New projects and RERA data in Vijayapura district, Karnataka
56 projects are registered in Vijayapura district: 2,916 units across the 6 that file a count, 0 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 56 covered registrations, 12 have revised their promised completion date and 0 declare litigation. Every figure comes from the projects' own RERA Karnataka filings.
How far Vijayapura possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 12 of 56 projects (21%) have moved at least once; the median move is 9 months and the longest is 12 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Where in Vijayapura: projects by taluka
56 of the 56 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Bijapur | 45 | 80% |
| Basavan Bagevadi | 2 | 4% |
| Indi | 2 | 4% |
| Muddebihal | 2 | 4% |
| Talikota | 2 | 4% |
| 3 other talukas | 3 | 5% |
Projects in Vijayapura
Showing all 56 projects.
Largest first, by the unit count in the filing.
Developers active in Vijayapura
Karnataka Slum Development Board (12), SVAMITVA INFRA PVT LTD (6), V G Parekh and Co (5), Runwal Infrastructure Pvt Ltd (4), SVAMITVA INFRA PRIVATE LIMITED (3), V G PAREKH & CO. (2). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Vijayapura projects listed above?
Compare each project against its neighbours, not against the brochure. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Vijayapura project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What if a Vijayapura project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.