Home / Browse projects / Gandhinagar, Gujarat / AAMIR VILLA

Valid until 28 Mar 2022 Residential/Group Housing project

AAMIR VILLA

By SHAIKH MOHAMMEDSAFWAN MOINUDDIN

RG-GJ-80057 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA01953/EX1/170621 · Last updated on GujRERA portal: 31 Mar 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Mar 2022Possession promisedmoved 12 months from the original
14 of 35Construction stages doneacross 5 buildings; furthest along: Stilt Floor, 90%
20 of 47Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

AAMIR VILLA is a Residential/Group Housing project by SHAIKH MOHAMMEDSAFWAN MOINUDDIN in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA01953/EX1/170621 on 9 Mar 2018. Possession is promised by 28 Mar 2022. The completion date has moved by 12 months from the original filing. 27 of the 47 units on this registration are recorded sold or booked, and 14 of 35 construction stages are filed complete.

At a glance

Project

  • NameAAMIR VILLA
  • TypeResidential/Group Housing
  • Location
    • 1202
    • TPS 4
    • NR AHMEDI PARK
    • KALOL.
    • KALOL
    • GANDHINAGAR
    • 382721.
    • Kalol
    • Gandhinagar
    • 382721
  • Pincode382721
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA01953/EX1/170621
  • ReraGenie IDRG-GJ-80057

Builder

  • NameSHAIKH MOHAMMEDSAFWAN MOINUDDIN
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredMar 2018First promiseMar 2021Revised toMar 2022

Key facts

Registration and timeline

  • StatusValid until 28 Mar 2022
  • Registered on9 Mar 2018
  • Promised completion28 Mar 2022
  • Revised completionRevised to 28 Mar 2022 (originally 28 Mar 2021)
  • Buildings5 building records
  • Documents filed42 files

Current status

57%27 of 47 units booked
82.2%Of the estimated cost spent so far

Figures as on 31 Mar 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E---15015
A---505
B---101
C---15015
D---11011

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 31 Mar 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 35 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 90%.

E92%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor90%
Slabs of Super Structure90%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
A60%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure60%
Internal walls, internal plaster, floorings, doors and windows within flats50%
Sanitary fittings within the flats50%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing50%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
B93%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats90%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing90%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure80%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats80%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 31 Mar 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes50%
Street lightingYes80%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes80%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,249 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.72 cr
Cost incurredRs 2.24 cr
Spent of the estimate82.21%
BuildingWingEstimatedIncurred
ANARs 54.38 lakhRs 44.70 lakh
BNARs 54.38 lakhRs 44.70 lakh
CNARs 54.38 lakhRs 44.70 lakh
DNARs 54.38 lakhRs 44.70 lakh
ENARs 54.38 lakhRs 44.70 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJENDRA.P.NIRMAL
EngineerHARESH A SHAH

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA01953/EX1/170621Applied Mar 2021; approved Jun 2021

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA01953/EX1/170621 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)31 Mar 2021
Site photograph, E31 Mar 2021
Site photograph, A31 Mar 2021
Site photograph, B31 Mar 2021
Site photograph, C31 Mar 2021
Site photograph, D31 Mar 2021
Accountant's certificate (Form 3)7 Jan 2021
RERA registration certificate9 Mar 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-
Engineer's certificate (Form 2)-
Engineer's certificate annexure-

How this compares with Gandhinagar

57%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 12 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep AAMIR VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kalol1,600+ in Gandhinagar

2 kmAAMIR VILLAOther 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: SHAIKH MOHAMMEDSAFWAN MOINUDDIN

SHAIKH MOHAMMEDSAFWAN MOINUDDIN has 1 registration on GujRERA, including AAMIR VILLA. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if AAMIR VILLA is delayed beyond 28 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AAMIR VILLA?

The registered promoter entity is SHAIKH MOHAMMEDSAFWAN MOINUDDIN, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AAMIR VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AAMIR VILLA?

The professionals named in the filing: Architect: RAJENDRA.P.NIRMAL; Engineer: HARESH A SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAMIR VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAMIR VILLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAMIR VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.