Provident Housing Limited: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Provident Housing Limited has 15 registrations in this build, including Provident Kenvista T1 and Provident Kenvista T2. Its filings disclose 2 earlier MahaRERA projects: 2 of 2 past projects completed on time. Litigation is declared on 3 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Provident Kenvista T1 | Pune, Maharashtra | 85 | 19% | Registered |
| Provident Kenvista T2 | Pune, Maharashtra | 88 | 17% | Registered |
| Provident Kenvista T3 | Pune, Maharashtra | - | - | Registered |
| Provident Kenvista T4 | Pune, Maharashtra | - | - | Registered |
| Provident Palmvista B1 | Thane, Maharashtra | 309 | 62% | Registered |
| Provident Palmvista B2 | Thane, Maharashtra | 182 | 32% | Registered |
| Provident Palmvista C1 | Thane, Maharashtra | 181 | 37% | Registered |
| Provident Palmvista C2 | Thane, Maharashtra | - | - | Registered |
| Provident Palmvista D1 | Thane, Maharashtra | - | - | Registered |
| Provident Palmvista D2 | Thane, Maharashtra | - | - | Registered |
| Provident Palmvista D3 | Thane, Maharashtra | - | - | Registered |
| Provident Palmvista D4 | Thane, Maharashtra | - | - | Registered |
| Provident Kenvista T10 | Pune, Maharashtra | - | - | Registered |
| PROVIDENT KENVISTA T11 | Pune, Maharashtra | - | - | Registered |
| Provident Kenvista T12 | Pune, Maharashtra | - | - | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Provident Sunworth 1 | 30 Nov 2015 | 18 Nov 2015 | On time |
| The Tree by Provident | 30 Jun 2017 | 31 Dec 2016 | On time |
Frequently asked questions
How do I verify Provident Housing Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Provident Housing Limited?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Provident Housing Limited unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.