Home / Browse projects / Belagavi, Karnataka / Ambica Orchid
Ambica Orchid
By M/S. ABHIJEET ARVIND JAWALKAR
RG-KA-28624 · RERA PRM/KA/RERA/1249/447/PR/010426/008567 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Ambica Orchid is a Residential/Group Housing project by M/S. ABHIJEET ARVIND JAWALKAR in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/010426/008567 on 1 Apr 2026. Possession is promised by 30 Sep 2028. 2 of the 10 units on this registration are recorded sold or booked, and 4 of 16 construction stages are filed complete.
At a glance
Project
- NameAmbica Orchid
- TypeResidential/Group Housing
- Location
- Belagavi
- 590006
- Pincode590006
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1249/447/PR/010426/008567
- ReraGenie IDRG-KA-28624
Builder
- NameM/S. ABHIJEET ARVIND JAWALKAR
- Entity typeProprietorship
- GSTIN29AMTPJ1864C1ZS
- Authorized SignatoryABHIJEET ARVIND JAWALKAR
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on1 Apr 2026
- Promised completion30 Sep 2028
- Revised completionNone
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Ambica Orchid | - | - | - | 10 | 0 | 10 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 16 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 80%.
Building: 33% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 80% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 30% |
| Masonry Construction | 25% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | Yes | 0% |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 15% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 15% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | 60% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Nitin Vithalrao Suntankar | - | - |
| Prasanna Vithalrao Suntankar | - | - |
| Sumedha W/o Sanjay Sunthankar | - | - |
| Sanket S/o Sanjay Sunthankar | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 4.38 cr | Rs 63.37 lakh |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 30.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ajit V Patil |
| Engineer | Milind K Belgaonkar |
| Chartered Accountant | Krishnanand Kamat |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed68
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/010426/008567 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant Certificate Orchid Q2 26-27.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5 Architect Certificate Q2 26-27 Orchid_compressed.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Certificate Q2 26-27 Orchid.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant Certificate Orchid Q1 26-27.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5 Architect Certificate Q1 26-27 Orchid.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Certificate Q1 26-27 Orchid_compressed.pdf | 15 Jul 2026 |
| CA CertificateFile: FORM-Reg1 CA Certificate-Orchid.pdf | 26 Mar 2026 |
| stability CertificateFile: stability Certificate .pdf | 26 Mar 2026 |
| Agreement of SaleFile: AGREEMENT FOR SALE-AMBICA ORCHID (1) (1).pdf | 26 Mar 2026 |
| Encumbrance CertificateFile: Thsildar 1 Encumbrance Certificate.pdf | 7 Mar 2026 |
| Form BFile: Thsildar 2 Form-B.pdf | 7 Mar 2026 |
| Non Litigation AffidavitFile: 3 Non Litigation Orchid.pdf | 7 Mar 2026 |
| Layout orderFile: TCP 1 and 2 Layout order _merged.pdf | 7 Mar 2026 |
| Permission Approved Certificate Ambica OrchidFile: TCP 3 Permission Approved Certificate Ambica Orchid.pdf | 7 Mar 2026 |
| 5 9 CTS Map Village Map singl layoutFile: TCP 4 5 9 CTS Map Village Map singl layout.pdf | 7 Mar 2026 |
| Approved Permission Drawing Ambica OrchidFile: 6 Approved Permission Drawing - Ambica Orchid.pdf | 7 Mar 2026 |
| CDP MapFile: 8 CDP Map.pdf | 7 Mar 2026 |
| Declaration KTCP NOCFile: TCP 10 and 11 Declration KTCP NOC.pdf | 7 Mar 2026 |
| Village Map layout planFile: TCP 12 Village Map layout plan.pdf | 7 Mar 2026 |
| structural stability certificate and valid licenceFile: Eng 7 Structural stability certificate and lincse.pdf | 7 Mar 2026 |
| AOSFile: ENG 8 AGREEMENT FOR SALE-AMBICA ORCHID.pdf | 7 Mar 2026 |
| Declaration for HESCOM NOCFile: ENG 9 Declration for Hescom Noc.pdf | 7 Mar 2026 |
| Declaration for Water NOCFile: Eng 10 Declration for Water NOC.pdf | 7 Mar 2026 |
| CA CertificateFile: CA Certificate .pdf | 7 Mar 2026 |
| land govt valueFile: land govt value_merged.pdf | 7 Mar 2026 |
| Query AbstractFile: Query Abstract (1).pdf | 7 Mar 2026 |
| Registration CertificateFile: GST RC.pdf | - |
| GST CertificateFile: GST RC.pdf | - |
| Certificate issued by CA Form 1File: FORM-Reg1 CA Certificate-Orchid.pdf | - |
| Certificate issued by Architect Form 2File: Form 2 Architect PR Orchid.pdf | - |
| Certificate issued by Engineer Form 3File: Form Engineer Orchid.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: 3 Non Litigation Orchid.pdf | - |
| Balance Sheet 2024 - 2025File: Balance Sheet 24-25.pdf | - |
| Balance Sheet 2023 - 2024File: Balance Sheet 23-24.pdf | - |
| Balance Sheet 2022 - 2023File: Balance Sheet 24-25.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: P&L 24-25.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: P&L 23-24.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: P&L 24-25.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: ITR 24-25.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR 23-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR 24-25.pdf | - |
| Permission Approved Certificate - Ambica Orchid | - |
| Approved Permission Drawing - Ambica Orchid | - |
| Approved Permission Drawing - Ambica Orchid | - |
| To be uploaded later | - |
| Specification (1) | - |
| AGREEMENT FOR SALE-AMBICA ORCHID NEW 01 - Copy | - |
| ANNEXURE Allotment Letter Ambica Orhid | - |
| No Violation Orchid | - |
| JDA Affiadavit Orchid | - |
| LEGAL OPINION | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| CTS Map(Sketch) | - |
| Extract From CTS | - |
| Estimation Copy | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| One Life Phase I & II | R S NO 94 AND 95/2 SITUATED AT 9TH CROSS BHAGYANAGAR , Belagavi , Belagavi , Belagavi, Karnataka - 590006 | Ongoing | Aug 2027 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep Ambica Orchid on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Filed coordinates, straight-line distance. 65 registered projects within 2 km.
One Life Phase III ,IV & V
Ambica Infra Build
ONE LIFE PHASE I & II
Ambica Infra Build
FORTUNE TOWER
The Fortune Five
ALORA
THE FORTUNE FIVE
SHREE DATTA SMRUTI
SHREE RADHAKRISHNA DEVELOPERS
SANAVI RESIDENCY
ANIL ANNASAHEB PATIL
See every Belagavi project, with the district possession charts
Builder: M/S. ABHIJEET ARVIND JAWALKAR
M/S. ABHIJEET ARVIND JAWALKAR has 1 registration on RERA Karnataka, including Ambica Orchid. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if Ambica Orchid is delayed beyond 30 Sep 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Ambica Orchid?
The registered promoter entity is M/S. ABHIJEET ARVIND JAWALKAR, a proprietorship as per the filing. Its GSTIN 29AMTPJ1864C1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Ambica Orchid?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Ambica Orchid?
The professionals named in the filing: Architect: Ajit V Patil; Engineer: Milind K Belgaonkar; Chartered Accountant: Krishnanand Kamat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Ambica Orchid?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback