Home / Browse projects / Bengaluru Urban, Karnataka / Aradhra

Registration approved No litigation declared Residential/Group Housing project

Aradhra

By Adish Properties

RG-KA-05931 · RERA PRM/KA/RERA/1251/308/PR/130622/004973 · Last updated on RERA Karnataka portal: 17 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Jan 2026Possession promisedmoved 12 months from the original
15 of 18Construction stages donefurthest along: Painting, 98%
26 of 56Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 86 documents Report an error

Aradhra is a Residential/Group Housing project by Adish Properties in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/130622/004973 on 13 Jun 2022. Possession is promised by 31 Jan 2026. The completion date has moved by 12 months from the original filing. 30 of the 56 units on this registration are recorded sold or booked, and 15 of 18 construction stages are filed complete.

At a glance

Project

  • NameAradhra
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562107
  • Pincode562107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/130622/004973
  • ReraGenie IDRG-KA-05931

Builder

  • NameAdish Properties
  • Entity typeProprietorship Firm
  • GSTIN29AVFPK4908F1ZI
  • Authorized SignatoryNitin G Karkikar

Key dates

this monthRegisteredJun 2022First promiseJan 2025Revised toJan 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Jun 2022
  • Promised completion31 Jan 2026
  • Revised completionRevised to 31 Jan 2026 (originally 31 Jan 2025)
  • Buildings3 building records
  • Documents filed86 files

Current status

54%30 of 56 units booked
121.5%Of the estimated cost spent so far

Figures as on 17 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ashwini---28028
ROHINI---16016
SHRAVANA---12012

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 17 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 18 construction stages are filed complete. The stage furthest along is Painting, at 98%.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting98%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)98%
Wardrobe, Showcase, Kitchen cabinet, Puja work98%
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 17 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes95%
Street LightingYes95%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes80%
Club HouseYes80%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes60%
GymYes100%
ParksYes60%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallYes90%
Open parking areasYes90%
Provision for lodging of management staff and security staffYes90%
Water conservation and renewable energyYes100%
Common storage spacesYes100%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,046 sq m
Named landowners2
LandownerVillageDistrict
Vasanthkumar N--
H.Gowramma W/o. Late Nagappa--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 15.00 cr
Cost incurredRs 18.22 cr
Spent of the estimate121.47%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 15.00 crRs 18.22 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNameet Vivek Shirali
EngineerBhagya Lakshmi RC
Chartered AccountantPrasanna Adiga

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/308/PR/250118/004973Jan 2025 → Jan 2026

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed86

As listed on the registration, under the names the promoter filed them with; the newest 80 of 86 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/130622/004973 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4_202526_Q3_CA.pdf17 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-6_202526_Q3_Engg.pdf17 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-5_202526_Q3_Arch.pdf17 Jan 2026
Q3 2025-26 Water supply and sewage board17 Jan 2026
Q3 2025-26 KPTCL- BESCOM17 Jan 2026
Q3 2025-26 Labour and Education Department17 Jan 2026
Commencement certificateFile: Commencement Certificate.pdf1 Jan 2025
Layout sanction orderFile: Layout sanction order.pdf23 May 2022
Balance Sheet 2020-21File: 1 CA UDIN Balance Sheet.pdf6 Apr 2022
Profit and Loss 2020-21File: 1 of 1 CA UDIN Profit and Loss.pdf6 Apr 2022
Single Layout Plan by AuthorityFile: 2 Single layout plan approved.pdf6 Apr 2022
Single Site Plan DigitalFile: 2 Single Site Plan Digital.pdf6 Apr 2022
Commencement CertificateFile: 3 Commencement Certificate.pdf6 Apr 2022
Declaration with respect to Sanction Letter UploadFile: 3 Declaration for Sanction Letter.pdf6 Apr 2022
Relinquishment Deed for Road ExtensionFile: 4 Relinquishment deed - Road Extn.pdf6 Apr 2022
Relinquishment Deed for STRRFile: 4 Relinquishment Deed - STRR Road.pdf6 Apr 2022
Balance Sheet 2020-21File: 1 - Balance Sheet - 2020-21 - 31032021.pdf12 Mar 2022
P&L 2020-21File: 1(1) - P&L - 2020-21 - 31032021.pdf12 Mar 2022
CA CertificateFile: 1(2) - CA Certificate.pdf12 Mar 2022
Single Layout and Sanction LetterFile: 2 Single Layout and Sanction Letter.pdf12 Mar 2022
Notarised Pollution CopyFile: 3(3) Notaraised pollution Copy.pdf12 Mar 2022
Agreement for Sale - Rera Format of 12062020File: 3(4) RERA -Sale Agreement (Final).pdf12 Mar 2022
Septic Tank Soak Pit and Sewer Line demarcation planFile: 3(5) - Plan of Septic Tank.pdf12 Mar 2022
Profit & Loss Statement 20-21File: 1 (1) P&L_20-21.pdf25 Feb 2022
Balance Sheet 20-21File: 1(1) BS_20-21.pdf25 Feb 2022
CA CertificateFile: 1(2) CA certificate_Rev1.pdf25 Feb 2022
Bank Account StatementFile: 1(3) Aradhra account statement.pdf25 Feb 2022
Self Attested PANFile: 1(4) Self attested pan.pdf25 Feb 2022
Floor Plan - Stilt, 1st 2nd 3rd and Terrace Plan with Section and ElevationFile: 2 - 2 - All Floor Plans ans Section.pdf25 Feb 2022
Layout Plan with Sanction Letter issued by STRRFile: 2(1) Plan with Sanction Letter.pdf25 Feb 2022
Water Supply NOC from Marasur Gram PanchayathFile: 3 (4) Water Permission of Gram Panchayat.pdf25 Feb 2022
KSPCB NOCFile: 3(4) Pollution copy (1).pdf25 Feb 2022
Proforma Agreement for SaleFile: 3(6) Proforma Agreement - Aradhra.pdf25 Feb 2022
Septic, Sewer and Soak - Layout Demarcation PlanFile: 3(6) Plan of septic tak, soap pitt,.pdf25 Feb 2022
Project Specifications issued by ArchitectFile: 3(7) Architect Specification of JD.pdf25 Feb 2022
RTC, survey 32/2-
Mutation, survey 32/2-
Encumbrance Certificate, survey 32/2-
Conversion/Alienation Order, survey 32/2-
Sale/Title/Gift Deed, survey 32/2-
JDA, survey 32/2-
Khatha, survey 32/2-
Registration CertificateFile: GST Registration Certificate.pdf-
Certificate issued by CA Form 1File: 1(2) - CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-2 - Architect Certificate (1).pdf-
Certificate issued by Engineer Form 3File: Form-3 - Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit - No Litigation.pdf-
Certificate from Chartered AccountFile: 1(2) - CA Certificate.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet_compressed.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet_compressed.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P&L_compressed.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P&L_compressed.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR.pdf-
STRR Final Aproval letter-
Electrical NOC Aproval-
Panchayathi water permission-
Plan 1_compressed-
Plan 1_compressed-
legal opinion for RERA-
G D COPY-
Conversion copy-
Form - B-
Section 3(1) Affidavit-
JDA Affidavit-
Electrical NOC Aproval-
Panchayathi water permission-
Pollution copy_compressed-
Parithyajana pathra 1_compressed-
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: FormEx5.pdf-
CA Certificate for Funds UtilizationFile: Form-Ex3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: EX-6.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4.pdf-
AffidavitFile: Form-Ex7_Affidavit.pdf-
Latest Encumbrance CertificateFile: EC.pdf-

How this compares with Bengaluru Urban

54%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Aradhra on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAradhraOther 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: Adish Properties

Adish Properties has 1 registration on RERA Karnataka, including Aradhra. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Aradhra is delayed beyond 31 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Aradhra?

The registered promoter entity is Adish Properties, a proprietorship firm as per the filing. Its GSTIN 29AVFPK4908F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Aradhra?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Aradhra?

The professionals named in the filing: Architect: Nameet Vivek Shirali; Engineer: Bhagya Lakshmi RC; Chartered Accountant: Prasanna Adiga. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aradhra?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aradhra. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aradhra to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.