MHADA(Nagpur Board): RERA track record
Public Authority ยท attribution by exact filing name, entity resolution in progress
MHADA(Nagpur Board) has 22 registrations in this build, including Construction of 14 Rowhouses at Waddhamna Nagpur and Site No.124, Datala, New Chandrapur. Its filings disclose 6 earlier MahaRERA projects: 1 of 6 past projects completed on time.
Projects in this build
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Construction of 24 Flats under HIGHS at Nandanvan Nagpur | 10 Jul 2014 | 31 Mar 2017 | +33 months |
| 106 T/S MIG | 30 Apr 2015 | 31 Aug 2015 | +4 months |
| construction of 24 HIG Nandanwan Nagpur | 21 Dec 2016 | 31 Mar 2017 | +3 months |
| Construction of 168 EWS 24 MIG 20 shops 10 Office chambers at S No 124 Datala Chandrapur | 5 Apr 2019 | 31 Dec 2019 | +9 months |
| Construction of 106 T/s under MIG, Chandrapur | 6 Apr 2020 | 6 Apr 2020 | On time |
| Construction of 24 flats and 9 row houses at mauza Digdoh, Nagpur p50500028482 | 31 Dec 2023 | 25 Apr 2025 | +16 months |
Frequently asked questions
How do I verify MHADA(Nagpur Board) as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with MHADA(Nagpur Board)?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.