ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / AAYAT AVENUE

Valid until 30 Apr 2030 Commercial project

AAYAT AVENUE

By CRYSTEL INFRA

RG-GJ-60990 · RERA PR/GJ/GANDHINAGAR/KALOL (G)/Ahmedabad Urban Development Authority/CAA16436/070226/311229 · Last updated on GujRERA portal: 7 Feb 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2030Possession promisedno revision filed
4 of 9Construction stages donefurthest along: Internal walls, 80%
33 of 33Units unsoldnot recorded sold or booked
Jump to the 37 documents Report an error

AAYAT AVENUE is a Commercial project by CRYSTEL INFRA in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL (G)/Ahmedabad Urban Development Authority/CAA16436/070226/311229 on 7 Feb 2026. Possession is promised by 30 Apr 2030. 0 of the 33 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameAAYAT AVENUE
  • TypeCommercial
  • Location
    • Nr. Sindbad Hotel
    • Beside Honda Service Station
    • Kalol-Mansa highway
    • KALOL
    • Kalol (G)
    • Gandhinagar
    • 382721
  • Pincode382721
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL (G)/Ahmedabad Urban Development Authority/CAA16436/070226/311229
  • ReraGenie IDRG-GJ-60990

Builder

  • NameCRYSTEL INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredFeb 2026PromisedApr 2030

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2030
  • Registered on7 Feb 2026
  • Promised completion30 Apr 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed37 files

Current status

0%0 of 33 units booked
78.0%Of the estimated cost spent so far

Figures as on 7 Feb 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---03333

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 7 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

A: 74% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats30%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 7 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,843 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.96 cr
Cost incurredRs 2.31 cr
Spent of the estimate78.0%
BuildingWingEstimatedIncurred
ANARs 2.96 crRs 2.31 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNIKUNJ VASANTLAL SUTHAR
EngineerMOHD HAARIS MUGISUDDIN MAL

Documents filed37

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL (G)/Ahmedabad Urban Development Authority/CAA16436/070226/311229 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate7 Feb 2026
Accountant's certificate (Form 3)3 Feb 2026
Engineer's certificate (Form 2)17 Jan 2026
Engineer's certificate annexure17 Jan 2026
Architect's certificate (Form 1)13 Jan 2026
Site photograph, A13 Jan 2026
Proforma agreement for sale-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

0%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep AAYAT AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KALOL1,600+ in Gandhinagar

2 kmAAYAT AVENUEOther 66Dot size: filed unitsN

Filed coordinates, straight-line distance. 66 registered projects within 2 km.

Builder: CRYSTEL INFRA

CRYSTEL INFRA has 1 registration on GujRERA, including AAYAT AVENUE. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if AAYAT AVENUE is delayed beyond 30 Apr 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AAYAT AVENUE?

The registered promoter entity is CRYSTEL INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AAYAT AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AAYAT AVENUE?

The professionals named in the filing: Architect: NIKUNJ VASANTLAL SUTHAR; Engineer: MOHD HAARIS MUGISUDDIN MAL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAYAT AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAYAT AVENUE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAYAT AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.