Home / Developers / SAI SHRUSHTI ENTERPRISES
SAI SHRUSHTI ENTERPRISES: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
SAI SHRUSHTI ENTERPRISES has 13 registrations in this build, including SAI SHRUSHTI HEIGHTS-B4 and SAI SHRUSHTI ANNEX. Its filings disclose 5 earlier MahaRERA projects: 3 of 4 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| SAI SHRUSHTI HEIGHTS-B4 | Thane, Maharashtra | - | - | Completed |
| SAI SHRUSHTI ANNEX | Thane, Maharashtra | - | - | Completed |
| SAI SHRUSHTI SAPPHIRE | Thane, Maharashtra | - | - | Completed |
| SAI SHRUSHTI HERITAGE | Thane, Maharashtra | - | - | Completed |
| SAI SHRUSHTI SAPPHIRE PLOT A-1 | Thane, Maharashtra | - | - | Registration lapsed |
| Sai Shrushti Sapphire B-1 | Thane, Maharashtra | - | - | Completed |
| SAI SHRUSHTI VALLEY - PHASE 1/RAMCHANDRA COMPLEX | Thane, Maharashtra | - | - | Completed |
| Sai Shrushti Valley - Phase II / Ramchandra Complex | Thane, Maharashtra | - | - | Completed |
| Sai Shrushti Vatika Gajanan Alimkar | Thane, Maharashtra | - | - | Registration lapsed |
| NAKHAWA ENCLAVE | Thane, Maharashtra | - | - | Completed |
| SAI SHRUSHTI LEELA | Thane, Maharashtra | 329 | 33% | Registered |
| SHIV SAROVAR HERITAGE | Thane, Maharashtra | 544 | 44% | Registered |
| SAI SHRUSHTI LEELA PHASE III | Thane, Maharashtra | 247 | 2% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| SAI SHRUSHTI HEIGHTS- B1 | 31 Dec 2015 | 11 Jun 2015 | On time |
| SAI SHRUSHTI HEIGHTS- B2 | 31 Dec 2016 | 20 Aug 2015 | On time |
| SAI SHRUSHTI HEIGHTS- B3 | 31 Dec 2016 | 15 Jun 2016 | On time |
| SAI SHRUSHTI RESIDENCY | 31 May 2017 | 17 Jun 2017 | +1 months |
| SAI SHRUSHTI LEELA | 31 Dec 2027 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify SAI SHRUSHTI ENTERPRISES as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with SAI SHRUSHTI ENTERPRISES?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make SAI SHRUSHTI ENTERPRISES unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.