Home / Developers / Meraki Habitats LLP
Meraki Habitats LLP: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
Meraki Habitats LLP has 5 registrations on MahaRERA, including MERAKI ARENA and SABARI SANGAM WING A. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations.
Projects by this developer
Showing all 5 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| One Meraki Wing C and Wing DP51800050796 | Borla, Mumbai Suburban, 400071 | 139 | 34% | 3 May 2023 | Registered |
| One Meraki Wing EP51800077475 | Borla, Mumbai Suburban, 400071 | 16 | 12% | 16 Aug 2024 | Registered |
| MERAKI ARENAP51800007144 | CHEMBUR, Mumbai Suburban, 400071 | - | - | 17 Aug 2017 | Completed |
| ONE MERAKI - Wing A & Wing BP51800011606 | CHEMBUR, Mumbai Suburban, 400071 | - | - | 31 Aug 2017 | Completed |
| SABARI SANGAM WING AP51800001271 | Chembur, Mumbai Suburban, 400088 | - | - | 27 Jul 2017 | Completed |
What this promoter declares as its own experience
Meraki Habitats LLP declares experience on 1 earlier project. One carries a registration number we could match on MahaRERA, under this promoter's own name.
One of these declarations can be compared with the dates that project's own registration holds. It gives the same original completion date that registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| SABARI SANGAM WING A P51800001271 | 31 Dec 2018 | 5 Jul 2018 | On time |
Frequently asked questions
How do I verify Meraki Habitats LLP as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Meraki Habitats LLP?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Meraki Habitats LLP unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.