Vascon Engineers Ltd: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Vascon Engineers Ltd has 11 registrations in this build, including Vista II and Windermere Phase 1. Its filings disclose 4 earlier MahaRERA projects: 1 of 4 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Vista II | Nashik, Maharashtra | - | - | Completed |
| Windermere Phase 1 | Maharashtra | - | - | Completed |
| Windermere Phase 2 | Maharashtra | - | - | Completed |
| Platinum Square Phase 1 | Pune, Maharashtra | - | - | Completed |
| Platinum Square Phase 2 | Pune, Maharashtra | - | - | Completed |
| Vascon Goodlife Phase B | Pune, Maharashtra | - | - | De-registered |
| Vascon Goodlife Phase A | Pune, Maharashtra | - | - | Registration lapsed |
| Vascon Goodlife Phase C | Pune, Maharashtra | - | - | Registration lapsed |
| Eco Tower Phase 2 | Pune, Maharashtra | - | - | Completed |
| Tower of Ascend | Maharashtra | 45 | 71% | Registered |
| Vascon Orchids | Mumbai Suburban, Maharashtra | 112 | 9% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Willows | 30 Nov 2013 | 27 Apr 2015 | +17 months |
| EcoTower | 20 Aug 2014 | 29 Nov 2016 | +27 months |
| ELA Hadapsar | 31 Dec 2014 | 12 Jul 2017 | +30 months |
| Forest County | 31 Dec 2017 | 10 Apr 2017 | On time |
Frequently asked questions
How do I verify Vascon Engineers Ltd as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Vascon Engineers Ltd?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.