Home / Browse projects / Bengaluru Urban, Karnataka / Adarsh Tropica (Phase-1)

Registration approved No litigation declared Residential/Group Housing project

Adarsh Tropica (Phase-1)

By ORCHIDS APARTMENTS PVT LTD

RG-KA-68165 · RERA PRM/KA/RERA/1251/446/PR/111022/005309 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Apr 2027Possession promisedno revision filed
7 of 18Construction stages donefurthest along: Joinery: Doors, 99%
2 of 309Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 138 documents Report an error

Adarsh Tropica (Phase-1) is a Residential/Group Housing project by ORCHIDS APARTMENTS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/111022/005309 on 11 Oct 2022. Possession is promised by 30 Apr 2027. 307 of the 309 units on this registration are recorded sold or booked, and 7 of 18 construction stages are filed complete.

At a glance

Project

  • NameAdarsh Tropica (Phase-1)
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 572214
  • Pincode572214
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/111022/005309
  • ReraGenie IDRG-KA-68165

Builder

  • NameORCHIDS APARTMENTS PVT LTD
  • Entity typeCompany
  • CINU45201KA1981PTC004086
  • GSTIN29AAACO2209G2ZO
  • Authorized SignatoryBM Jayeshankar
  • MdBM Jayeshankar
  • DirectorsBM Jayeshankar, Sudha Shanker
  • Project HeadYogesh MM
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2022PromisedApr 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Oct 2022
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed138 files

Current status

99%307 of 309 units booked
100.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 1---2060206
Block 2---1030103

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 18 construction stages are filed complete. The stage furthest along is Joinery: Doors, at 99%.

Building: 96% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)95%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc99%
Basic work of Water supply, Sanitary and Electrification98%
Dadoing, Skirting, Flooring, Tiles work (All types)99%
Railing and Grill fixing99%
Electrification, Water supply and Sanitary Finishing98%
Painting97%
Fire prevention and fire fighting fitting and fixture with network98%
Weather Proof work(tile,concrete)99%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work80%
Internal and External work including landscapes as per sanctioned drawings75%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes98%
Sewage and Drainage SystemYes98%
Water conservation/rain water harvesting/recharge of ground waterYes85%
Energy managementYes0%
Fire protection and fire safety requirementsYes85%
Solid waste management and disposalYes85%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes96%
Electricity supply transformer and substationYes90%
Storm water drainsYes95%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingYes80%
Street LightingYes90%
ElectricityYes95%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes85%
Community HallNoNot applicable
Outdoor Sports facilityYes50%
Indoor Sports facilityYes10%
Swimming PoolYes40%
GymYes20%
ParksYes60%
Power BackupYes50%
Piped GasYes0%
Water and SanitationYes60%
Air ConditioningNoNot applicable
StaircasesYes98%
LiftsYes100%
Corridor/LobbiesYes95%
Fire escapesYes95%
Common entrance and exit for the building/common portico/foyer/verandahYes95%
BasementYes95%
TerraceYes80%
Outer WallYes95%
Open parking areasYes75%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,736 sq m
Named landowners4
LandownerVillageDistrict
B M Karunesh--
B M Karunesh--
B M Karunesh--
B M Karunesh--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 107.56 cr
Cost incurredRs 107.66 cr
Spent of the estimate100.1%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 78.78 crRs 88.28 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 13.25 cr-
On-site expenditure-Salaries of workersRs 9.88 crRs 9.91 cr
On-site expenditure-Site OverheadRs 3.57 crRs 6.51 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.26 crRs 96.42 lakh
On-site expenditure-Consultants FeesRs 81.88 lakhRs 2.00 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShyamala.H.R
EngineerChetana Consultants
Chartered AccountantMahesh B S

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed138

As listed on the registration, under the names the promoter filed them with; the newest 80 of 138 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/111022/005309 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Tropica Ph-1_.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Tropica PH 1.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Tropica PH 1.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Tropica PH 1_.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Tropica PH 1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Tropica PH 1.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Tropica PH 1_.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Tropica PH 1.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Tropica PH 1.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Tropica PH 1_merged.pdf31 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Tropica PH 1.pdf31 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Eng Tropica PH 1.pdf31 Jan 2026
Q3 2025-26 Water supply and sewage board31 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)31 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)31 Jan 2026
Q3 2025-26 KPTCL- BESCOM31 Jan 2026
Q3 2025-26 Fire and Safety31 Jan 2026
Q3 2025-26 Airport Authority of India31 Jan 2026
Certificate from Registered Engineer indicating the structural safety for the proposed buildingFile: Letter for Adarsh Tropica 001.pdf3 Oct 2022
Doc No 1-RTC obtained from revenue department office for syno 64/4File: Doc No 1-RTC-2013-2019-20-Sy No 64-4.pdf19 Sep 2022
Doc No 2 - sale deed from chinnappa reddy to shivarudraiah for syno 64/5File: Doc No2-Sale deed-Doc 5961-2007-08 (64-4.pdf19 Sep 2022
Doc No 3-sale deed/title deed from h m venkatesh reddy to shivarudraiah for syno 64/4File: Doc No 3-Sale Deed-Doc 5960-2007-08 (64-4.pdf19 Sep 2022
Doc No 4 - sale deed/title deed from n kumar to kkalyanna for syno 65/1AFile: Doc No 4-Sale deed-Doc 23-2008-09 (65-1A.pdf19 Sep 2022
Doc No - 5 - sale deeed/title deed from gowramma to b m karunesh for syno65/1bFile: Doc No 5-Sale deed-Doc 2504-2007-08 (65-1B.pdf19 Sep 2022
Doc o - 7- mortage deed infavour of vistara itclFile: Doc No7-MOE-2360-2018-19 (19-06-18) Part-1-Vismaya,Orchids & Akarsha Realty to Vistra ITCL19 Sep 2022
DocNo 8-Hissa Survey Tippani, Atlas & RR Balabagada Nakal-Sy No 64-2File: Doc No 8-Hissa Survey Tippani, Atlas & RR Balabagada Nakal-Sy No 64-2.pdf19 Sep 2022
DocNo 8- Hissa Survey Tippani-Sy No 56-4File: Doc No 8-Hissa Survey Tippani-Sy No 56-4.pdf19 Sep 2022
Doc No 8-Hissa Tippani-Sy No 37-5File: Doc No 8-Hissa Tippani-Sy No 37-5.pdf19 Sep 2022
Doc No 8-Hissa Tippani-Sy No 65-1AFile: Doc No 8-Hissa Tippani-Sy No 65-1A.pdf19 Sep 2022
Doc No 8-Hissa Tippani-Sy No 65-1BFile: Doc No 8-Hissa Tippani-Sy No 65-1B.pdf19 Sep 2022
Attachment 1 -- Architect BCC Registration certificateFile: Attachment -1-bcc reg.pdf19 Sep 2022
Attchment 2 - Demarcation plan Signed by ArchitectFile: Attachment -2 Demarcation plan with Signature.pdf19 Sep 2022
Attachment 3--FAR and Building Height entered same as Sanction PlanFile: Attachment -3-Same as sanction plan.png19 Sep 2022
Attachment 4- Building Plan letterFile: Attachment -4-BP.pdf19 Sep 2022
Attachment 4- Development Plan letterFile: Attachment -4-DP.pdf19 Sep 2022
Attachment 5-Village map demarcation of the proposed siteFile: Attachment -5-Village map.pdf19 Sep 2022
Attachment 6--CDP Plan demarcation of the proposed siteFile: Attachment -6-CDP Plan demarcation of the proposed site.pdf19 Sep 2022
Attachment 7--All level Floor PlansFile: Attachment -7 -Blk 1 2 and 4 FLOOR PLANS_compressed.pdf19 Sep 2022
Attachment 8-- project location latitude and longitude detailsFile: Attachment -8-Latitude Longitude.pdf19 Sep 2022
Attachment 9-Phase 1 STP location in demarcation plan with area detailsFile: Attachment -9-Phase-1 plan with area details.pdf19 Sep 2022
Attachment 9--STP schematic diagramFile: Attachment -9-STP design.jpg19 Sep 2022
Doc No 10-Adarsh Tropica Phase-I-Agreement for Sale-090922File: Doc No 10-Adarsh Tropica Phase-I-Agreement for Sale-090922.pdf19 Sep 2022
Attachment 10-- TROPICA SPECIFICATIONSFile: Attachment -10-TROPICA SPECIFICATIONS.pdf19 Sep 2022
RTC, survey 64/4-
Mutation, survey 64/4-
Encumbrance Certificate, survey 64/4-
Conversion/Alienation Order, survey 64/4-
Sale/Title/Gift Deed, survey 64/4-
Khatha, survey 64/4-
RTC, survey 65/1A1-
Mutation, survey 65/1A1-
Encumbrance Certificate, survey 65/1A1-
Conversion/Alienation Order, survey 65/1A1-
Sale/Title/Gift Deed, survey 65/1A1-
Khatha, survey 65/1A1-
RTC, survey 65/1B-
Mutation, survey 65/1B-
Encumbrance Certificate, survey 65/1B-
Conversion/Alienation Order, survey 65/1B-
Sale/Title/Gift Deed, survey 65/1B-
Khatha, survey 65/1B-
RTC, survey 64/5-

How this compares with Bengaluru Urban

99%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Adarsh Tropica (Phase-1) on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAdarsh Tropica (Phase-1)Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 62 registered projects within 2 km.

Builder: ORCHIDS APARTMENTS PVT LTD

ORCHIDS APARTMENTS PVT LTD has 2 registrations on RERA Karnataka, including Adarsh Tropica (Phase-2) and Adarsh Tropica (Phase-1). Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Adarsh Tropica (Phase-1) is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Adarsh Tropica (Phase-1)?

The registered promoter entity is ORCHIDS APARTMENTS PVT LTD, a company as per the filing. Its CIN U45201KA1981PTC004086 and GSTIN 29AAACO2209G2ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Adarsh Tropica (Phase-1)?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Adarsh Tropica (Phase-1)?

The professionals named in the filing: Architect: Shyamala.H.R; Engineer: Chetana Consultants; Chartered Accountant: Mahesh B S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Adarsh Tropica (Phase-1)?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Adarsh Tropica (Phase-1). Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Adarsh Tropica (Phase-1) to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.