Home / Browse projects / Vijayapura, Karnataka / SHUBH GRUH APPARTMENTS

Registration approved Residential/Group Housing project

SHUBH GRUH APPARTMENTS

By V G PAREKH & CO.

RG-KA-92742 · RERA PRM/KA/RERA/1275/448/PR/181010/002047

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jul 2021Possession promisedmoved 6 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 72 documents Report an error

SHUBH GRUH APPARTMENTS is a Residential/Group Housing project by V G PAREKH & CO. in Vijayapura, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1275/448/PR/181010/002047 on 10 Oct 2018. Possession is promised by 15 Jul 2021. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameSHUBH GRUH APPARTMENTS
  • TypeResidential/Group Housing
  • Location
    • Bijapur
    • Vijayapura
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1275/448/PR/181010/002047
  • ReraGenie IDRG-KA-92742

Builder

  • NameV G PAREKH & CO.
  • Entity typePartnership Firm
  • Authorized SignatoryMAHAVEERCHAND PAREKH
  • Other registrations1 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2018First promiseJan 2021Revised toJul 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Oct 2018
  • Promised completion15 Jul 2021
  • Revised completionRevised to 15 Jul 2021 (originally 15 Jan 2021)
  • Buildings7 building records
  • Documents filed72 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHUBH GRUH APARTMENT TOWER NO 1---16016
SHUBH GRUH APARTMENT TOWER NO 2---16016
SHUBH GRUH APARTMENT TOWER NO 3---16016
SHUBH GRUH APARTMENT TOWER NO 4---16016
SHUBH GRUH APARTMENT TOWER NO 5---16016
SHUBH GRUH APARTMENT TOWER NO 6---16016
SHUBH GRUH APARTMENT TOWER NO 7---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities37

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,456 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.20 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAVIKUMAR BADIGER
EngineerRAVIKUMAR BADIGER

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJan 2021 → Jul 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed72

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1275/448/PR/181010/002047 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: V G Co.pdf-
Architect Certificate for Work Completion Schedule till DateFile: BROCHER.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: BROCHER.pdf-
CA Certificate for Funds UtilizationFile: BROCHER.pdf-
Architect Certificate for Pending Work Completion Schedule.File: BROCHER.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: BROCHER.pdf-
CA Certificate for Funds required for Project CompletionFile: BROCHER.pdf-
AffidavitFile: BROCHER.pdf-
Latest Encumbrance CertificateFile: BROCHER.pdf-
Details Of Sold/ Un-sold UnitsFile: BROCHER.pdf-
CMC COVER RE-
DRAWING PLAN (1)-
layout-
SALE DEED RE-
APPLICATION FORM-
slae deed and rtc-
DRAWING PLAN (1)-
layout-
PROVISIONAL ALLOTMENT LETTER-
Brochure-
specification-
EC-
merged utare-
JDA-
Partnership Deed-
DC OFFICE RE-
CC re-
N A-
N A-
N A-
N A-
N A-
N A-
N A-
N A-
N A-
N A-
N A-
Unnamed document-
N A-
N A-
N A-
N A-
DC OFFICE RE-
N A-
stability-
DRAWING PLAN (1)-
layout-
DRAWING PLAN (1)-
KGP RE-
ADVOCATE SEARCH REPORT-
Balance Sheet 2016 - 2017File: Balance Sheet 16-17.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 15-16.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet 14-15.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & Loss 16-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss 15-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit & Loss 14-15.pdf-
Director's Report 2016 - 2017File: 3.jpeg-
Director's Report 2015 - 2016File: 4.jpeg-
Director's Report 2014 - 2015File: 3.jpeg-
Cash Flow Statement 2016 - 2017File: 4.jpeg-
Cash Flow Statement 2015 - 2016File: 4.jpeg-
Auditor's Report 2016 - 2017File: Audit Report 16-17.pdf-
Auditor's Report 2015 - 2016File: Audit Report AY 15-16.pdf-
Auditor's Report 2014 - 2015File: Audit Report AY14-15.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR2017-18.jpeg-
Income Tax Return Acknowledgement 2015 - 2016File: ITR2016-17.jpeg-
Income Tax Return Acknowledgement 2014 - 2015File: ITR2015-16.jpeg-
52337 tax paid-
Tower Excel SheetFile: PRMKARERA1275448PR181010002047 (1).xlsx-
Occupancy CertificateFile: Combined Completion Certificate- Shubh Gruh.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: AFFID AVIT CUM DECLARATION.pdf-

How this compares with Vijayapura

21%of Vijayapura projects moved their completion datethis one moved by 6 months
0%of Vijayapura registrations are shown as withdrawn or revokedthis one is not

Computed across the 56 Vijayapura projects on ReraGenie, from their own filings.

Keep SHUBH GRUH APPARTMENTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vijayapura56 in Vijayapura

Builder: V G PAREKH & CO.

V.G.Parekh & Co has 2 registrations on RERA Karnataka, including Shubh Gruh and SHUBH GRUH APPARTMENTS. Its filings declare 4 earlier projects, 4 of them declared completed. Read the full track record. See more projects on the Vijayapura district page.

Frequently asked questions

What are my rights if SHUBH GRUH APPARTMENTS is delayed beyond 15 Jul 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHUBH GRUH APPARTMENTS?

The registered promoter entity is V G PAREKH & CO., a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHUBH GRUH APPARTMENTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHUBH GRUH APPARTMENTS?

The professionals named in the filing: Architect: RAVIKUMAR BADIGER; Engineer: RAVIKUMAR BADIGER. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUBH GRUH APPARTMENTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUBH GRUH APPARTMENTS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUBH GRUH APPARTMENTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.