Registration approved No litigation declared Residential/Group Housing project

AGANI VELOCITY

By AGANI PROJECTS PRIVATE LIMITED

RG-KA-99761 · RERA PRM/KA/RERA/1251/308/PR/150324/006705 · Last updated on RERA Karnataka portal: 9 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2030Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
29 of 60Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 175 documents Report an error

AGANI VELOCITY is a Residential/Group Housing project by AGANI PROJECTS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/150324/006705 on 15 Mar 2024. Possession is promised by 31 Dec 2030. 31 of the 60 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameAGANI VELOCITY
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/150324/006705
  • ReraGenie IDRG-KA-99761

Builder

  • NameAGANI PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70100KA2013PTC072459
  • GSTIN29AADCE5581G1ZF
  • Authorized SignatorySUDHAKAR AGANI
  • Managing DirectorSUDHAKAR AGANI
  • DirectorsSUDHAKAR AGANI, PRIYANKA SUDHAKAR REDDY
  • Project HeadSUDHAKAR AGANI

Key dates

this monthRegisteredMar 2024PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Mar 2024
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed175 files

Current status

52%31 of 60 units booked
3.4%Of the estimated cost spent so far

Figures as on 9 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
velocity---60060

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesYes100%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,035 sq m
Named landowners2
LandownerVillageDistrict
SIRAJ--
SIRAJ--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 16.29 cr
Cost incurredRs 54.61 lakh
Spent of the estimate3.35%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 15.92 crRs 49.49 lakh
On-site expenditure-Site OverheadRs 18.00 lakh-
On-site expenditure-Salaries of workersRs 13.49 lakhRs 5.12 lakh
On-site expenditure-Consultants FeesRs 6.02 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKRISHNAMURTHY. M
EngineerMADAMANCHI SURENDRA NADH
Chartered AccountantI V S S RAJU

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed175

As listed on the registration, under the names the promoter filed them with; the newest 80 of 175 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/150324/006705 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate June 26.pdf9 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate June 26.pdf9 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate June 26.pdf9 Jul 2026
Q1 2026-27 Water supply and sewage board9 Jul 2026
Q1 2026-27 KPTCL- BESCOM9 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA March 26 Agani.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect March 26.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer March 26.pdf11 Apr 2026
Q4 2025-26 Water supply and sewage board11 Apr 2026
Q4 2025-26 KPTCL- BESCOM11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate - Dec 2025.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architects certificate - Dec 2025.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Engineer's Certificate -Dec 2025.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
katha extract obtained from local bodyFile: velocity khata_compressed.pdf6 Mar 2024
C L U ORDER COPYFile: c l u oder copy _compressed.pdf6 Mar 2024
C D P sketchFile: C D P PLAN AGAIN.pdf6 Mar 2024
Audit Report March 2020File: Audit Report March 2020.pdf5 Mar 2024
Balance sheet 2020File: Balance sheet 2020.pdf5 Mar 2024
Cashflow March 2020File: Cashflow March 2020.pdf5 Mar 2024
Directors Report march 2020File: Directors Report march 2020.pdf5 Mar 2024
Profit and Loss 2020File: Profit and Loss 2020.pdf5 Mar 2024
AUDITOR REPORT march 2021File: AUDITOR REPORT march 2021.pdf5 Mar 2024
Balance Sheet 2021File: Balance Sheet 2021.pdf5 Mar 2024
CASH FLOW STATEMENT 3_03_2021File: CASH FLOW STATEMENT 3_03_2021.pdf5 Mar 2024
Director Report March 2021File: Director Report March 2021.pdf5 Mar 2024
Profit and Loss 2021File: Profit and Loss 2021.pdf5 Mar 2024
Auditor Report march 2022File: Auditor Report march 2022.pdf5 Mar 2024
Balance sheet 2022File: Balance sheet 2022.pdf5 Mar 2024
Cash Flow Statement 2022File: Cash Flow Statement 2022.pdf5 Mar 2024
Directors report march 2022File: Directors report march 2022.pdf5 Mar 2024
Profit and Loss 2022File: Profit and Loss 2022.pdf5 Mar 2024
Estella Maple Square Rera Application formFile: Estella Maple Square Rera Application form.pdf5 Mar 2024
Estella Maple Square Rera Form 4File: Estella Maple Square Rera Form 4.pdf5 Mar 2024
Estella Maple Square Rera Form_5File: Estella Maple Square Rera Form_5.pdf5 Mar 2024
Estella Maple Square Rera Form_6File: Estella Maple Square Rera Form_6.pdf5 Mar 2024
Estella Maple SquareFile: Estella Maple Square.pdf5 Mar 2024
SOURCE OF FUNDSFile: SOURCE OF FUNDS.PDF5 Mar 2024
CDP MapFile: CDP Map.pdf5 Mar 2024
Conversion Order 2013File: Conversion Order 2013.pdf5 Mar 2024
BESCOMFile: BESCOM.PDF5 Mar 2024
LAND COST CALCULATIONFile: LAND COST CALCULATION.PDF5 Mar 2024
STP DrawingFile: STP Drawing.pdf5 Mar 2024
Water NOCFile: Water NOC.pdf5 Mar 2024
Floor PlanFile: Floor Plan.PDF5 Mar 2024
Grond And Tipical floor PlanFile: Grond And Tipical floor Plan.PDF5 Mar 2024
VELOCITY BDA APPROVAL LETTERFile: VELOCITY BDA APPROVAL LETTER.PDF5 Mar 2024
Post Registration Details Q2 20_21File: Post Registration Details Q2 20_21.pdf5 Mar 2024
Post Registration Details Q4 19_20File: Post Registration Details Q4 19_20.pdf5 Mar 2024
Post Registration Details Q1 20_21File: Post Registration Details Q1 20_21.pdf5 Mar 2024
Post Registration Details Q2 19_20File: Post Registration Details Q2 19_20.pdf5 Mar 2024
Post Registration Details Q3 19_20File: Post Registration Details Q3 19_20.pdf5 Mar 2024
Form 6File: Engineer certificate form 6 .pdf5 Mar 2024
Project completion certificate by enngrFile: Completion certificate engineer agni.pdf5 Mar 2024
form 5File: Architects Certificate- Form 5 agani.pdf5 Mar 2024
Project completion certificate by arctFile: TOWER A COMPLETION CERTIFICATE 29 06 2021.pdf5 Mar 2024
Project completion oc copyFile: IMG_6274.pdf5 Mar 2024
AGREEMENT FOR SALEFile: AGREEMENT FOR SALE.pdf29 Jan 2024
Allotment letter agani velocityFile: Allotment letter agani velocity.pdf29 Jan 2024
Amenities & Comon Area CertificateFile: Amenities & Comon Area Certificate.pdf29 Jan 2024
AUDITOR REPORT PDF 20_21 AY 21_22File: AUDITOR REPORT PDF 20_21 AY 21_22.pdf29 Jan 2024
Auditor ReportFile: Auditor Report.pdf29 Jan 2024
Balance sheet FY 19_20 AY 20_21File: Balance sheet FY 19_20 AY 20_21.pdf29 Jan 2024
BESCOM Fee and letterFile: BESCOM Fee and letter.pdf29 Jan 2024
Board of Director reportFile: Board of Director report.pdf29 Jan 2024
Carpet Area CertificateFile: Carpet Area Certificate.pdf29 Jan 2024
Cash Flow Statement 31_03_2022File: Cash Flow Statement 31_03_2022.pdf29 Jan 2024
CDP Map with Proposed SiteFile: CDP Map with Proposed Site.pdf29 Jan 2024
ConversionFile: Conversion.pdf29 Jan 2024
Director Report 2020_21File: Director Report 2020_21.pdf29 Jan 2024
Directors report 2021_22File: Directors report 2021_22.pdf29 Jan 2024
Directors Report Estella ProjectsFile: Directors Report Estella Projects.pdf29 Jan 2024
ENGINEER BBMP Licence CertificateFile: ENGINEER BBMP Licence Certificate.pdf29 Jan 2024
Estella Cash flow statementFile: Estella Cash flow statement.pdf29 Jan 2024
Financial auditor reprort Merged oneFile: Financial auditor reprort Merged one.pdf29 Jan 2024
Financials 20_21 2 CASH FLOW STATEMENTFile: Financials 20_21 2 CASH FLOW STATEMENT.pdf29 Jan 2024
Financials 20_21 pdfFile: Financials 20_21 pdf.pdf29 Jan 2024
Khatha LETTER OF DECLARATIONFile: Khatha LETTER OF DECLARATION.PDF29 Jan 2024
PCB Fee and letterFile: PCB Fee and letter.pdf29 Jan 2024

How this compares with Bengaluru Urban

52%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep AGANI VELOCITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAGANI VELOCITYOther 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: AGANI PROJECTS PRIVATE LIMITED

AGANI PROJECTS PRIVATE LIMITED has 1 registration on RERA Karnataka, including AGANI VELOCITY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if AGANI VELOCITY is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AGANI VELOCITY?

The registered promoter entity is AGANI PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U70100KA2013PTC072459 and GSTIN 29AADCE5581G1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AGANI VELOCITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AGANI VELOCITY?

The professionals named in the filing: Architect: KRISHNAMURTHY. M; Engineer: MADAMANCHI SURENDRA NADH; Chartered Accountant: I V S S RAJU. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AGANI VELOCITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AGANI VELOCITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AGANI VELOCITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.