Home / Developers / Pharande Promoters and Builders

Pharande Promoters and Builders: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Pharande Promoters and Builders has 19 registrations in this build, including L Axis Phase 1 Cluster B and Woodsville Phase 3 Cluster B. Its filings disclose 5 earlier MahaRERA projects: 0 of 5 past projects completed on time.

19Registrations in this build
5Past projects disclosed
+13 monthsMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
L Axis Phase 1 Cluster BPune, Maharashtra--Completed
Woodsville Phase 3 Cluster BPune, Maharashtra--Completed
Woodsville Phase 1 D1 and D3 BuildingsPune, Maharashtra--Completed
Woodsville Phase 3 Cluster CPune, Maharashtra--Completed
L Axis Phase II Cluster APune, Maharashtra--Completed
Felicity Cluster APune, Maharashtra141100%Registration lapsed
101 High StreetPune, Maharashtra--Registration lapsed
L Axis Phase II Cluster BPune, Maharashtra--Registration lapsed
L Axis Commercial CentrePune, Maharashtra--Registered
Vaanya Cluster APune, Maharashtra144100%Registration lapsed
Felicity Cluster BPune, Maharashtra14199%Registered
L Axis Phase II Cluster CPune, Maharashtra96100%Registered
Vaanya Cluster BPune, Maharashtra72100%Registration lapsed
Vaanya Cluster CPune, Maharashtra6997%Registered
Vaanya Cluster DPune, Maharashtra69100%Registered
L Axis Phase III Cluster APune, Maharashtra96100%Registered
Pharande ProwessPune, Maharashtra9972%Registered
L Axis Phase III Cluster BPune, Maharashtra16328%Registered
L-AXIS PHASE III CLUSTER CPune, Maharashtra2100%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Woodsville Phase 1 Cluster A
30 Sep 201220 Dec 2013+15 months
Woodsville Phase 1 Cluster B
1 Jan 20151 Apr 2016+15 months
Woodsville Phase 3
31 Mar 201627 Apr 2017+13 months
L-Axis Phase 1 Part A
31 Mar 201629 Apr 2017+13 months
Woodsville Phase 2
1 Apr 201627 Apr 2017+13 months

Frequently asked questions

How do I verify Pharande Promoters and Builders as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Pharande Promoters and Builders?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.