RG-KA-98109 · RERA PRM/KA/RERA/1257/478/PR/050224/006605 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
3 of 14Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 75%
24 of 24Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 96 documents Report an error

AACO ACURA is a Residential/Group Housing project by AACO ACURA in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/478/PR/050224/006605 on 5 Feb 2024. Possession is promised by 31 Dec 2028. 0 of the 24 units on this registration are recorded sold or booked, and 3 of 14 construction stages are filed complete.

At a glance

Project

  • NameAACO ACURA
  • TypeResidential/Group Housing
  • Location
    • Moodabidri
    • Dakshina Kannada
    • 574227
  • Pincode574227
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/478/PR/050224/006605
  • ReraGenie IDRG-KA-98109

Builder

  • NameAACO ACURA
  • Entity typePartnership Firm
  • GSTIN29ACAFA9970B1ZD
  • Authorized SignatoryABDUL RAWOOF

Key dates

this monthRegisteredFeb 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Feb 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed96 files

Current status

0%0 of 24 units booked
19.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AACO ACURA---24024

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 14 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 75%.

Building: 28% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)75%
Retaining wall (All types)Not applicable
RCC or MS Framed structure10%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,032 sq m
Named landowners1
LandownerVillageDistrict
ABDUL RAWOOF--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.04 cr
Cost incurredRs 1.00 cr
Spent of the estimate19.9%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.90 crRs 88.39 lakh
On-site expenditure-Consultants FeesRs 10.00 lakh-
On-site expenditure-Site OverheadRs 4.11 lakh-
Payment of taxes-Rs 11.93 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHALINI SURESH
EngineerBENNY MATHEW
Chartered AccountantRAVI RAO

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed96

As listed on the registration, under the names the promoter filed them with; the newest 80 of 96 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/478/PR/050224/006605 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: form 5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: form 6.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: architect.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: engineer.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: form 4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: architect certificate.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA Certificate (FORM 4).pdf23 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: architect certificate.pdf23 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer certificate.pdf23 Jan 2026
SINGLE LAYOUTFile: order -FOR SINGLE LAYOUT MOODBIDRI.pdf23 Jan 2024
all sanctioned drawings Floor plans, sectional drawings and elevationsFile: all approved floor, section elevation plan.pdf23 Jan 2024
CLARIFICATIONFile: clarification.pdf23 Jan 2024
SINGLE LAYOUT ORDER COPYFile: order -FOR SINGLE LAYOUT MOODBIDRI.pdf20 Dec 2023
all sanctioned drawings Floor plans, sectional drawings and elevationsFile: all approved floor, section elevation plan.pdf20 Dec 2023
CLARIFICATIONFile: clarification.pdf20 Dec 2023
PARTNERSHIP DEEDFile: partnership deed.pdf1 Dec 2023
ORDER FOR SINGLE SITEFile: order -FOR SINGLE LAYOUT MOODBIDRI.pdf1 Dec 2023
VILLAGE MAPFile: village map.pdf1 Dec 2023
all sanctioned drawings Floor plans sectional drawings and elevationsFile: all approved floor, section elevation plan.pdf1 Dec 2023
CLARIFICATIONFile: Clarification on notice01.pdf1 Dec 2023
STP DARWINGFile: STP.pdf1 Dec 2023
RTC, survey 59/P8-
Mutation, survey 59/P8-
Encumbrance Certificate, survey 59/P8-
Conversion/Alienation Order, survey 59/P8-
Sale/Title/Gift Deed, survey 59/P8-
Khatha, survey 59/P8-
Registration CertificateFile: firm registartion certificate.pdf-
Partnership DeedFile: partnership deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA certiifcate.pdf-
Certificate issued by Architect Form 2File: Form-2 architect.pdf-
Certificate issued by Engineer Form 3File: Form -3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: litigation affidavit.pdf-
Certificate from Chartered AccountFile: CA certiifcate.pdf-
Balance Sheet 2022 - 2023File: BALANCE SHHET 2023.pdf-
building licence revised-
sanction plan-revised-
floor, section elevation plan-
sanction plan-revised-
sanction plan -old-
sanction plan -old-
specification-
sanction plan-revised-
sanction plan-revised-
stability certificate-
search report-
title deed-
Conversion order_compressed-
Conversion order_compressed-
release deed-
proforma AOS-
proforma allotment letter-
form b_compressed-
affidavit 3(1)-
mescom noc_compressed-
water noc_compressed-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
pollution noc_compressed-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Dakshina Kannada

0%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep AACO ACURA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmAACO ACURAOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: AACO ACURA

AACO ACURA has 1 registration on RERA Karnataka, including AACO ACURA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if AACO ACURA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AACO ACURA?

The registered promoter entity is AACO ACURA, a partnership firm as per the filing. Its GSTIN 29ACAFA9970B1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AACO ACURA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AACO ACURA?

The professionals named in the filing: Architect: SHALINI SURESH; Engineer: BENNY MATHEW; Chartered Accountant: RAVI RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AACO ACURA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AACO ACURA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AACO ACURA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.