Home / Developers / CONCRETE DEVELOPERS
CONCRETE DEVELOPERS: RERA track record
GSTIN 27AAAFC6294L1Z3 · Partnership · attribution by exact filing name, entity resolution in progress
CONCRETE DEVELOPERS has 5 registrations on MahaRERA, including NARENDRA HEIGHTS and GOVIND ENCLAVE. Its filings disclose 8 earlier MahaRERA projects: declares 2 of 8 past projects completed on time.
Projects by this developer
Showing all 5 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| SHREERAM SKYLINEPR1190002501677 | KACHIPURA, Nagpur, 440010 | 81 | 6% | 3 Dec 2025 | Registered |
| DEV DATTA HEIGHTSP50500049650 | DHANTOLI, Nagpur, 440012 | 46 | 87% | 22 Feb 2023 | Registered |
| RAGHAV HEALTH STARP50500051632 | RAMDASPETH, Nagpur, 440010 | 24 | 62% | 27 Jun 2023 | Completed |
| GOVIND ENCLAVEP50500024602 | DABHA, NAGPUR, Nagpur, 440023 | - | - | 24 Feb 2020 | Completed |
| NARENDRA HEIGHTSP50500015511 | Narendra Nagar, Nagpur, 440015 | - | - | 7 Mar 2018 | Completed |
What this promoter declares as its own experience
CONCRETE DEVELOPERS declares experience on 8 earlier projects. 4 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
4 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Gauri Heights | 1 May 2015 | 29 Jul 2015 | +3 months |
| Hare Krishna Enclave | 12 Oct 2015 | 18 Dec 2015 | +2 months |
| Vasundhara Enclave | 1 Feb 2016 | 19 Mar 2016 | +2 months |
| Narayana Heights | 13 Jan 2017 | 20 Mar 2017 | +2 months |
| NARENDRA HEIGHTS P50500015511 | 28 Feb 2022 | 18 Jun 2025 | +40 months |
| GOVIND ENCLAVE P50500024602 | 30 Dec 2024 | 31 Mar 2025 | +3 months |
| RAGHAV HEALTH STAR P50500051632 | 31 May 2026 | 3 Oct 2025 | On time |
| DEV DATTA HEIGHTS P50500049650 | 30 Sep 2026 | 31 Oct 2024 | On time |
Frequently asked questions
How do I verify CONCRETE DEVELOPERS as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AAAFC6294L1Z3 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with CONCRETE DEVELOPERS?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.