Home / Developers / Tejas Enterprises
Tejas Enterprises: RERA track record
Others ยท attribution by exact filing name, entity resolution in progress
Tejas Enterprises has 7 registrations in this build, including Tejas Emerald and Tejas Parishma. Its filings disclose 14 earlier MahaRERA projects: 1 of 14 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Tejas Emerald | Raigarh, Maharashtra | - | - | Completed |
| Tejas Parishma | Raigarh, Maharashtra | - | - | Completed |
| Tejas Sparsh | Raigarh, Maharashtra | - | - | Completed |
| Tejas Ambience | Raigarh, Maharashtra | - | - | Completed |
| Tejas Mauli | Raigarh, Maharashtra | - | - | Completed |
| Tejas Sapphire | Raigarh, Maharashtra | - | - | Completed |
| Tejas Heritage | Raigarh, Maharashtra | 2 | 50% | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Tejas Harmony | 31 Mar 2010 | 29 Sep 2010 | +6 months |
| Tejas Apartment | 30 Sep 2010 | 11 Dec 2012 | +26 months |
| Tejas Residency | 30 Sep 2010 | 4 Dec 2012 | +26 months |
| Tejas Villa | 30 Jun 2011 | 14 Dec 2012 | +18 months |
| Tejas Payas | 31 Mar 2012 | 27 Nov 2014 | +32 months |
| Tejas Exotica | 30 Jun 2012 | 13 Sep 2013 | +14 months |
| Tejas Roshan | 5 Jul 2012 | 12 Nov 2012 | +4 months |
| Tejas Shree Samarth | 31 Aug 2012 | 19 Jul 2013 | +11 months |
| Tejas GanpatSheth Apartment | 31 Oct 2012 | 30 Apr 2014 | +18 months |
| Tejas Kritika | 30 Nov 2012 | 28 Nov 2014 | +24 months |
| Tejas Heights | 31 Oct 2013 | 11 Mar 2015 | +16 months |
| Tejas Narmada | 31 May 2014 | 27 May 2015 | +12 months |
Frequently asked questions
How do I verify Tejas Enterprises as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Tejas Enterprises?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.