Possession is promised by 15 Aug 2026. 19 of the 24 units on this registration are recorded sold or booked, and 14 of 14 construction stages are filed complete.

At a glance

Project

  • NameARINJAY EMPIRE
  • TypeResidential/Group Housing
  • Location
    • Belagavi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1249/447/PR/161123/006412
  • ReraGenie IDRG-KA-78187

Builder

  • NameARINJAY CONSTRUCTIONS
  • Entity typePartnership Firm
  • GSTIN29ACAFA9817D1ZF
  • Authorized SignatoryTEJAS ARJUN MOHANDAS

Key dates

this monthRegisteredNov 2023PromisedAug 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Nov 2023
  • Promised completion15 Aug 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed112 files

Current status

79%19 of 24 units booked
89.2%Of the estimated cost spent so far

Figures as on 2 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ARINJAY EMPIRE---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 2 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 14 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 2 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes70%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes90%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners9
LandownerVillageDistrict
VISHWANATH NARYAN REVANKAR--
GOUTAM VISHNU RAIKAR--
SATYAM VISHNU RAIKAR--
ARUN VASUDEV DESURKAR--
SAVITA ARUN DESURKAR--
RAJABHAU VASUDEV DESURKAR--
ANURADHA RAJABHAU DESURKAR--
PRANAV RAJARAM DESURKAR--
BHASKAR RAJABHAU DESURKAR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.17 cr
Cost incurredRs 3.72 cr
Spent of the estimate89.23%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 3.79 crRs 3.37 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 27.50 lakh-
On-site expenditure-Consultants FeesRs 10.00 lakhRs 18.53 lakh
Payment of taxes-Rs 16.23 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShrutika L Waghmare
EngineerVINAY BEHERE
Chartered AccountantSANDEEP S KAJUKAR

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed112

As listed on the registration, under the names the promoter filed them with; the newest 80 of 112 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/161123/006412 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Scan.pdf2 Jul 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHITECT Q3 2025.pdf2 Jul 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENGINEERS Q3 2025.pdf2 Jul 2026
Q3 2025-26 Water supply and sewage board2 Jul 2026
Q3 2025-26 Engineering Department (PWD) for completion of development works2 Jul 2026
Q3 2025-26 KPTCL- BESCOM2 Jul 2026
Clarification of Portion of Joint Development LandFile: Portion of joint development land.pdf28 Oct 2023
Clarification of Sources of fundsFile: Source of fund Clarification.pdf28 Oct 2023
Annexure 1 Firm BSFile: annexure 1-firm BS.pdf28 Oct 2023
Annexure 2 Arjun Mohandas BSFile: annexure 2-arjun mohandas BS.pdf28 Oct 2023
Annexure 3 Tejas Mohandas BSFile: annexure 3-tejas mohandas BS.pdf28 Oct 2023
Annexure 4 Sanction LetterFile: annexure 4 sanction letter.pdf28 Oct 2023
Sources of Funds to Complete the Project with the Supporting documentsFile: Source of Funds.pdf18 Oct 2023
Uploaded the Architects details with Valid COA NumberFile: Council of Architects.pdf18 Oct 2023
Uploaded Commencement CertificateFile: commencement certificate.pdf18 Oct 2023
Source of Funds with Supporting DocumentsFile: SOURCE OF FUNDS.pdf15 Sep 2023
Profit an Loss and Balance SheetFile: P&L BS 22-23.pdf15 Sep 2023
Area DetailsFile: Area Details.pdf15 Sep 2023
Certified Area CalculationFile: Ceritified Area Calculation.pdf15 Sep 2023
CDP Map With Proposed SiteFile: CDP map.pdf15 Sep 2023
Architect Details With Valid Coa NumberFile: Architects details.pdf15 Sep 2023
Commencement CertificateFile: Commencemnt Certificate (1).pdf15 Sep 2023
Project EngineerFile: engineer licesense.pdf15 Sep 2023
Project Engineer Adhar CardFile: Adhar Card.pdf15 Sep 2023
Engineer CertificateFile: Engineer certificate certified.pdf15 Sep 2023
Agreement For SaleFile: Agreement of sale draft.pdf15 Sep 2023
Allotment of LetterFile: Proforma of allotment letter.pdf15 Sep 2023
PROFIT AND LOSSFile: profit and loss scan final.pdf24 Aug 2023
Bank Account as per Direction CircularFile: Bank Account.pdf24 Aug 2023
Source of FundsFile: Source of Funds.pdf24 Aug 2023
Agreement Of AuthorizationFile: POA.pdf24 Aug 2023
Registered Patnership DeedFile: Patnership Deed.pdf24 Aug 2023
Mother Deed of English 1920/BFile: 1920B English Agreement.pdf24 Aug 2023
Form BFile: FormB.pdf24 Aug 2023
Affadavit JD Cum DFile: affidavit cum declaration.pdf24 Aug 2023
Project Details as Sanctioned PlanFile: architect calc.pdf24 Aug 2023
Break up of Types of UnitFile: architect calc.pdf24 Aug 2023
Certified Carpet Area CalculationFile: architect calc.pdf24 Aug 2023
CDP Map Showing LocationFile: cdp map.pdf24 Aug 2023
Village Map 1920/AFile: 1920 A cts map.pdf24 Aug 2023
Village Map 1920/BFile: 1920B cts map.pdf24 Aug 2023
Village Map 1921File: 1921 cts map.pdf24 Aug 2023
Village Map 1922File: 1922 cts map.pdf24 Aug 2023
Architect Details With Valid COA NumberFile: architect liscense.pdf24 Aug 2023
Commencement CertifiacteFile: commencemnt order.pdf24 Aug 2023
Amalgation OrderFile: Amalgation order.pdf24 Aug 2023
Common Area Alloted Association and No.of ParkingFile: architect calc.pdf24 Aug 2023
Ammenities and Common Area Details As Per SanctionedFile: Specifications.pdf24 Aug 2023
Engineer LicenseFile: engineer licesense.pdf24 Aug 2023
Brief Estimated Cost Certified By EngineerFile: Estimation of Engineers.pdf24 Aug 2023
NOC OF power Supply With RecieptFile: HESCOM NOC.pdf24 Aug 2023
STP Certified With EngineerFile: Stp Drawing.pdf24 Aug 2023
Specifaction Certified By EngineerFile: Specifications.pdf24 Aug 2023
Notarized Affadavit 3(1)File: Affidavit3(1).pdf24 Aug 2023
AffadavitFile: Affidavit2.pdf24 Aug 2023
Land Calculation as per Guidance ValueFile: Guidance Value.pdf24 Aug 2023
Profoma of Allotment LetterFile: Proforma of allotment letter.pdf24 Aug 2023
Agreement of SaleFile: Agreement of sale draft.pdf24 Aug 2023
Registration CertificateFile: Registration of firm.pdf-
Partnership DeedFile: Patnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1.pdf-
Certificate issued by Architect Form 2File: form 2.pdf-
Certificate issued by Engineer Form 3File: form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit2.pdf-
Certificate from Chartered AccountFile: form 1.pdf-
Balance Sheet 2021 - 2022File: balance sheet.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Arinjay ITR Acknolodgement.pdf-
Director's Report 2021 - 2022File: computation.pdf-
Cash Flow Statement 2021 - 2022File: cash flow statement.pdf-
Auditor's Report 2021 - 2022File: audit report.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: Arinjay ITR Acknolodgement.pdf-
Sanctioned Letter (1)-
HESCOM NOC-
Water Noc-
Sanctioned plan-

How this compares with Belagavi

79%of this project is bookeddistrict median 39%
24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep ARINJAY EMPIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

Builder: ARINJAY CONSTRUCTIONS

ARINJAY CONSTRUCTIONS has 1 registration on RERA Karnataka, including ARINJAY EMPIRE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if ARINJAY EMPIRE is delayed beyond 15 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ARINJAY EMPIRE?

The registered promoter entity is ARINJAY CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29ACAFA9817D1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ARINJAY EMPIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ARINJAY EMPIRE?

The professionals named in the filing: Architect: Shrutika L Waghmare; Engineer: VINAY BEHERE; Chartered Accountant: SANDEEP S KAJUKAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARINJAY EMPIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARINJAY EMPIRE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARINJAY EMPIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.