Home / Browse projects / Vadodara, Gujarat / ALORA 18

Valid until 1 Jul 2027 Residential/Group Housing project

ALORA 18

By Shakti Infra

RG-GJ-90966 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA12892/070224/010327 · Last updated on GujRERA portal: 17 Jul 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2027Possession promisedno revision filed
24 of 50Construction stages doneacross 5 buildings; furthest along: Internal walls, 60%
13 of 18Units unsoldnot recorded sold or booked
Jump to the 35 documents Report an error

ALORA 18 is a Residential/Group Housing project by Shakti Infra in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA12892/070224/010327 on 7 Feb 2024. Possession is promised by 1 Jul 2027. 5 of the 18 units on this registration are recorded sold or booked, and 24 of 50 construction stages are filed complete.

At a glance

Project

  • NameALORA 18
  • TypeResidential/Group Housing
  • Location
    • RS NO. 331/P1/P1
    • FP NO.30
    • OP NO. 30 AT VILL BILL TAL & DIST VADODARA
    • BILL
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA12892/070224/010327
  • ReraGenie IDRG-GJ-90966

Builder

  • NameShakti Infra
  • Entity typePARTNERSHIP FIRM
  • Other registrations4 more →

Key dates

this monthRegisteredFeb 2024PromisedJul 2027

Key facts

Registration and timeline

  • StatusValid until 1 Jul 2027
  • Registered on7 Feb 2024
  • Promised completion1 Jul 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed35 files

Current status

28%5 of 18 units booked
35.9%Of the estimated cost spent so far

Figures as on 17 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE-B---404
TYPE-A---11011
TYPE-A2---101
TYPE-A1---101
TYPE-A3---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 50 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 60%.

TYPE-B32%
ActivityProgress
Excavation100%
Podiums (if any)40%
Plinth100%
Stilt Floor40%
Slabs of Super Structure40%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A64%
ActivityProgress
Excavation100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing60%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing40%
TYPE-A260%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A180%
ActivityProgress
Excavation100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
TYPE-A356%
ActivityProgress
Excavation100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing20%

Progress on shared amenities19

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,008 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 9.00 cr
Cost incurredRs 3.23 cr
Spent of the estimate35.87%
BuildingWingEstimatedIncurred
TYPE-ANARs 5.30 crRs 2.00 cr
TYPE-BNARs 2.34 crRs 87.00 lakh
TYPE-A1NARs 48.18 lakhRs 18.36 lakh
TYPE-A2NARs 46.26 lakhRs 9.08 lakh
TYPE-A3NARs 41.94 lakhRs 8.04 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVineet Vijay Matai
EngineerCHETAN MANJIBHAI KAMBAD

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RAA12892/070224/010327 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)17 Jul 2026
Engineer's certificate (Form 2)15 Jul 2026
Engineer's certificate annexure15 Jul 2026
Architect's certificate (Form 1)4 May 2026
Site photograph, TYPE-B11 Apr 2026
Site photograph, TYPE-A11 Apr 2026
Site photograph, TYPE-A211 Apr 2026
Site photograph, TYPE-A111 Apr 2026
Site photograph, TYPE-A311 Apr 2026
RERA registration certificate7 Feb 2024
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

28%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep ALORA 18 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near BILL2,900+ in Vadodara

2 kmALORA 18Other 231Dot size: filed unitsN

Filed coordinates, straight-line distance. 231 registered projects within 2 km.

Builder: Shakti Infra

SHAKTI INFRA has 5 registrations on GujRERA, including AMBIKA HEAVEN and VICTORIAN OASIS. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if ALORA 18 is delayed beyond 1 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ALORA 18?

The registered promoter entity is Shakti Infra, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ALORA 18?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ALORA 18?

The professionals named in the filing: Architect: Vineet Vijay Matai; Engineer: CHETAN MANJIBHAI KAMBAD. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ALORA 18?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ALORA 18. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ALORA 18 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.