Home / Browse projects / Gandhinagar, Gujarat / APPLE GREEN HOMES

Valid until 31 Mar 2026 Residential/Group Housing project

APPLE GREEN HOMES

By ABHISHEK INFRA

RG-GJ-97964 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN313AA10213/270223 · Last updated on GujRERA portal: 25 Nov 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2026Possession promisedno revision filed
24 of 27Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 0%
14 of 120Units unsoldnot recorded sold or booked
Jump to the 25 documents Report an error

APPLE GREEN HOMES is a Residential/Group Housing project by ABHISHEK INFRA in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN313AA10213/270223 on 27 Feb 2023. Possession is promised by 31 Mar 2026. 106 of the 120 units on this registration are recorded sold or booked, and 24 of 27 construction stages are filed complete.

At a glance

Project

  • NameAPPLE GREEN HOMES
  • TypeResidential/Group Housing
  • Location
    • APPLE GREEN HOMES
    • NEAR PARKLANE GREEN
    • B/H. KAMLAM BJP OFFICE
    • KOBA
    • GANDHINAGAR HIGHWAY
    • GANDHINAGAR -382421
    • KOBA
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN313AA10213/270223
  • ReraGenie IDRG-GJ-97964

Builder

  • NameABHISHEK INFRA
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →
  • Past their filed date2

Key dates

this monthRegisteredFeb 2023PromisedMar 2026

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2026
  • Registered on27 Feb 2023
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed25 files

Current status

88%106 of 120 units booked
90.8%Of the estimated cost spent so far

Figures as on 25 Nov 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---40040
Block B---40040
Block C---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 25 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 0%.

Block A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Block C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 25 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes80%
Landscaping and tree plantingYes80%
Street lightingYes85%
Community buildingsYes95%
Treatment and disposal of sewage and sullage waterYes90%
Solid waste management and disposalYes90%
Water conservation, rain water harvestingYes85%
Energy managementYes85%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes95%
Fire fightingYes80%
Drinking water facilitiesYes90%
Emergency evacuationYes95%
Use of renewable energyYes85%
SecurityYes95%
Letter boxYes90%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,917 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 43.00 cr
Cost incurredRs 39.03 cr
Spent of the estimate90.78%
BuildingWingEstimatedIncurred
Block CNARs 14.34 crRs 13.01 cr
Block ANARs 14.33 crRs 13.01 cr
Block BNARs 14.33 crRs 13.01 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSiddharth Vitthalbhai Patel
EngineerKETAN KANUBHAI PATEL

Documents filed25

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN313AA10213/270223 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)25 Nov 2025
Architect's certificate (Form 1)24 Nov 2025
Engineer's certificate (Form 2)24 Nov 2025
Engineer's certificate annexure24 Nov 2025
Site photograph, Block A24 Nov 2025
Site photograph, Block B24 Nov 2025
Site photograph, Block C24 Nov 2025
RERA registration certificate27 Feb 2023
Proforma agreement for sale-
Project specific document-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-

How this compares with Gandhinagar

88%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep APPLE GREEN HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KOBA1,600+ in Gandhinagar

2 kmAPPLE GREEN HOMESOther 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 106 registered projects within 2 km.

Builder: ABHISHEK INFRA

ABHISHEK INFRA has 2 registrations on GujRERA, including ABHISHEK HOMES and APPLE GREEN HOMES. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if APPLE GREEN HOMES is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of APPLE GREEN HOMES?

The registered promoter entity is ABHISHEK INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in APPLE GREEN HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at APPLE GREEN HOMES?

The professionals named in the filing: Architect: Siddharth Vitthalbhai Patel; Engineer: KETAN KANUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in APPLE GREEN HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About APPLE GREEN HOMES. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save APPLE GREEN HOMES to a free account