SAI ENTERPRISES has 14 registrations in this build, including SAI SANSKRUTI and SAI HARMONY. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations.

14Registrations in this build
1Past projects disclosed
no completions yetMedian delivery slip
1Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
SAI SANSKRUTIDadra & Nagar Haveli, Maharashtra--Registration lapsed
SAI HARMONYAurangabad, Maharashtra--Completed
SAI CAPITALPune, Maharashtra--Registration lapsed
SAINANDANPune, Maharashtra--Registration lapsed
SAI PUSHKRAJPune, Maharashtra--Completed
SANSKRUTI PHASE IVRatnagiri, Maharashtra--Completed
SAI SHRUSTIRaigarh, Maharashtra--Completed
Sethia Imperial AvenueMumbai Suburban, Maharashtra453100%Registered
SAI SILVER 44Aurangabad, Maharashtra370%Registration lapsed
SARANGI RESIDENCYPune, Maharashtra--Registration lapsed
CHINTAMANI APARTMENTRatnagiri, Maharashtra--Registration lapsed
SAI BHAKTIRaigarh, Maharashtra--Registration lapsed
SAI PARADISEThane, Maharashtra--Registered
SAI PALACEThane, Maharashtra500%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
GOLDEN PALACE
P51700077297
23 Aug 2027Not completed yetOngoing

Frequently asked questions

How do I verify SAI ENTERPRISES as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SAI ENTERPRISES?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make SAI ENTERPRISES unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.