Tejas Enterprises has 7 registrations in this build, including Tejas Emerald and Tejas Parishma. Its filings disclose 14 earlier MahaRERA projects: 1 of 14 past projects completed on time.

7Registrations in this build
14Past projects disclosed
+15 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Tejas EmeraldRaigarh, Maharashtra--Completed
Tejas ParishmaRaigarh, Maharashtra--Completed
Tejas SparshRaigarh, Maharashtra--Completed
Tejas AmbienceRaigarh, Maharashtra--Completed
Tejas MauliRaigarh, Maharashtra--Completed
Tejas SapphireRaigarh, Maharashtra--Completed
Tejas HeritageRaigarh, Maharashtra250%Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Tejas Harmony
31 Mar 201029 Sep 2010+6 months
Tejas Apartment
30 Sep 201011 Dec 2012+26 months
Tejas Residency
30 Sep 20104 Dec 2012+26 months
Tejas Villa
30 Jun 201114 Dec 2012+18 months
Tejas Payas
31 Mar 201227 Nov 2014+32 months
Tejas Exotica
30 Jun 201213 Sep 2013+14 months
Tejas Roshan
5 Jul 201212 Nov 2012+4 months
Tejas Shree Samarth
31 Aug 201219 Jul 2013+11 months
Tejas GanpatSheth Apartment
31 Oct 201230 Apr 2014+18 months
Tejas Kritika
30 Nov 201228 Nov 2014+24 months
Tejas Heights
31 Oct 201311 Mar 2015+16 months
Tejas Narmada
31 May 201427 May 2015+12 months

Frequently asked questions

How do I verify Tejas Enterprises as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Tejas Enterprises?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.