ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / AAKRUTHI NEST

Registration approved No litigation declared Residential/Group Housing project

AAKRUTHI NEST

By KRITI BUILDERS AND DEVELOPERS

RG-KA-51820 · RERA PRM/KA/RERA/1251/446/PR/200126/008414 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
6 of 18Construction stages donefurthest along: Retaining wall (All types), 90%
64 of 72Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 79 documents Report an error

AAKRUTHI NEST is a Residential/Group Housing project by KRITI BUILDERS AND DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200126/008414 on 20 Jan 2026. Possession is promised by 31 Dec 2028. 8 of the 72 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.

At a glance

Project

  • NameAAKRUTHI NEST
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/200126/008414
  • ReraGenie IDRG-KA-51820

Builder

  • NameKRITI BUILDERS AND DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29ABAFK5600RIZX
  • Authorized SignatorySirivelu Janardhan

Key dates

this monthRegisteredJan 2026PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2026
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed79 files

Current status

11%8 of 72 units booked
13.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AAKRUTHI NEST---72072

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 18 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 90%.

Building: 42% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)90%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling50%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation work10%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes30%
Sewage and Drainage SystemYes10%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes20%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes50%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes30%
Club HouseNoNot applicable
Community HallYes70%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes30%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes25%
Corridor/LobbiesYes50%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes30%
BasementNoNot applicable
TerraceYes70%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,642 sq m
Named landowners1
LandownerVillageDistrict
M Umashankar--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 28.71 cr
Cost incurredRs 3.90 cr
Spent of the estimate13.57%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 24.01 crRs 3.23 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 3.00 crRs 15.65 lakh
On-site expenditure-Site OverheadRs 80.00 lakhRs 45.15 lakh
On-site expenditure-Salaries of workersRs 45.00 lakhRs 2.00 lakh
On-site expenditure-Consultants FeesRs 25.00 lakhRs 3.64 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 20.00 lakhRs 13,005

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHIVAKUMAR
EngineerPRABHU S
Chartered AccountantN Girinath Reddy

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed79

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200126/008414 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4-Q2 CA Certificate.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: form 6.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4, Source of Funds Declaration, Saction Letter of AU Small Finance Bank.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect (QU) Q1-26-27 Signed.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Q1-26-27 Signed.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - CA Certificate.pdf25 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf25 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: form 6 Engineer Certificate_c.pdf25 Apr 2026
Q4 2025-26 Water supply and sewage board25 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)25 Apr 2026
Q4 2025-26 KPTCL- BESCOM25 Apr 2026
Financial Statements 2022-2023 clarificationFile: Financial statement Clarification.pdf13 Jan 2026
ITR V for the F.Y. 203-24File: ITR V FY 23 24 KRITI BUILDERS AND DEVELOPERS.pdf13 Jan 2026
Financials for the F.Y. 2023-24File: 2024 Financials.pdf13 Jan 2026
Conversion OrderFile: Conversion Order.pdf13 Jan 2026
EC from 1-4-2011 to till dateFile: ECC-09012026-9052498.pdf13 Jan 2026
Single Plot layout plan clarificationFile: Single Plot Plan Clarification.pdf13 Jan 2026
Single Plot layout order clarificationFile: Single Plot Order Clarification.pdf13 Jan 2026
Building License from Local Authority Original -Digital signed copyFile: KRITI LICENCE COPY.pdf13 Jan 2026
ADLR Certified survey sketch Certifying the Boundary of the Proposed land- survey sketchFile: ADLR Sketch.pdf13 Jan 2026
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: PRJ 5856 pdf plans.pdf13 Jan 2026
commencement certificate clarificationFile: Commencement Certificate Clarification.pdf13 Jan 2026
Demarcation of proposed land in Approved Master planFile: MASTER PLAN SITE MARKED.pdf13 Jan 2026
Demarcation of proposed land in original Village mapFile: VILLAGE MAP SITE MARKED.pdf13 Jan 2026
NOC under section 14 of the KTCP Act clarificationFile: NOC KTCP ACT Clarification.pdf13 Jan 2026
self-attested copy of the Engineer license certificateFile: ENGINEER CERTIFICATE SELF ATTESTED.pdf13 Jan 2026
engineer licence who has signed the form-3 engineer certificateFile: ENGINEER CERTIFICATE SELF ATTESTED.pdf13 Jan 2026
self attested structural engineer licence who has signed the structural stability certificateFile: ENGINEER CERTIFICATE SELF ATTESTED.pdf13 Jan 2026
Land cost calculation sheet as per the guidance value (Self-attested copy) along with guidance certiFile: Guideline Value certified.pdf13 Jan 2026
STP drawing certified by the Engineer with project name and addressFile: 50 KLD STP KRITI.pdf13 Jan 2026
project estimate mentioning the amount against each item wise of the projectFile: COST ESTIMATE SEAL AND SIGNED.pdf13 Jan 2026
RTC, survey 20/9-
Mutation, survey 20/9-
Encumbrance Certificate, survey 20/9-
Conversion/Alienation Order, survey 20/9-
Sale/Title/Gift Deed, survey 20/9-
JDA, survey 20/9-
Khatha, survey 20/9-
Registration CertificateFile: Kriti Firm Reg Cert attested.pdf-
GST CertificateFile: Kriti GST selfattested.pdf-
Partnership DeedFile: Kriti-Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form1 CA CERTIFICATE Signed Final.pdf-
Certificate issued by Architect Form 2File: FORM-2 AAKRUTHI NEST ARCHITECT CET.pdf-
Certificate issued by Engineer Form 3File: FORM-03 AAKRUTHI NEST ENGINEER CERT.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Kriti-Declaration about Non Litigation.pdf-
Balance Sheet 2024 - 2025File: Kriti-Financial-FY 24-25.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Kriti-Financial-FY 24-25.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Kriti-Financial-FY 24-25.pdf-
Kriti Building Licence-
Kriti Project Plan-
Kriti Project Plan-
STRUCTURAL STABILITY CERT AAKRUTHI NEST ENGINEER -
PROJECT SPECIFICATIONS AAKRUTHI NEST ENGINEER CERT-
Aakruthi Nest BrochureC-
PRJ 5856 LICENCE COPY-
Kriti Agreement for Sale-
Kriti Model Form of Allotment letter-
Kriti Form-B Affidavit cum declaration 2-
Kriti Non-Violation Affidavit for Aakruthi Nest-
Kriti JD Affidavit Cum Declaration-
AAKRUTHI NEST Legal Report-
NOC Bescom-
NOC BWSSB-
NOC PCB Aakruti-
Kriti-Conversion Order-
Prospectus/BrochureFile: Brochure_c.pdf-
Advertisement Copy 1File: Advertisement.pdf-

How this compares with Bengaluru Urban

11%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep AAKRUTHI NEST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAAKRUTHI NESTOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: KRITI BUILDERS AND DEVELOPERS

KRITI BUILDERS AND DEVELOPERS has 1 registration on RERA Karnataka, including AAKRUTHI NEST. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if AAKRUTHI NEST is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AAKRUTHI NEST?

The registered promoter entity is KRITI BUILDERS AND DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29ABAFK5600RIZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AAKRUTHI NEST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AAKRUTHI NEST?

The professionals named in the filing: Architect: SHIVAKUMAR; Engineer: PRABHU S; Chartered Accountant: N Girinath Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAKRUTHI NEST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAKRUTHI NEST. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAKRUTHI NEST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.