Home / Developers / SHIVAM DEVELOPERS PRIVATE LIMITED
SHIVAM DEVELOPERS PRIVATE LIMITED: RERA track record
CIN U45201MH2006PTC166443 · GSTIN 27AAKCS4397P1ZB · Company · attribution by exact filing name, entity resolution in progress
SHIVAM DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including GURUKRUPA HEIGHTS. Its filings disclose 5 earlier MahaRERA projects: declares 2 of 3 past projects completed on time.
Projects by this developer
Showing the one project.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| GURUKRUPA HEIGHTSPM1261012601158 | -, Pune, 410501 | 7 | 0% | 13 Jul 2026 | Registered |
What this promoter declares as its own experience
SHIVAM DEVELOPERS PRIVATE LIMITED declares experience on 5 earlier projects. 5 of them carry a registration number we could match on MahaRERA, and all of them are registered under a different promoter name.
5 of these declarations can be compared with the dates those projects' own registrations hold. On 3, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 1 of the 2 completions recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it.
| Declared project | Registered to | Status |
|---|---|---|
| GHANWAT SQUARE | SHIVAM DEVELOPERS PVT. LTD. | Completed |
| SHIVAM GREENCOURT | SHIVAM DEVELOPERS PVT. LTD. | Completed |
| 19 GRAND WEST - C WING and D WING | Shivam Development Ventures LLP | Registration lapsed |
| 19 Grand West Wing A | Shivam Development Ventures LLP | Registration lapsed |
| 19 Grand West Wing B | Shivam Development Ventures LLP | Completed |
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| SHIVAM GREENCOURT P52100010035 | 30 Oct 2021 | 12 Feb 2021 | On time |
| 19 Grand West Wing B P52100017919 | 30 Nov 2022 | 30 Dec 2024 | +25 months |
| 19 Grand West Wing A P52100018030 | 30 Dec 2024 | Not completed yet | Ongoing |
| 19 GRAND WEST - C WING and D WING P52100031024 | 31 Dec 2024 | Not completed yet | Ongoing |
| GHANWAT SQUARE P52100025403 | 30 Nov 2025 | 16 Apr 2025 | On time |
Frequently asked questions
How do I verify SHIVAM DEVELOPERS PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45201MH2006PTC166443 and GSTIN 27AAKCS4397P1ZB on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SHIVAM DEVELOPERS PRIVATE LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.