SHARNAM RESIDENCY is a Mixed Development project by MANOJKUMAR PANNALAL SHAH in Bharuch, Gujarat, registered with GujRERA as PR/GJ/BHARUCH/BHARUCH/Others/MAA00590/031117 on 3 Nov 2017. Possession is promised by 30 Sep 2025. 230 of the 230 units on this registration are recorded sold or booked, and 76 of 81 construction stages are filed complete.
At a glance
Project
- NameSHARNAM RESIDENCY
- TypeMixed Development
- Location
- 142/1+3 ZADESHWAR BHARUCH
- ZADESHWAR BHARUCH
- Zadeshwar
- Bharuch
- 392001
- Pincode392001
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/BHARUCH/BHARUCH/Others/MAA00590/031117
- ReraGenie IDRG-GJ-51669
Builder
- NameMANOJKUMAR PANNALAL SHAH
- Entity typeIndividual/Propritorship
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Sep 2025
- Registered on3 Nov 2017
- Promised completion30 Sep 2025
- Revised completionNone
- Buildings9 building records
- Documents filed47 files
Current status
Figures as on 12 Aug 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| K | - | - | - | 23 | 1 | 24 |
| A | - | - | - | 27 | 9 | 36 |
| B+C | - | - | - | 40 | 0 | 40 |
| D | - | - | - | 20 | 0 | 20 |
| E | - | - | - | 20 | 0 | 20 |
| F | - | - | - | 10 | 0 | 10 |
| G | - | - | - | 20 | 0 | 20 |
| H | - | - | - | 20 | 0 | 20 |
| I+J | - | - | - | 40 | 0 | 40 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building9
As on 12 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
76 of 81 construction stages are filed complete across 9 buildings. The stage furthest along is Plinth, at 0%.
K89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
B+C89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
D89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
G100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
H89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
I+J89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 12 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 100% |
| Letter box | Yes | 100% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 3.21 cr | Rs 3.21 cr |
| B+C | NA | Rs 3.21 cr | Rs 3.21 cr |
| D | NA | Rs 3.21 cr | Rs 3.21 cr |
| E | NA | Rs 3.21 cr | Rs 3.21 cr |
| F | NA | Rs 3.21 cr | Rs 3.21 cr |
| G | NA | Rs 3.21 cr | Rs 3.21 cr |
| H | NA | Rs 3.21 cr | Rs 3.21 cr |
| I+J | NA | Rs 3.21 cr | Rs 3.21 cr |
| K | NA | Rs 3.21 cr | Rs 3.21 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SURESH RAJPUT |
| Engineer | ANIL MISTRY |
Documents filed47
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/BHARUCH/BHARUCH/Others/MAA00590/031117 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 12 Aug 2025 |
| Architect's certificate (Form 1) | 8 Aug 2025 |
| Site photograph, K | 26 Jul 2025 |
| Site photograph, A | 26 Jul 2025 |
| Site photograph, B+C | 26 Jul 2025 |
| Site photograph, D | 26 Jul 2025 |
| Site photograph, E | 26 Jul 2025 |
| Site photograph, F | 26 Jul 2025 |
| Site photograph, G | 26 Jul 2025 |
| Site photograph, H | 26 Jul 2025 |
| Site photograph, I+J | 26 Jul 2025 |
| Site photograph, I+J | 26 Jul 2025 |
| Engineer's certificate (Form 2) | 5 Jul 2024 |
| Engineer's certificate annexure | 5 Jul 2024 |
| RERA registration certificate | 3 Nov 2017 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bharuch
Computed across the 200+ Bharuch projects on ReraGenie, from their own filings.
Keep SHARNAM RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Zadeshwar200+ in Bharuch
Filed coordinates, straight-line distance. 45 registered projects within 2 km.
R K COUNTY
SHREE SAI KRUPA CREATION
SAHJANAND LUXURIA
SAHJANAND BUILD SQUARE LLP
CITY CENTER
DRA NARMADA BUSPORT PRIVATE LIMITED
WELL TRADE CENTER
WELLWORTH INFRASTRUCTURE AND DEVELOPMENT P
SHYAM RICHMOND
JALARAM DEVELOPERS
NARAYAN ARENA
NARAYAN LAND ESTATE
See every Bharuch project, with the district possession charts
Builder: MANOJKUMAR PANNALAL SHAH
MANOJKUMAR PANNALAL SHAH has 2 registrations on GujRERA, including SHARNAM RESIDENCY and SHILPI SANGINI. Read the full track record. See more projects on the Bharuch district page.
Frequently asked questions
What are my rights if SHARNAM RESIDENCY is delayed beyond 30 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SHARNAM RESIDENCY?
The registered promoter entity is MANOJKUMAR PANNALAL SHAH, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SHARNAM RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHARNAM RESIDENCY?
The professionals named in the filing: Architect: SURESH RAJPUT; Engineer: ANIL MISTRY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHARNAM RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.