SAI SHRUSHTI ENTERPRISES: RERA track record

GSTIN 27ACKFS0306D1ZH · Partnership · attribution by exact filing name, entity resolution in progress

SAI SHRUSHTI ENTERPRISES has 14 registrations on MahaRERA, including SAI SHRUSHTI HEIGHTS-B4 and SAI SHRUSHTI ANNEX. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Litigation is declared on 1 of its registrations.

14RERA registrations
5Past projects disclosed
on timeMedian delivery slip
1Registrations with litigation
Follow this developer. An email when SAI SHRUSHTI ENTERPRISES registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 14 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
SHIV SAROVAR HERITAGEP51700079256KHIDKALI, Thane, 42120454444%24 Feb 2025Registered
SAI SHRUSHTI LEELA PHASE VPM1330002601558MOUJE PADALE, Thane, 4212043590%14 Aug 2026Registered
SAI SHRUSHTI LEELAP51700078596PADALE, Thane, 42120432933%27 Dec 2024Registered
SAI SHRUSHTI LEELA PHASE IIIPR1330002600117Padale, Thane, 4212042472%17 Apr 2026Registered
NAKHAWA ENCLAVEP51700046673NAUPADA, Thane, 400602--29 Aug 2022Completed
SAI SHRUSHTI ANNEXP51700015209NEAR KHIDKALESHWAR MANDIR, Thane, 400612--8 Feb 2018Completed
SAI SHRUSHTI HEIGHTS-B4P51700000450Thane (M Corp.), Thane, 400612--18 Jul 2017Completed
SAI SHRUSHTI HERITAGEP51700018247DIVA EAST, Thane, 400612--16 Oct 2018Completed
SAI SHRUSHTI SAPPHIREP51700017148DIVA WEST, Thane, 400612--17 Jul 2018Completed
Sai Shrushti Sapphire B-1P51700023096DIVA, Thane, 400612--29 Nov 2019Completed
SAI SHRUSHTI SAPPHIRE PLOT A-1P51700021742DIVA WEST, Thane, 400612--23 Jul 2019Registration lapsed
SAI SHRUSHTI VALLEY - PHASE 1/RAMCHANDRA COMPLEXP51700023900NEAR SAI BABA MANDIR, DAWLE VILLAGE, KHARDI, Thane, 400612--10 Jan 2020Completed
Sai Shrushti Valley - Phase II / Ramchandra ComplexP51700026600Near Sai Baba Mandir Dawale, Thane, 400612--7 Oct 2020Completed
Sai Shrushti Vatika Gajanan AlimkarP51700033427Dawale, Thane, 400612--22 Feb 2022Registration lapsed

What this promoter declares as its own experience

SAI SHRUSHTI ENTERPRISES declares experience on 5 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
SAI SHRUSHTI HEIGHTS- B1
31 Dec 201511 Jun 2015On time
SAI SHRUSHTI HEIGHTS- B2
31 Dec 201620 Aug 2015On time
SAI SHRUSHTI HEIGHTS- B3
31 Dec 201615 Jun 2016On time
SAI SHRUSHTI RESIDENCY
31 May 201717 Jun 2017+1 months
SAI SHRUSHTI LEELA
31 Dec 2027Not completed yetOngoing

Frequently asked questions

How do I verify SAI SHRUSHTI ENTERPRISES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27ACKFS0306D1ZH on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SAI SHRUSHTI ENTERPRISES?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make SAI SHRUSHTI ENTERPRISES unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the SAI SHRUSHTI ENTERPRISES developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.