Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2029Possession promisedno revision filed
4 of 18Construction stages donefurthest along: RCC or MS Framed structure, 95%
191 of 399Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 180 documents Report an error

ABHEE CELESTIAL CITY is a Residential/Group Housing project by NEXPLACE INFRASTRUCTURE in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/071123/006380 on 7 Nov 2023. Possession is promised by 30 Jun 2029. 208 of the 399 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.

At a glance

Project

  • NameABHEE CELESTIAL CITY
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/071123/006380
  • ReraGenie IDRG-KA-07265

Builder

  • NameNEXPLACE INFRASTRUCTURE
  • Entity typePartnership Firm
  • GSTIN29AASFN1079J1ZL
  • Authorized SignatoryR NAGARAJ REDDY

Key dates

this monthRegisteredNov 2023PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Nov 2023
  • Promised completion30 Jun 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed180 files

Current status

52%208 of 399 units booked
67.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABHEE CELESTIAL CITY---3990399

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 95%.

Building: 69% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)70%
Retaining wall (All types)100%
RCC or MS Framed structure95%
Masonry Construction69%
Plastering inside , outside & Ceiling69%
Joinery: Doors, Windows, Ventilators etc56%
Basic work of Water supply, Sanitary and Electrification51%
Dadoing, Skirting, Flooring, Tiles work (All types)65%
Railing and Grill fixing74%
Electrification, Water supply and Sanitary Finishing45%
Painting55%
Fire prevention and fire fighting fitting and fixture with network68%
Weather Proof work(tile,concrete)73%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work47%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes20%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes40%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes15%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes70%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes90%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes30%
Swimming PoolYes40%
GymYes30%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes77%
LiftsYes78%
Corridor/LobbiesYes72%
Fire escapesYes72%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes85%
TerraceYes75%
Outer WallYes14%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,602 sq m
Named landowners9
LandownerVillageDistrict
NEXPLACE INFRASTRUCTURE--
NEXPLACE INFRASTRUCTURE--
NEXPLACE INFRASTRUCTURE--
NEXPLACE INFRASTRUCTURE--
DV DHANARAJU--
APPARAO JAMPANI--
DV KRISHNAPPA--
RATAKONDA RAMESH--
BASAVA REDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 270.89 cr
Cost incurredRs 181.84 cr
Spent of the estimate67.13%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 194.72 crRs 119.86 cr
Payment of taxesRs 38.10 crRs 27.58 cr
On-site expenditure-Consultants FeesRs 16.12 crRs 9.92 cr
On-site expenditure-Site OverheadRs 10.58 crRs 6.51 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 6.35 crRs 3.91 cr
On-site expenditure-Salaries of workersRs 5.02 crRs 3.09 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 10.96 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFWD ARCHITECTS
EngineerCRATIS DESIGNERS PVT LTD
Chartered AccountantRAVEENDRA REDDY V

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed180

As listed on the registration, under the names the promoter filed them with; the newest 80 of 180 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/071123/006380 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form- 4 Celestial Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: form-5 Architecture Certificate_Q2_13OCT2026.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6, FY 26-27-CELESTIAL CITY.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Abhee Celestial City Form 4 Q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: celestial form 5 final.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Celestial City 1 FORM 3 Engineer Certificate-4 copy.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Celestial City Q4 2025-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certifiacte.PDF15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate_compressed.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate-ACC.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate ACC.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate-ACC.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Airport Authority of India15 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department15 Jan 2026
Carpet area calculationsFile: Nexplace Flat Wise Carpet Areas.pdf3 Nov 2023
CLU & Clv fee letterFile: CDP Clarification.pdf3 Nov 2023
1st BasementFile: 1st Basement Floor Plan Blw.pdf3 Nov 2023
2nd BasementFile: 2nd Basement Floor Plan Blw.pdf3 Nov 2023
Ground FloorFile: Ground Floor Blw.pdf3 Nov 2023
1st and 2nd FloorFile: 1st & 2nd Floor Plan Blw.pdf3 Nov 2023
3rd to 25th FloorFile: 3rd to 25th Floor Plan Blw.pdf3 Nov 2023
Section AAFile: Section AA Blw.pdf3 Nov 2023
ElevationFile: Elevation Blw.pdf3 Nov 2023
Site PlanFile: Site Plan Blw.pdf3 Nov 2023
Terrace FloorFile: Terrace Floor Plan Blw.pdf3 Nov 2023
Engineer LicenseFile: Engineer License.pdf3 Nov 2023
Bank AccountFile: Bank Statement.pdf31 Oct 2023
Source of FundsFile: Source of Funds.pdf31 Oct 2023
Saledeed In favour of BharathFile: Sale Deed 24-2 & 24-11.pdf31 Oct 2023
Saledeed 24/8 DV Dhanaraju, Apparao, DV Krishnappa, Ratakonda RameshFile: DV Dhanaraju, Apparao, Ratakonda, Krishnappa.pdf31 Oct 2023
Saledeed Jyothi, Annayanavar, BasavareddyFile: Jyothi, Annayanavar, Basavareddy.pdf31 Oct 2023
Notarized Non LitigationFile: Affidavit - Non Litigation.pdf31 Oct 2023
Ec from 01.04.2004 to till dateFile: Ec 1-4-2004 to Till Date.pdf31 Oct 2023
Form - BFile: Form-B Affidavit Cum Declaration.pdf31 Oct 2023
OS No. 21/1991 Compromise Order and MR CopyFile: Compromise Petition and MR.pdf31 Oct 2023
Carpet Area CalculationFile: certified carpet area calculation (1).pdf31 Oct 2023
CDP MapFile: Chikvaderpura CDP.jpeg31 Oct 2023
Village MapFile: Village Map (2).pdf31 Oct 2023
Sanctioned PlansFile: Sanctioned Plans.pdf31 Oct 2023
Area CalculationFile: AREA DETAILS CERTIFIED BY ENGINEER.pdf31 Oct 2023
Amenities and Common area detailsFile: AMENITIES AND COMMON AREA DETAILS CERTIFIED.pdf31 Oct 2023
Engineer License self attestedFile: ENGINEER'S LICENCE CERTIFICATE.pdf31 Oct 2023
Cost of construction Brief estimationFile: Form - 3, Engineer.pdf31 Oct 2023
Project SpecificationFile: PROJECT NAME ADDRESS AND SPECIFICATION.pdf31 Oct 2023
Affidavit Section 3(1) notarizedFile: Affidavit for 3(1) Voilation.pdf31 Oct 2023
Proforma Allotment LetterFile: Allotment Letter.pdf31 Oct 2023
Self Attested NOCFile: Self Attested NOC.pdf31 Oct 2023
STP Design drawingFile: STP CERTIFIED DRAWING.pdf31 Oct 2023
Guidance Valuation certified by Sub RegistrarFile: Guideline value - Chikvaderpura.pdf31 Oct 2023
Source of Water - Own BorewellFile: WATER SUPPLY - BOREWELLS LOCATIONS POINTS.pdf31 Oct 2023
KathaFile: Katha.pdf31 Oct 2023
RTC, survey 24/2-
Mutation, survey 24/2-
Encumbrance Certificate, survey 24/2-
Conversion/Alienation Order, survey 24/2-
Sale/Title/Gift Deed, survey 24/2-
Khatha, survey 24/2-
RTC, survey 24/11-

How this compares with Bengaluru Urban

52%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ABHEE CELESTIAL CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmABHEE CELESTIAL CITYOther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: NEXPLACE INFRASTRUCTURE

NEXPLACE INFRASTRUCTURE has 1 registration on RERA Karnataka, including ABHEE CELESTIAL CITY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ABHEE CELESTIAL CITY is delayed beyond 30 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ABHEE CELESTIAL CITY?

The registered promoter entity is NEXPLACE INFRASTRUCTURE, a partnership firm as per the filing. Its GSTIN 29AASFN1079J1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ABHEE CELESTIAL CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ABHEE CELESTIAL CITY?

The professionals named in the filing: Architect: FWD ARCHITECTS; Engineer: CRATIS DESIGNERS PVT LTD; Chartered Accountant: RAVEENDRA REDDY V. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ABHEE CELESTIAL CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ABHEE CELESTIAL CITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ABHEE CELESTIAL CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.