Provident Housing Limited has 15 registrations on MahaRERA, including Provident Kenvista T1 and Provident Kenvista T2. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 3 of its registrations.

15RERA registrations
2Past projects disclosed
on timeMedian delivery slip
3Registrations with litigation
Follow this developer. An email when Provident Housing Limited registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 15 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Provident Palmvista B1P51700025841-, Thane, 42120430962%20 Jul 2020Registered
Provident Palmvista B2P51700025839-, Thane, 42120418232%20 Jul 2020Registered
Provident Palmvista C1P51700025840-, Thane, 42120418137%20 Jul 2020Registered
Provident Kenvista T2P52100025342-, Pune, 0000008817%30 Apr 2020Registered
Provident Kenvista T1P52100025343-, Pune, 0000008519%30 Apr 2020Registered
Provident Kenvista T10P52100048107o, Pune, 411048--12 Dec 2022Registered
PROVIDENT KENVISTA T11P521000480250, Pune, 411048--7 Dec 2022Registered
Provident Kenvista T12P521000485520, Pune, 411048--6 Jan 2023Registered
Provident Kenvista T3P52100025345-, Pune, 000000--30 Apr 2020Registered
Provident Kenvista T4P52100025344-, Pune, 000000--30 Apr 2020Registered
Provident Palmvista C2P51700025864-, Thane, 421204--23 Jul 2020Registered
Provident Palmvista D1P51700025844-, Thane, 421204--20 Jul 2020Registered
Provident Palmvista D2P51700025854-, Thane, 421204--21 Jul 2020Registered
Provident Palmvista D3P51700025849-, Thane, 421204--20 Jul 2020Registered
Provident Palmvista D4P51700025842-, Thane, 421204--20 Jul 2020Registered

What this promoter declares as its own experience

Provident Housing Limited declares experience on 2 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Provident Sunworth 1
30 Nov 201518 Nov 2015On time
The Tree by Provident
30 Jun 201731 Dec 2016On time

Frequently asked questions

How do I verify Provident Housing Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200KA2008PLC048273 and GSTIN 27AAECP8877D1Z0 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Provident Housing Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Provident Housing Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the Provident Housing Limited developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.