Home / Developers / MAYFAIR HOUSING PRIVATE LIMITED
MAYFAIR HOUSING PRIVATE LIMITED: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
MAYFAIR HOUSING PRIVATE LIMITED has 5 registrations in this build, including MAYFAIR VISHWARAJA and MAYFAIR AASAAN. Its filings disclose 11 earlier MahaRERA projects: 7 of 11 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| MAYFAIR VISHWARAJA | Thane, Maharashtra | - | - | Completed |
| MAYFAIR AASAAN | Thane, Maharashtra | - | - | Completed |
| SHEEL APARTMENTS BY MAYFAIR | Mumbai Suburban, Maharashtra | - | - | Completed |
| MAYFAIR GNYANADEEP | Mumbai Suburban, Maharashtra | - | - | Completed |
| MAYFAIR BREEZE | Mumbai Suburban, Maharashtra | 109 | 31% | Completed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| MAYFAIR KUMKUM | 22 Jun 2013 | 4 Sep 2013 | +2 months |
| MAYFAIR HERITAGE | 31 Mar 2014 | 24 Sep 2014 | +6 months |
| MAYFAIR BOULEVARD | 29 Jun 2014 | 16 Sep 2014 | +3 months |
| MAYFAIR SERENE | 31 Dec 2014 | 26 Dec 2014 | On time |
| MAYFAIR AKSHAY | 31 Dec 2015 | 17 Dec 2015 | On time |
| MAYFAIR GREENS | 31 Dec 2015 | 17 Mar 2016 | +3 months |
| MAYFAIR SHYAM | 31 Jan 2016 | 1 Sep 2015 | On time |
| MAYFAIR VISHWARAJA BUILDING D AND E | 31 Mar 2016 | 19 Mar 2016 | On time |
| MAYFAIR MYSTIC | 30 Jun 2016 | 29 Jun 2015 | On time |
| MAYFAIR VISHWARAJA BUILDING C | 31 Mar 2017 | 31 Mar 2017 | On time |
| MAYFAIR ASTRAL | 30 Jun 2017 | 9 Mar 2017 | On time |
Frequently asked questions
How do I verify MAYFAIR HOUSING PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with MAYFAIR HOUSING PRIVATE LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.