ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / AARYA EXOTICA

Valid until 31 Jan 2022 Mixed Development project

AARYA EXOTICA

By SHIVAM ENTERPRISE

RG-GJ-77021 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA02557/EX2/030122 · Last updated on GujRERA portal: 24 Jun 2024

Source: official GujRERA filing

Red flags

  • Completion date moved by 27 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jan 2022Possession promisedmoved 27 months from the original
64 of 72Construction stages doneacross 8 buildings; furthest along: Stilt Floor, 0%
17 of 202Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

AARYA EXOTICA is a Mixed Development project by SHIVAM ENTERPRISE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA02557/EX2/030122 on 5 May 2018. Possession is promised by 31 Jan 2022. The completion date has moved by 27 months from the original filing. 185 of the 202 units on this registration are recorded sold or booked, and 64 of 72 construction stages are filed complete.

At a glance

Project

  • NameAARYA EXOTICA
  • TypeMixed Development
  • Location
    • AARYA EXOTICA
    • F.P. 61
    • AT VILLAGE BIL
    • BIL MAIN ROAD
    • Bill
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA02557/EX2/030122
  • ReraGenie IDRG-GJ-77021

Builder

  • NameSHIVAM ENTERPRISE
  • Entity typePARTNERSHIP FIRM
  • Other registrations10 more →

Key dates

this monthRegisteredMay 2018First promiseOct 2019Revised toJan 2022

Key facts

Registration and timeline

  • StatusValid until 31 Jan 2022
  • Registered on5 May 2018
  • Promised completion31 Jan 2022
  • Revised completionRevised to 31 Jan 2022 (originally 31 Oct 2019)
  • Buildings8 building records
  • Documents filed45 files

Current status

92%185 of 202 units booked
100.0%Of the estimated cost spent so far

Figures as on 24 Jun 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower D---161228
Tower E---20020
Tower F---20020
Tower G---20020
Tower H---30030
Tower A---16824
Tower B---141832
Tower c---161228

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 24 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

64 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is Stilt Floor, at 0%.

Tower D89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower E89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower F89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower G89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower H89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Tower c89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 24 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsYes100%
Landscaping and tree plantingNoNot applicable
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,045 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.51 cr
Cost incurredRs 10.51 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Tower ANARs 1.31 crRs 1.31 cr
Tower BNARs 1.31 crRs 1.31 cr
Tower DNARs 1.31 crRs 1.31 cr
Tower ENARs 1.31 crRs 1.31 cr
Tower FNARs 1.31 crRs 1.31 cr
Tower GNARs 1.31 crRs 1.31 cr
Tower HNARs 1.31 crRs 1.31 cr
Tower cNARs 1.31 crRs 1.31 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRAN PATEL
EngineerVINUBHAI PATEL

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA02557/EX1/280520Applied Mar 2020; approved May 2020
PR/GJ/VADODARA/VADODARA/Others/MAA02557/EX2/030122Applied Dec 2021; approved Jan 2022

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA02557/EX2/030122 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)24 Jun 2024
Engineer's certificate (Form 2)24 Jun 2024
Engineer's certificate annexure24 Jun 2024
Accountant's certificate (Form 3)24 Jun 2024
Site photograph, Tower D21 Jun 2024
Site photograph, Tower E21 Jun 2024
Site photograph, Tower F21 Jun 2024
Site photograph, Tower G21 Jun 2024
Site photograph, Tower H21 Jun 2024
Site photograph, Tower A21 Jun 2024
Site photograph, Tower B21 Jun 2024
Site photograph, Tower c21 Jun 2024
RERA registration certificate5 May 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

92%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 27 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep AARYA EXOTICA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bill2,900+ in Vadodara

2 kmAARYA EXOTICAOther 198Dot size: filed unitsN

Filed coordinates, straight-line distance. 198 registered projects within 2 km.

Builder: SHIVAM ENTERPRISE

SHIVAM ENTERPRISE has 11 registrations on GujRERA, including AARYA EXOTICA and RUDRAKSH BLISS. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if AARYA EXOTICA is delayed beyond 31 Jan 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AARYA EXOTICA?

The registered promoter entity is SHIVAM ENTERPRISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AARYA EXOTICA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AARYA EXOTICA?

The professionals named in the filing: Architect: KIRAN PATEL; Engineer: VINUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARYA EXOTICA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARYA EXOTICA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARYA EXOTICA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.