New projects and RERA data in Bharuch district, Gujarat

201 projects are registered in Bharuch district: 31,421 units across the 200 that file a count, 14 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

201Projects covered
14Registered, last 12 months
31,421Units declared
42Completion dates revised

Of the 201 covered registrations, 42 have revised their promised completion date. Of the 194 that file a booking figure, the median is 52% booked as of the current data. Every figure comes from the projects' own GujRERA filings.

How far Bharuch possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 42 of 201 projects (21%) have moved at least once; the median move is 12 months and the longest is 48 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

06121825Originally due 2018: 2 projects kept the original date, 33% of the yearOriginally due 2018: 3 projects moved by under 2 years, 50% of the yearOriginally due 2018: 1 projects moved by 2 years or more, 17% of the year’18Originally due 2019: 2 projects kept the original date, 33% of the yearOriginally due 2019: 3 projects moved by under 2 years, 50% of the yearOriginally due 2019: 1 projects moved by 2 years or more, 17% of the year’19Originally due 2020: 3 projects kept the original date, 43% of the yearOriginally due 2020: 2 projects moved by under 2 years, 29% of the yearOriginally due 2020: 2 projects moved by 2 years or more, 29% of the year’20Originally due 2021: 3 projects kept the original date, 60% of the yearOriginally due 2021: 1 projects moved by under 2 years, 20% of the yearOriginally due 2021: 1 projects moved by 2 years or more, 20% of the year’21Originally due 2022: 13 projects kept the original date, 81% of the yearOriginally due 2022: 3 projects moved by 2 years or more, 19% of the year’22Originally due 2023: 10 projects kept the original date, 77% of the yearOriginally due 2023: 1 projects moved by under 2 years, 8% of the yearOriginally due 2023: 2 projects moved by 2 years or more, 15% of the year’23Originally due 2024: 7 projects kept the original date, 35% of the yearOriginally due 2024: 7 projects moved by under 2 years, 35% of the yearOriginally due 2024: 6 projects moved by 2 years or more, 30% of the year’24Originally due 2025: 19 projects kept the original date, 79% of the yearOriginally due 2025: 5 projects moved by under 2 years, 21% of the year’25Originally due 2026: 6 projects kept the original date, 60% of the yearOriginally due 2026: 4 projects moved by under 2 years, 40% of the year’26Originally due 2027: 19 projects kept the original date, 100% of the year’27Originally due 2028: 24 projects kept the original date, 100% of the year’28Originally due 2029: 24 projects kept the original date, 100% of the year’29Originally due 2030: 18 projects kept the original date, 100% of the year’30Originally due 2031: 6 projects kept the original date, 100% of the year’31Originally due 2032: 2 projects kept the original date, 100% of the year’32Originally due 2033: 1 projects kept the original date, 100% of the year’33

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

01,2502,5003,7505,000Originally due 2018: 225 flats kept the original date, 33% of the yearOriginally due 2018: 357 flats moved by under 2 years, 50% of the yearOriginally due 2018: 108 flats moved by 2 years or more, 17% of the year’18Originally due 2019: 367 flats kept the original date, 33% of the yearOriginally due 2019: 340 flats moved by under 2 years, 50% of the yearOriginally due 2019: 85 flats moved by 2 years or more, 17% of the year’19Originally due 2020: 320 flats kept the original date, 43% of the yearOriginally due 2020: 166 flats moved by under 2 years, 29% of the yearOriginally due 2020: 50 flats moved by 2 years or more, 29% of the year’20Originally due 2021: 477 flats kept the original date, 60% of the yearOriginally due 2021: 134 flats moved by under 2 years, 20% of the yearOriginally due 2021: 155 flats moved by 2 years or more, 20% of the year’21Originally due 2022: 1,843 flats kept the original date, 81% of the yearOriginally due 2022: 308 flats moved by 2 years or more, 19% of the year’22Originally due 2023: 1,492 flats kept the original date, 77% of the yearOriginally due 2023: 86 flats moved by under 2 years, 8% of the yearOriginally due 2023: 572 flats moved by 2 years or more, 15% of the year’23Originally due 2024: 1,191 flats kept the original date, 35% of the yearOriginally due 2024: 1,394 flats moved by under 2 years, 35% of the yearOriginally due 2024: 1,127 flats moved by 2 years or more, 30% of the year’24Originally due 2025: 3,158 flats kept the original date, 79% of the yearOriginally due 2025: 727 flats moved by under 2 years, 21% of the year’25Originally due 2026: 1,316 flats kept the original date, 60% of the yearOriginally due 2026: 499 flats moved by under 2 years, 40% of the year’26Originally due 2027: 2,388 flats kept the original date, 100% of the year’27Originally due 2028: 3,228 flats kept the original date, 100% of the year’28Originally due 2029: 4,099 flats kept the original date, 100% of the year’29Originally due 2030: 2,642 flats kept the original date, 100% of the year’30Originally due 2031: 1,716 flats kept the original date, 100% of the year’31Originally due 2032: 419 flats kept the original date, 100% of the year’32Originally due 2033: 432 flats kept the original date, 100% of the year’33

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Where in Bharuch: projects by taluka

201 of the 201 registrations on this page name their taluka.

TalukaProjectsShare
Bharuch15477%
Anklesvar4321%
4 other talukas42%

Projects in Bharuch

Showing 1 to 60 of 201 projects.

Largest first, by the unit count in the filing.

ProjectDeveloperUnitsBookedRegisteredStatus
R K COUNTYJhadeshwar, 392001SHREE SAI KRUPA CREATION87298%21 Sep 2017Valid until 30 Sep 2022
SHARNAM SKYSHUBH INFRA62920%6 Mar 2023Valid until 30 Apr 2029
SAHJANAND LUXURIAUmraj, 392001SAHJANAND BUILD SQUARE LLP59888%17 Oct 2019Valid until 30 Jun 2028
TULSI GLORIOUSSAHJANAND ENTERPRISE49528%17 Dec 2022Valid until 30 Apr 2031
CITY CENTERKasak, 392001DRA NARMADA BUSPORT PRIVATE LIMITED45630%12 Sep 2019Valid until 29 Jun 2025
RANG EMPIRECHAVAJAVDHOOT INFRA44545%19 Jun 2023Valid until 31 Jul 2030
WELL TRADE CENTERAALI, 392001WELLWORTH INFRASTRUCTURE AND DEVELOPMENT PRIVATE LIMITED4320%17 Oct 2026Valid until 31 Dec 2033
GOLDEN RESIDENCYTavraTAVRA ENTERPRISE43094%18 Jun 2020Valid until 30 Jun 2026
SHIVALIK HEIGHTSTavra, 392011KHENI INFRA422100%10 May 2018Valid until 30 Sep 2023
APPLE PLAZAAnkleshwar, 393001SHUBHAM ENTERPRISE42149%17 Oct 2018Valid until 30 May 2024
R K GLORIASHREE SAIKRUPA REAL ESTATE VENTURES41088%17 Jun 2021Valid until 30 Dec 2026
RANG EMPIRE 2CHAVAJ, 392015AVDHOOT INFRA-240615%2 Jun 2025Valid until 28 Jun 2030
SHYAM RICHMONDUmaraj, 392001JALARAM DEVELOPERS3796%25 Oct 2024Valid until 30 Apr 2029
SAI HEAVENPropritorship of SHIVSAI CONSTRUCTION37269%10 Aug 2022Valid until 30 Apr 2028
SAHJANAND EMPIRENANDELAV, 392015SAHJANAND EMPIRE36826%20 May 2024Valid until 30 Apr 2031
VIVANTA SKY TOWERS (PHASE-01)NANDELAV, 392015YOG ASSOCIATES3473%2 Sep 2024Valid until 30 Oct 2029
GANESH NANDANM & M ASSOCIATES33966%16 Jul 2021Valid until 30 Apr 2027
RK Elinora Phase-lZadeshwar, 392011SHREE SAI DEEP ENTERPRISE33056%26 Dec 2022Valid until 31 Mar 2025
MAA RESIDENCYRahadporGRM CONSTRUCTION32863%24 Aug 2020Valid until 29 Oct 2027
SARTHI HEIGHTSARTHI INFRA32744%27 Apr 2023Valid until 31 Jul 2028
RANG SKYCITYSAIASHISH DEVELOPERS31755%30 Oct 2018Valid until 30 Sep 2026
AGRIM HEIGHTSAGRIM ENTERPRISE30597%30 Jan 2021Valid until 31 Dec 2025
NILKANTH VILLAAnkleshwar, 393020ANJANI DEVELOPER295100%7 Mar 2018Valid until 31 Jan 2029
RANG CITY FLATSChavaj, 392020AVDHOOT BUILDERS28852%24 Jan 2019Valid until 30 Sep 2026
SHIVALIK RIVERAZADESHWAR, 392011KHENI INFRA28815%16 Mar 2024Valid until 31 Jul 2030
SHREE UMANG LAXMI RESIDENCYKosamadi, 393001Propritorship of DOLATBHAI DEVJIBHAI VANJARA (PROP. OF GEHLOT ENTERPRISE)28621%5 Mar 2018Valid until 30 Jun 2024
MATRUCHHYA RESIDENCYTavra, 392011BHAVYA ENTERPRISE28265%23 Jan 2018Valid until 30 Apr 2023
SARJAN TOWERSAKSHI CORPORATION27271%21 May 2021Valid until 31 Mar 2025
NARAYAN ARENAUmraj, 392001NARAYAN LAND ESTATE26988%21 Nov 2017Valid until 30 Mar 2022
R K CELESTIALSHREE SAIKRUPA INFRA DEVELOPERS26841%1 May 2023Valid until 30 Apr 2027
GOLDEN LUXURIATAVRA DEVELOPERS26052%2 Mar 2023Valid until 30 Apr 2028
ATHARV GREENZADESHWAR, 392011Veer Developers2580%13 Oct 2026Valid until 31 Mar 2031
CELEBRATION LUXURIAKOSAMDI, 393001VARNI INFRA2560%17 Feb 2026Valid until 28 Feb 2031
SARJAN TOWERBHADKODRASAKSHI CORPORATION2561%6 Nov 2023Valid until 30 Apr 2030
AKSHAR ICONSAndada, 393010AKSHAR INFRA25462%26 Feb 2018Valid until 30 Sep 2020
7X LANDMARKTAVRA, 393001LANDMARKK REALITY2510%8 Oct 2025Valid until 31 Jul 2032
GOLDEN SQUAREBholav, 392001BHOLAV ENTERPRISE25057%26 Feb 2018Valid until 16 Dec 2021
7-X RIVERATavraPRIYANKA DEVELOPERS24680%17 Dec 2019Valid until 30 Sep 2025
VENEZIA BELLIZAJHADESHWAR, 392015SHREE RAM INFRA24413%4 Nov 2025Valid until 30 Apr 2031
AAROHI HEIGHTSAAROHI ENTERPRISE24173%22 Mar 2022Valid until 31 Mar 2027
SAMRUDDHI RESIDENCYSANSKRUT INFRACON PRIVATE LIMITED24048%6 Feb 2021Valid until 31 Mar 2027
VENEZIA SKYJ B ENTERPRISE23697%9 Nov 2020Valid until 31 Dec 2025
SHARNAM RESIDENCYZadeshwar, 392001MANOJKUMAR PANNALAL SHAH230100%3 Nov 2017Valid until 30 Sep 2025
SHAMIYANA PARKUmraj, 392020SEJALKUMAR PANNALAL SHAH22653%27 Dec 2017Valid until 30 Sep 2027
TULSI VILLA / SQUAREAnkleshwar, 393001KARUNANIDHI DEVELOPERS22278%22 Oct 2018Valid until 28 Feb 2026
THE MAPLE SQUARETavraTIRUMALA ENTERPRISE21727%12 Mar 2020Valid until 30 Jun 2026
SOLITAIRE PALLAZZOTAVARA, 392002Propritorship of KIRAN KRISHNAKANT MAJMUDAR SOLE PROPRIETOR OF BHUMI DEVELOPERS2160%15 Jul 2025Valid until 31 Jul 2029
ASOPALAV RESIDENCYSarangpur, 393002CHHAGANBHAI ODHABHAI GOTI AND ETC21148%6 Jun 2018Valid until 15 Jul 2023
YOGI HEIGHTSKOSAMDI, 393001YOGI BUILDCON20615%12 Jun 2025Valid until 31 Dec 2029
THE MAPLE SKYDECKKUBER ENTERPRISE20483%23 Jul 2021Valid until 31 Dec 2026
TULSI HOMESSAHJANAND ENTERPRISE20499%15 Sep 2021Valid until 30 Jun 2026
Al-Karim HeightsSKY DEVELOPER1962%14 Jul 2022Valid until 31 Dec 2026
7X EleganceAGRAWAL DEVELOPERS19447%18 Apr 2023Valid until 31 Jul 2028
CELEBRATION HEIGHTSKosamdiVARNI INFRA19498%7 May 2021Valid until 31 Dec 2025
GOLDEN NIRVANASurvadi, 393001DWARKESH DEVELOPERS19331%18 Sep 2024Valid until 30 Apr 2030
VIVANTA THE GRANDEURYOG ASSOCIATES19294%6 Feb 2021Valid until 1 Dec 2025
RUDRAKSH GALLERIAANKLESHWAR, 393001MAA DEVELOPERS1915%18 May 2024Valid until 30 Apr 2029
NEXUS BUSINESS HUBMojampur, 392001SHREEM DEVELOPERS18775%29 Jan 2018Valid until 30 Jun 2019
Ambey Valley TownshipKosamdi, 393001AMBEY VALLEY ENTERPRISES184100%16 Feb 2019Valid until 30 Jun 2025
MANNAT RESIDENCYDYNAMIC SOLUTION CORPORATION18474%19 Mar 2022Valid until 31 Dec 2025

Developers active in Bharuch

OM DEVELOPERS (5), PP & SONS (5), Propritorship of RAMESHBHAI VALLABHBHAI SAVANI (5), KHENI INFRA (4), NARAYAN LAND ESTATE (4), YOG ASSOCIATES (3). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Bharuch projects listed above?

Compare each project against its neighbours, not against the brochure. Of the 194 projects on this page that file a booking figure, the median is 52% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Bharuch project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What if a Bharuch project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own GujRERA filings, and we read every report.

Report an errorShare feedback

Data from official GujRERA filings.