ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / ANUSTHAN HOMES

Valid until 30 Jun 2019 Residential/Group Housing project

ANUSTHAN HOMES

By life infra

RG-GJ-86901 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00506/EX1/100419 · Last updated on GujRERA portal: 28 Jun 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 3 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2019Possession promisedmoved 3 months from the original
7 of 7Construction stages doneevery applicable stage filed complete
10 of 27Units unsoldnot recorded sold or booked
Jump to the 36 documents Report an error

ANUSTHAN HOMES is a Residential/Group Housing project by life infra in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00506/EX1/100419 on 18 Oct 2017. Possession is promised by 30 Jun 2019. The completion date has moved by 3 months from the original filing. 17 of the 27 units on this registration are recorded sold or booked, and 7 of 7 construction stages are filed complete.

At a glance

Project

  • NameANUSTHAN HOMES
  • TypeResidential/Group Housing
  • Location
    • NR. PEHEL
    • b/H RATNA PARABIZE
    • B/H AUDA GARDEN
    • KHORAJ
    • Khoraj
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00506/EX1/100419
  • ReraGenie IDRG-GJ-86901

Builder

  • Namelife infra
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2017First promiseMar 2019Revised toJun 2019

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2019
  • Registered on18 Oct 2017
  • Promised completion30 Jun 2019
  • Revised completionRevised to 30 Jun 2019 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed36 files

Current status

63%17 of 27 units booked
100.0%Of the estimated cost spent so far

Figures as on 28 Jun 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
a---27027

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 28 Jun 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 7 construction stages are filed complete.

a: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 Jun 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area668 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.62 cr
Cost incurredRs 2.62 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
aNARs 2.62 crRs 2.62 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00506/EX1/100419Applied Mar 2019; approved Apr 2019

Documents filed36

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA00506/EX1/100419 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)28 Jun 2019
Architect's certificate (Form 1)26 Jun 2019
Engineer's certificate (Form 2)26 Jun 2019
RERA registration certificate18 Oct 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

63%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 3 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep ANUSTHAN HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Khoraj1,600+ in Gandhinagar

2 kmANUSTHAN HOMESOther 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 101 registered projects within 2 km.

Builder: life infra

life infra has 1 registration on GujRERA, including ANUSTHAN HOMES. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if ANUSTHAN HOMES is delayed beyond 30 Jun 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ANUSTHAN HOMES?

The registered promoter entity is life infra, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ANUSTHAN HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in ANUSTHAN HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANUSTHAN HOMES. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANUSTHAN HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.