Neelyog Construction Pvt Ltd: RERA track record
CIN U45200MH1993PTC073168 · GSTIN 27AAACN1792R1ZT · Company · attribution by exact filing name, entity resolution in progress
Neelyog Construction Pvt Ltd has 4 registrations on MahaRERA, including Neelyog Aashiyana and Neelyog Virat -B Wing. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 5 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects by this developer
Showing all 4 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Neelyog Aashiyana IIP51800034106 | KANDIVALI WEST, Mumbai Suburban, 400067 | 60 | 90% | 24 Mar 2022 | Completed |
| Neelyog AashiyanaP51800001136 | Sunderpada, Mumbai Suburban, 400067 | - | - | 26 Jul 2017 | Completed |
| Neelyog Virat -A WingP51800004052 | Dhanjiwadi, Mumbai Suburban, 400097 | - | - | 7 Aug 2017 | Completed |
| Neelyog Virat -B WingP51800003560 | Dhanjiwadi, Mumbai Suburban, 400097 | - | - | 5 Aug 2017 | Completed |
What this promoter declares as its own experience
Neelyog Construction Pvt Ltd declares experience on 5 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.
One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Neelyog Anand | 31 Dec 2015 | 31 Mar 2014 | On time |
| Neelyog Samruddhi Building No 11 A | 31 Dec 2016 | 12 Apr 2017 | +3 months |
| Neelyog Aashiyana | 31 Mar 2022 | 22 Sep 2020 | On time |
| Neelyog Virat B Wing | 31 Dec 2024 | 24 Dec 2020 | On time |
| Neelyog Virat -A Wing P51800004052 | 31 Dec 2025 | 15 Jun 2022 | On time |
Frequently asked questions
How do I verify Neelyog Construction Pvt Ltd as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200MH1993PTC073168 and GSTIN 27AAACN1792R1ZT on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Neelyog Construction Pvt Ltd?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Neelyog Construction Pvt Ltd unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.