Registration approved No litigation declared Residential/Group Housing project

Aiikya Village Sarjapur

By Aiikya Village Sarajapur LLP

RG-KA-66006 · RERA PRM/KA/RERA/1251/446/PR/221123/006419 · Last updated on RERA Karnataka portal: 3 Nov 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2026Possession promisedno revision filed
3 of 19Construction stages donefurthest along: Retaining wall (All types), 87%
51 of 169Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 171 documents Report an error

Aiikya Village Sarjapur is a Residential/Group Housing project by Aiikya Village Sarajapur LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/221123/006419 on 22 Nov 2023. Possession is promised by 26 Nov 2026. 118 of the 169 units on this registration are recorded sold or booked, and 3 of 19 construction stages are filed complete.

At a glance

Project

  • NameAiikya Village Sarjapur
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/221123/006419
  • ReraGenie IDRG-KA-66006

Builder

  • NameAiikya Village Sarajapur LLP
  • Entity typePartnership Firm
  • LLPINAAW-9936
  • GSTIN29ABVFA4243M1ZR
  • Authorized SignatoryChethan Kumar P

Key dates

this monthRegisteredNov 2023PromisedNov 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Nov 2023
  • Promised completion26 Nov 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed171 files

Current status

70%118 of 169 units booked
98.4%Of the estimated cost spent so far

Figures as on 3 Nov 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---63063
B---60060
C---46046

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 3 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 19 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 87%.

Building: 34% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)49%
Retaining wall (All types)87%
RCC or MS Framed structure71%
Masonry Construction55%
Plastering inside , outside & Ceiling39%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification19%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing21%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 3 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes60%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes50%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes61%
LiftsYes0%
Corridor/LobbiesYes58%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes68%
TerraceYes0%
Outer WallYes54%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,879 sq m
Named landowners1
LandownerVillageDistrict
Sindhu G--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 63.87 cr
Cost incurredRs 62.85 cr
Spent of the estimate98.4%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 42.83 crRs 36.40 cr
Payment of taxesRs 7.71 crRs 4.93 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 4.78 crRs 4.21 cr
On-site expenditure-Salaries of workersRs 4.67 crRs 13.42 cr
Payment of feesRs 3.89 crRs 3.89 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrinath .R. Advani (Advani and Associates)
EngineerRajesh M H
Chartered AccountantV Sagar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed171

As listed on the registration, under the names the promoter filed them with; the newest 80 of 171 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/221123/006419 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form BFile: Form B.pdf3 Nov 2026
self attested engineer licenceFile: Licence Attested Copy.pdf3 Nov 2026
sold and unsold units detailsFile: Availability List.pdf3 Nov 2026
Water NOCFile: Water NOC.pdf3 Nov 2026
Fire NOCFile: FIRE NOC.pdf3 Nov 2026
Airport NOCFile: Airport Authority NOC.pdf3 Nov 2026
Bescom NOCFile: BESCOM NOC.pdf3 Nov 2026
BSnl nocFile: BSNL NOC.pdf3 Nov 2026
KSPCB NOCFile: KSPCB Pollution NOC.pdf3 Nov 2026
SEIAA NOCFile: SEIAA (Environment) NOC.pdf3 Nov 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate - AIIKYA V by iScanner.pdf17 Aug 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 - Architect - March 2026.pdf17 Aug 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate-Mar-26.pdf17 Aug 2026
Q4 2025-26 Water supply and sewage board17 Aug 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)17 Aug 2026
Q4 2025-26 KPTCL- BESCOM17 Aug 2026
Q4 2025-26 Fire and Safety17 Aug 2026
Q4 2025-26 Airport Authority of India17 Aug 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate - Alikya V by iScanner_compressed.pdf17 Aug 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 - Architect - June 2026.pdf17 Aug 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate-Jun-26.pdf17 Aug 2026
Q1 2026-27 Water supply and sewage board17 Aug 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)17 Aug 2026
Q1 2026-27 KPTCL- BESCOM17 Aug 2026
Q1 2026-27 Fire and Safety17 Aug 2026
Q1 2026-27 Airport Authority of India17 Aug 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form - 4 Chartered Accountant - Dec 2025.pdf24 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form - 5 Architect - Dec 2025.pdf24 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Chartered Engineer - Dec 2025.pdf24 Feb 2026
Q3 2025-26 Water supply and sewage board24 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)24 Feb 2026
Q3 2025-26 KPTCL- BESCOM24 Feb 2026
Q3 2025-26 Fire and Safety24 Feb 2026
Q3 2025-26 Airport Authority of India24 Feb 2026
Relinquishment deed road wideningFile: Relinquishment deed.pdf20 Nov 2023
AIIKYA SARJAPUR Conversion OrderFile: AIIKYA SARJAPUR Conversion Order.pdf20 Nov 2023
PCB NOC application givenFile: PCB NOC application given.jpeg20 Nov 2023
NOC DeclarationFile: NOC Declaration.jpeg20 Nov 2023
Change of LandFile: Change of Land.pdf20 Nov 2023
Tasildhar Letter for ConversionFile: Tasildhar Letter for Conversion.pdf20 Nov 2023
Tower wise inventory details updatedFile: Tower wise inventory details updated.xlsx20 Nov 2023
STRR Sanctioned Site Plan Section and ElevationFile: STRR Site Plan Section and Elevation.pdf20 Nov 2023
Aiikya Village Sarjapur LLP - RERA Designated Collection Account StatementFile: Point 1 Aiikya RERA Designated Collection Account Statement.jpeg17 Nov 2023
Partnership DeedFile: Point 7 - Aiikya Village Sarjapura Partnership Deed Scan.pdf17 Nov 2023
MR ExtractFile: Point 8 - MR Extract.pdf17 Nov 2023
EC from 01-04-2004 till 30-10-2023File: Point 9 ECC-14102023-4306885.pdf17 Nov 2023
Katha Extract from the PanchyatFile: Point 10 - Sarjapur Panchayat E-Katha Extract.pdf17 Nov 2023
Notorized Non-Litigation AffidavitFile: Point 11 Non-Litigation Affidavit.pdf17 Nov 2023
Signed Copy of Advocate Search ReportFile: Point 12 - Legal Opinion - Aiikya Village Sarjapur.pdf17 Nov 2023
Revised Form-B Affidavit with date of completion in DDMMYYYY formatFile: Point 13 - Affidavit Form B Notorised.pdf17 Nov 2023
JD Affidavit Cum DeclarationFile: JD Affidavit cum declaration signed copy.pdf17 Nov 2023
Single Plot LayoutFile: Point 21 Single Site Approval Plan.pdf17 Nov 2023
Single Plot Layout OrderFile: Point 22 - Single Site Layout Order.pdf17 Nov 2023
Architects Certificate with valid COA NumberFile: Point 23 - Architects certificate with COA.pdf17 Nov 2023
CDP MAP Showing Proposed SiteFile: Point 25 CDP Map Showing Proposed Site.pdf17 Nov 2023
Village Map Showing the Proposed SiteFile: Point 26 - Village Map Sarjapura.pdf17 Nov 2023
Relinguishment DeedFile: Point 27 - Reliquishement Deed - STRR.pdf17 Nov 2023
Sanctioned Plan 1File: Point 30 STRR Basement Floor Plan.pdf17 Nov 2023
Sanctioned Plan 2File: Point 30 STRR Ground Floor & First Floor Plan.pdf17 Nov 2023
Sanctioned Plan 3File: Point 30 STRR Site Plan Section & Elevation.pdf17 Nov 2023
Sanctioned Plan 4File: Point 30 STRR Terrace Floor Plan.pdf17 Nov 2023
Sanctioned Plan 5File: Point 30 STRR Typical Lower & Upper Floor Plan.pdf17 Nov 2023
Sanctioned Plan 6File: Point 30 STRR 14th Floor Simplex Floor Plan.pdf17 Nov 2023
Water NOCFile: Point 36 - Water NOC.pdf17 Nov 2023
Fire NOCFile: Point 37 - Fire Noc.pdf17 Nov 2023
Proforma of Allotment LetterFile: Point 40 - Proforma Allotment Letter.pdf17 Nov 2023
Proforma of Agreement of SaleFile: Point 41 - Proforma of Agreement of Sale.pdf17 Nov 2023
STP Design DrawingFile: Point 43 - STP 130KLD.pdf17 Nov 2023
Project Name & Address Notarized AffidavitFile: Point 45 Notorised Affidavit.pdf17 Nov 2023
Financials Balance Sheet - 2021-22File: Point 2 Financials fy 2021-22.pdf17 Nov 2023
Financials Balance Sheet - 2022-23File: Point 2 Financials fy 2022-23.pdf17 Nov 2023
Financials Balance Sheet - 2023-24File: Point 2 Financials fy 2023-24.pdf17 Nov 2023
Chartered Accountant Certificate - in the RERA FormatFile: Point 5 Chartered Accountant Revised Certificate.pdf17 Nov 2023
Souces of fundsFile: Sources of Funds.pdf17 Nov 2023
Partner Chethan ITR AY 22-23File: CHETHAN ITR AY 22-23.pdf17 Nov 2023
chethan provisional 23-24File: chethan provisional 23-24.pdf17 Nov 2023
Chethan Networth certificateFile: Chethan Networth certificate.pdf17 Nov 2023
Tower wise inventory details updatedFile: Tower wise inventory details updated.xlsx17 Nov 2023
Floor wise Tower details updatedFile: Floor wise Tower details updated.xlsx17 Nov 2023
Aiikya RERA workingFile: Aiikya RERA working.xlsx17 Nov 2023

How this compares with Bengaluru Urban

70%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Aiikya Village Sarjapur on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAiikya Village SarjapurOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: Aiikya Village Sarajapur LLP

Aiikya Village Sarajapur LLP has 1 registration on RERA Karnataka, including Aiikya Village Sarjapur. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Aiikya Village Sarjapur is delayed beyond 26 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Aiikya Village Sarjapur?

The registered promoter entity is Aiikya Village Sarajapur LLP, a partnership firm as per the filing. Its LLPIN AAW-9936 and GSTIN 29ABVFA4243M1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Aiikya Village Sarjapur?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Aiikya Village Sarjapur?

The professionals named in the filing: Architect: Srinath .R. Advani (Advani and Associates); Engineer: Rajesh M H; Chartered Accountant: V Sagar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aiikya Village Sarjapur?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aiikya Village Sarjapur. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aiikya Village Sarjapur to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.