AARYA ELITE PHASE - I

By SUDHAPATI DEVELOPERS PRIVATE LIMITED

RG-GJ-34999 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA04909/220219 · Last updated on GujRERA portal: 7 Jun 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2024Possession promisedno revision filed
27 of 27Construction stages doneacross 3 buildings; every applicable stage filed complete
0 of 25Units unsoldnot recorded sold or booked
Jump to the 52 documents Report an error

AARYA ELITE PHASE - I is a Residential/Group Housing project by SUDHAPATI DEVELOPERS PRIVATE LIMITED in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA04909/220219 on 22 Feb 2019. Possession is promised by 30 Jun 2024. 25 of the 25 units on this registration are recorded sold or booked, and 27 of 27 construction stages are filed complete.

At a glance

Project

  • NameAARYA ELITE PHASE - I
  • TypeResidential/Group Housing
  • Location
    • AARYA ELITE-01
    • OPP. AARYA EMPIRE
    • B/H NARAYAN KATHIYAWADI HOTEL
    • PADRA ROAD
    • ATLADRA
    • VADODARA
    • Kalali
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA04909/220219
  • ReraGenie IDRG-GJ-34999

Builder

  • NameSUDHAPATI DEVELOPERS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations7 more →

Key dates

this monthRegisteredFeb 2019PromisedJun 2024

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2024
  • Registered on22 Feb 2019
  • Promised completion30 Jun 2024
  • Revised completionNone
  • Buildings3 building records
  • Documents filed52 files

Current status

100%25 of 25 units booked
93.1%Of the estimated cost spent so far

Figures as on 7 Jun 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---303
B---707
C---15015

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 7 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 27 construction stages are filed complete across 3 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 7 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,170 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.00 cr
Cost incurredRs 2.79 cr
Spent of the estimate93.14%
BuildingWingEstimatedIncurred
ANARs 1.00 crRs 93.14 lakh
BNARs 1.00 crRs 93.14 lakh
CNARs 1.00 crRs 93.14 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRAN PATEL
EngineerVINUBHAI R. PATEL

Documents filed52

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA04909/220219 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)7 Jun 2022
Engineer's certificate (Form 2)7 Jun 2022
Engineer's certificate annexure7 Jun 2022
Accountant's certificate (Form 3)7 Jun 2022
Site photograph, A7 Jun 2022
Site photograph, B7 Jun 2022
Site photograph, B7 Jun 2022
Site photograph, B7 Jun 2022
Site photograph, C7 Jun 2022
Site photograph, C7 Jun 2022
Site photograph, C7 Jun 2022
Site photograph, C7 Jun 2022
Site photograph, C7 Jun 2022
Site photograph, C7 Jun 2022
Site photograph, C7 Jun 2022
Site photograph, C7 Jun 2022
RERA registration certificate22 Feb 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

100%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep AARYA ELITE PHASE - I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kalali2,900+ in Vadodara

2 kmAARYA ELITE PHASE - IOther 290Dot size: filed unitsN

Filed coordinates, straight-line distance. 290 registered projects within 2 km.

Builder: SUDHAPATI DEVELOPERS PRIVATE LIMITED

SUDHAPATI DEVELOPERS PRIVATE LIMITED has 8 registrations on GujRERA, including AARYA ELEGANCE and AARYA ELITE PHASE-II. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if AARYA ELITE PHASE - I is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AARYA ELITE PHASE - I?

The registered promoter entity is SUDHAPATI DEVELOPERS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AARYA ELITE PHASE - I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AARYA ELITE PHASE - I?

The professionals named in the filing: Architect: KIRAN PATEL; Engineer: VINUBHAI R. PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARYA ELITE PHASE - I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARYA ELITE PHASE - I. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARYA ELITE PHASE - I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.