313 projects are registered in Anand district: 14,485 units across the 312 that file a count, 22 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

313Projects covered
22Registered, last 12 months
14,485Units declared
56Completion dates revised

Of the 313 covered registrations, 56 have revised their promised completion date. Of the 308 that file a booking figure, the median is 57% booked as of the current data. Every figure comes from the projects' own GujRERA filings.

How far Anand possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 56 of 313 projects (18%) have moved at least once; the median move is 12 months and the longest is 60 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

0255075100Originally due 2018: 1 projects kept the original date, 33% of the yearOriginally due 2018: 2 projects moved by under 2 years, 67% of the year’18Originally due 2019: 5 projects kept the original date, 42% of the yearOriginally due 2019: 6 projects moved by under 2 years, 50% of the yearOriginally due 2019: 1 projects moved by 2 years or more, 8% of the year’19Originally due 2020: 9 projects kept the original date, 64% of the yearOriginally due 2020: 5 projects moved by under 2 years, 36% of the year’20Originally due 2021: 18 projects kept the original date, 72% of the yearOriginally due 2021: 5 projects moved by under 2 years, 20% of the yearOriginally due 2021: 2 projects moved by 2 years or more, 8% of the year’21Originally due 2022: 21 projects kept the original date, 84% of the yearOriginally due 2022: 3 projects moved by under 2 years, 12% of the yearOriginally due 2022: 1 projects moved by 2 years or more, 4% of the year’22Originally due 2023: 21 projects kept the original date, 68% of the yearOriginally due 2023: 7 projects moved by under 2 years, 23% of the yearOriginally due 2023: 3 projects moved by 2 years or more, 10% of the year’23Originally due 2024: 29 projects kept the original date, 78% of the yearOriginally due 2024: 4 projects moved by under 2 years, 11% of the yearOriginally due 2024: 4 projects moved by 2 years or more, 11% of the year’24Originally due 2025: 46 projects kept the original date, 84% of the yearOriginally due 2025: 7 projects moved by under 2 years, 13% of the yearOriginally due 2025: 2 projects moved by 2 years or more, 4% of the year’25Originally due 2026: 20 projects kept the original date, 83% of the yearOriginally due 2026: 4 projects moved by under 2 years, 17% of the year’26Originally due 2027: 26 projects kept the original date, 100% of the year’27Originally due 2028: 28 projects kept the original date, 100% of the year’28Originally due 2029: 20 projects kept the original date, 100% of the year’29Originally due 2030: 11 projects kept the original date, 100% of the year’30Originally due 2031: 1 projects kept the original date, 100% of the year’31Originally due 2032: 1 projects kept the original date, 100% of the year’32

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

01,2502,5003,7505,000Originally due 2018: 20 flats kept the original date, 33% of the yearOriginally due 2018: 35 flats moved by under 2 years, 67% of the year’18Originally due 2019: 165 flats kept the original date, 42% of the yearOriginally due 2019: 222 flats moved by under 2 years, 50% of the yearOriginally due 2019: 23 flats moved by 2 years or more, 8% of the year’19Originally due 2020: 213 flats kept the original date, 64% of the yearOriginally due 2020: 163 flats moved by under 2 years, 36% of the year’20Originally due 2021: 675 flats kept the original date, 72% of the yearOriginally due 2021: 189 flats moved by under 2 years, 20% of the yearOriginally due 2021: 421 flats moved by 2 years or more, 8% of the year’21Originally due 2022: 769 flats kept the original date, 84% of the yearOriginally due 2022: 390 flats moved by under 2 years, 12% of the yearOriginally due 2022: 133 flats moved by 2 years or more, 4% of the year’22Originally due 2023: 617 flats kept the original date, 68% of the yearOriginally due 2023: 375 flats moved by under 2 years, 23% of the yearOriginally due 2023: 247 flats moved by 2 years or more, 10% of the year’23Originally due 2024: 1,563 flats kept the original date, 78% of the yearOriginally due 2024: 146 flats moved by under 2 years, 11% of the yearOriginally due 2024: 116 flats moved by 2 years or more, 11% of the year’24Originally due 2025: 2,118 flats kept the original date, 84% of the yearOriginally due 2025: 480 flats moved by under 2 years, 13% of the yearOriginally due 2025: 96 flats moved by 2 years or more, 4% of the year’25Originally due 2026: 1,346 flats kept the original date, 83% of the yearOriginally due 2026: 216 flats moved by under 2 years, 17% of the year’26Originally due 2027: 705 flats kept the original date, 100% of the year’27Originally due 2028: 1,078 flats kept the original date, 100% of the year’28Originally due 2029: 1,009 flats kept the original date, 100% of the year’29Originally due 2030: 591 flats kept the original date, 100% of the year’30Originally due 2031: 16 flats kept the original date, 100% of the year’31Originally due 2032: 348 flats kept the original date, 100% of the year’32

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Where in Anand: projects by taluka

313 of the 313 registrations on this page name their taluka.

TalukaProjectsShare
Anand27889%
Umreth186%
Borsad124%
3 other talukas52%

Projects in Anand

Showing 1 to 60 of 313 projects.

Largest first, by the unit count in the filing.

ProjectDeveloperUnitsBookedRegisteredStatus
SUKIRTAN FLORAKaramsad, 388121SHAKTI INFRACON41695%23 Sep 2019Valid until 30 Jun 2026
Svayam Symphony & Svayam SapphireKaramsad, 388120Radheshyam Developers35843%7 Jul 2018Valid until 25 Jul 2026
SUKIRTAN REGALIAKARAMSAD, 388325SHAKTI BUILDERS34838%5 Aug 2024Valid until 30 Apr 2032
Royal HeightAnand, 388001Royal Height Land Developers26024%23 Oct 2018Valid until 1 Jun 2023
SHALIGRAM GREENS IISHREEJI DEVELOPERS22446%18 Jun 2021Valid until 28 May 2026
ATMIYA FIELDSPACEKARAMSAD, 388345ATMIYA FIELDSPACE19523%10 Jun 2024Valid until 30 Apr 2030
EARTH ICONDREAMLAND ASSOCIATES19547%14 Jul 2022Valid until 31 Dec 2026
SHAAN AV FORTUNEKARAMSAD, 388120DIYA DEVELOPERS19315%13 Jun 2019Valid until 30 Sep 2024
H R PRIMEAnandHIRENKUMAR PATEL PROPRIETOR OF H. R. DEVELOPERS17518%4 Jan 2020Valid until 30 Jun 2026
JANTA COMPLEXKARAMSAD, 388001DREAMLAND ASSOCIATES1610%16 Mar 2026Valid until 31 Dec 2028
NARAYAN EMPIREAnandNARAYAN BUILDCON160100%2 Dec 2020Valid until 31 Dec 2024
AMBE FLATSAnand, 388001MEHUL PATEL PROPRIETOR OF SHREE AMBICA DEVELOPERS15477%30 Apr 2019Valid until 30 Dec 2026
Sukirtan AuraKaramsadSHAKTI BUILDERS15380%23 Sep 2020Valid until 24 Jul 2025
LEGACY ENCLAVEHARI DEVELOPERS14435%11 Jun 2021Valid until 31 Dec 2024
RAGHUKUL PARISAR - 3KARAMSAD, 388325PURANSINGH RAMSINGH RATHORE (PROP. OF RAGHUKUL BUILDERS)13798%7 Mar 2024Valid until 31 Jul 2029
Shiv IconBorsad, 388540Pramukh Associates13336%11 Jul 2019Valid until 18 May 2027
Shree Ram AnandAnandSHRI RAM BUILDERS13177%24 Dec 2019Valid until 30 Jun 2024
RUDVEDAJITENDRA RATILAL PRAJAPATI (Prop. Of LR Realty)12779%4 Jun 2021Valid until 30 Sep 2025
SHREE BALAJI AVENUEBorsad, 388540SAROJBEN CHANDRAKANT PRAJAPATI1192%4 Apr 2019Valid until 30 Mar 2025
VISAMO LUXURIASHYAMRIYA PROJECTS LLP11228%7 Jun 2021Valid until 31 Dec 2025
RAGHUKUL PRAVESHKARAMSAD, 388315PURANSINGH RAMSINGH RATHORE (PROP. OF RAGHUKUL BUILDERS)10557%1 Apr 2024Valid until 31 Jul 2029
Veer EleganceKARAMSAD, 388325KUSHAL VINODKUMAR BHATT AND OTHERS1050%6 May 2025Valid until 31 Dec 2027
ATMIYA EMPIREATMIYA EMPIRE ASSOCIATES10360%29 Dec 2021Valid until 30 Apr 2029
LAKSH NEELAKASHANANTA BUILDCON1000%16 Nov 2023Valid until 31 Dec 2029
AAKAR CITY CENTERBIPINBHAI HIMABHAI PATEL9990%31 Mar 2022Valid until 31 Mar 2025
BOMBAY MALLAnandPINNACLE BUILD AND INFRA LLP980%29 Jan 2020Valid until 30 Dec 2023
ATMIYA SKYKaramsad, 388325ATMIYA FIELDCON PRIVATE LIMITED9665%30 Aug 2019Valid until 31 May 2023
Narayan HubAnand, 388001NARAYAN INFRA9240%6 Sep 2025Valid until 15 Feb 2029
SHATAK ICONICAnand, 388001SHRI AADI INFRASTRUCTURE920%16 Mar 2026Valid until 30 Jun 2030
VASHISHTH NAKSHTRAKaramsadNAVYA DEVELOPERS9285%19 Jun 2020Valid until 30 Jun 2025
RAMA FLATSBakrol, 388315RAMA BUILDCON9057%9 Dec 2019Valid until 30 Apr 2024
SIDDHI ENCLAVESmit Manojkumar Shah Proprietor of Siddhi Corporation8948%15 Oct 2018Valid until 30 Oct 2024
DEV KAKSHS K DEVELOPERS8836%16 Nov 2021Valid until 20 Mar 2027
Dev ShikharAnand, 388345DEV DEVELOPERS8855%15 May 2019Valid until 31 Dec 2023
Raghukul ParisarKaramsad, 388121PURANSINGH RAMSINGH RATHORE (PROP. OF RAGHUKUL BUILDERS)8899%5 Jan 2019Valid until 30 Apr 2022
ZEENAT RESIDENCYAnand, 388001ZEENAT ENTERPRISE8885%15 May 2019Valid until 30 Sep 2024
KRISHNA PARKBakrol, 388120PARESHKUMAR BHANUPRASAD PATEL (PROP. OF SHREE JANKI DEVELOPERS)8584%12 Apr 2018Valid until 14 Jun 2020
Sahajanad Elegance-3Karamsad, 388325Sahajanand Developers8559%13 Feb 2019Valid until 30 Jun 2021
SAHAJANAND-21SAHAJANAND SARJAN DEVELOPERS8596%3 Jul 2021Valid until 31 Dec 2025
MALBAR HILL & ARCADEBakrol, 388315ROOHANI INFRACON8477%6 Jul 2019Valid until 30 Dec 2021
RUDRA DREAMZLambhvel, 387310RUDRA DEVELOPERS8437%16 Sep 2025Valid until 28 Feb 2030
Ambe Shubh LabhMEHUL PATEL PROPRIETOR OF SHREE AMBICA DEVELOPERS800%6 Sep 2022Valid until 30 Nov 2026
Sahajanand AksharKaramsad, 388120Sahajanand Buildcon8094%16 May 2019Valid until 30 Sep 2022
GAJANAN THE BUSINESS HUBVallabh Vidhyanagar, 388120MD INFRASTRUCTURE79100%23 Jul 2019Valid until 30 Sep 2025
SHATAK HEIGHTSAnand, 388001Vetrivel Infrastructure7663%14 Nov 2018Valid until 30 Jun 2021
SHASHWAT BLISSKaramsad, 388325SHAKTI ASSOCIATES7596%1 Jun 2018Valid until 30 Jun 2022
K 10 ARCADEAnandK 10 DEVELOPERS749%25 Feb 2020Valid until 30 Jun 2024
Krishna AaronAnand, 388120Krishna Hiteshbhai Patel Proprietor of Krishna Realty7289%23 Sep 2019Valid until 30 Jun 2024
NIRAV AVENUEKaramsadDILIPBHAI PURSHOTTAMDAS PATEL (Prop. D. P. Construction)7029%11 Oct 2019Valid until 1 Jul 2024
NIRAV AVENUE (TOWER - B)DILIPBHAI PURSHOTTAMDAS PATEL (Prop. D. P. Construction)701%9 Jun 2021Valid until 31 Mar 2025
NIRAV AVENUE (TOWER - C)DILIPBHAI PURSHOTTAMDAS PATEL (Prop. D. P. Construction)700%28 Dec 2021Valid until 31 Mar 2026
VASHISTH VANIJYAMVallabh Vidhyanagar, 388120MAITRY DEVELOPERS7066%29 Dec 2018Valid until 30 Jun 2022
DEV HEIGHTKaramsadVeerabhai Samantbhai Bharvad Proprietor of Dev Builder6964%5 Jan 2021Valid until 30 Sep 2025
SHIVALIK SHILPSHIVALIK ASSOCIATES6719%5 Mar 2022Valid until 3 May 2025
Radha EleganceKARAMSAD, 388325ASHIRWAD PROCON PRIVATE LIMITED6617%1 Jul 2024Valid until 30 Apr 2029
Atelier SixtyAnandShree Developers6557%24 Sep 2019Valid until 30 Sep 2026
KRISHNA SHREYKrishna Hiteshbhai Patel Proprietor of Krishna Realty6557%19 Jan 2022Valid until 30 Apr 2027
SHATAK RESIDENCY TOWER C AND TOWER DKaramsadVetrivel Infrastructure6498%5 Nov 2020Valid until 16 Mar 2025
ZEENAT BUNGALOWSZEENATH DEVELOPERS6431%20 Oct 2022Valid until 30 Apr 2028
AMISHRUJAnand, 388001Varsh Developers6340%27 Nov 2018Valid until 30 Sep 2023

Developers active in Anand

SHRI RAM BUILDERS (11), PURANSINGH RAMSINGH RATHORE (PROP. OF RAGHUKUL BUILDERS) (8), Krishna Hiteshbhai Patel Proprietor of Krishna Realty (8), ASHIRWAD PROCON PRIVATE LIMITED (6), Vetrivel Infrastructure (4), SUNIL BHAGWATLAL DALAL (4). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Anand projects listed above?

Compare each project against its neighbours, not against the brochure. Of the 308 projects on this page that file a booking figure, the median is 57% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Anand project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What if a Anand project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own GujRERA filings, and we read every report.

Report an errorShare feedback

Data from official GujRERA filings.

Report an error or share feedback

About Anand district. Every figure on this page is summed from the projects' own filings, so if a number looks wrong it helps to say which one.