ReraGenieLog inGet a buyer report

Home / Developers / Aditya Associates

Aditya Associates: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Aditya Associates has 26 registrations in this build, including Thana Co-Op Housing Society Sopan and ADITYA VIHAR. Its filings disclose 7 earlier MahaRERA projects: 4 of 6 past projects completed on time.

26Registrations in this build
7Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Thana Co-Op Housing Society SopanThane, Maharashtra--Completed
ADITYA VIHARPune, Maharashtra--Completed
KAMAL RESIDENCYPune, Maharashtra--Completed
Atmaram SadanThane, Maharashtra--Completed
VRUSHALI VILLAMumbai Suburban, Maharashtra--Registration lapsed
SHUBHAMMumbai Suburban, Maharashtra--Registration lapsed
TILAK NAGAR DAYASAGARMumbai Suburban, Maharashtra--Registration lapsed
Laxmi KeshavThane, Maharashtra--Completed
LITTLE CHERRYPune, Maharashtra--Completed
LOTUSPune, Maharashtra--Completed
SAI VATIKAPune, Maharashtra--Completed
AISHWARYAMPune, Maharashtra--Registration lapsed
SAI KRUPAPune, Maharashtra--Registration lapsed
SHANTI KUNJPune, Maharashtra--Registration lapsed
SAI PLAZAPune, Maharashtra--Registration lapsed
Satyajit Co-Op Housing Society Ltd.Thane, Maharashtra--Completed
SanyogThane, Maharashtra--Completed
Pankaj Co-Op Housing Society Ltd.Thane, Maharashtra--Completed
Madhu Milind Co-Op Housing Society LtdThane, Maharashtra--Completed
HundiwaleThane, Maharashtra--Completed
Phatak WadaThane, Maharashtra5816%Registration lapsed
SAI PARADISEPune, Maharashtra4676%Registered
Rameshwar Co-Op Housing Society Ltd.Thane, Maharashtra6912%Registered
Arvind Co-Op Housing Society LtdThane, Maharashtra240%Registered
SONAIPune, Maharashtra3040%Registered
Deepjyoti Co. Op. Housing SocietyThane, Maharashtra470%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Vrundavan
31 Dec 201218 Nov 2013+11 months
Yashodeep
2 Jun 201319 Dec 2013+7 months
BHARAT SADAN
6 Aug 201519 Nov 2014On time
LAXMI POORAM
30 Jun 201630 Jun 2016On time
KAMATHE TOWER
5 Aug 201727 Sep 2016On time
Gauri
31 Aug 201710 Sep 2012On time
Rameshwar Co-Op Housing Society Ltd.
P51700053476
10 Mar 2027Not completed yetOngoing

Frequently asked questions

How do I verify Aditya Associates as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Aditya Associates?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.