ReraGenieLog inGet a buyer report

Home / Browse projects / Anand, Gujarat / KRISHNA PARK

Valid until 14 Jun 2020 Residential/Group Housing project

KRISHNA PARK

By PARESHKUMAR BHANUPRASAD PATEL (PROP. OF SHREE JANKI DEVELOPERS)

RG-GJ-87887 · RERA PR/GJ/ANAND/ANAND/Others/RAA02343/EX1/160819 · Last updated on GujRERA portal: 13 Jun 2020

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Jun 2020Possession promisedmoved 12 months from the original
78 of 78Construction stages doneacross 11 buildings; every applicable stage filed complete
14 of 85Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

KRISHNA PARK is a Residential/Group Housing project by PARESHKUMAR BHANUPRASAD PATEL (PROP. OF SHREE JANKI DEVELOPERS) in Anand, Gujarat, registered with GujRERA as PR/GJ/ANAND/ANAND/Others/RAA02343/EX1/160819 on 12 Apr 2018. Possession is promised by 14 Jun 2020. The completion date has moved by 12 months from the original filing. 71 of the 85 units on this registration are recorded sold or booked, and 78 of 78 construction stages are filed complete.

At a glance

Project

  • NameKRISHNA PARK
  • TypeResidential/Group Housing
  • Location
    • NEAR CHANKYAPURI ROW HOUSE
    • BEHIND GAYATRI TENAMENT
    • Bakrol
    • Anand
    • 388120
  • Pincode388120
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/ANAND/ANAND/Others/RAA02343/EX1/160819
  • ReraGenie IDRG-GJ-87887

Builder

  • NamePARESHKUMAR BHANUPRASAD PATEL (PROP. OF SHREE JANKI DEVELOPERS)
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredApr 2018First promiseJun 2019Revised toJun 2020

Key facts

Registration and timeline

  • StatusValid until 14 Jun 2020
  • Registered on12 Apr 2018
  • Promised completion14 Jun 2020
  • Revised completionRevised to 14 Jun 2020 (originally 14 Jun 2019)
  • Buildings11 building records
  • Documents filed48 files

Current status

84%71 of 85 units booked
100.0%Of the estimated cost spent so far

Figures as on 13 Jun 2020, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
wing8---808
wing9---707
wing10---707
wing11---808
wing1---909
wing2---909
wing3---606
wing4---707
wing5---808
wing6---808
wing7---808

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building11

As on 13 Jun 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

78 of 78 construction stages are filed complete across 11 buildings.

wing8100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing9100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing10100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing11100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing5100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing6100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
wing7100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 13 Jun 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,564 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.46 cr
Cost incurredRs 5.46 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
wing1NARs 49.67 lakhRs 49.67 lakh
wing2NARs 49.67 lakhRs 49.67 lakh
wing3NARs 49.67 lakhRs 49.67 lakh
wing4NARs 49.67 lakhRs 49.67 lakh
wing5NARs 49.67 lakhRs 49.67 lakh
wing6NARs 49.67 lakhRs 49.67 lakh
wing7NARs 49.67 lakhRs 49.67 lakh
wing8NARs 49.67 lakhRs 49.67 lakh
wing9NARs 49.67 lakhRs 49.67 lakh
wing10NARs 49.67 lakhRs 49.67 lakh
wing11NARs 49.67 lakhRs 49.67 lakh

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/ANAND/ANAND/Others/RAA02343/EX1/160819Applied Aug 2019; approved Aug 2019

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/ANAND/ANAND/Others/RAA02343/EX1/160819 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)13 Jun 2020
Engineer's certificate (Form 2)13 Jun 2020
Engineer's certificate annexure13 Jun 2020
Accountant's certificate (Form 3)13 Jun 2020
Site photograph, wing813 Jun 2020
Site photograph, wing913 Jun 2020
Site photograph, wing1013 Jun 2020
Site photograph, wing1113 Jun 2020
Site photograph, wing113 Jun 2020
Site photograph, wing213 Jun 2020
Site photograph, wing313 Jun 2020
Site photograph, wing413 Jun 2020
Site photograph, wing513 Jun 2020
Site photograph, wing613 Jun 2020
Site photograph, wing713 Jun 2020
RERA registration certificate12 Apr 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Anand

84%of this project is bookeddistrict median 57%
17%of Anand projects moved their completion datethis one moved by 12 months

Computed across the 310+ Anand projects on ReraGenie, from their own filings.

Keep KRISHNA PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bakrol310+ in Anand

2 kmKRISHNA PARKOther 125Dot size: filed unitsN

Filed coordinates, straight-line distance. 125 registered projects within 2 km.

Builder: PARESHKUMAR BHANUPRASAD PATEL (PROP. OF SHREE JANKI DEVELOPERS)

PARESHKUMAR BHANUPRASAD PATEL (PROP. OF SHREE JANKI DEVELOPERS) has 1 registration on GujRERA, including KRISHNA PARK. Read the full track record. See more projects on the Anand district page.

Frequently asked questions

What are my rights if KRISHNA PARK is delayed beyond 14 Jun 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KRISHNA PARK?

The registered promoter entity is PARESHKUMAR BHANUPRASAD PATEL (PROP. OF SHREE JANKI DEVELOPERS), an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KRISHNA PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in KRISHNA PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA PARK. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.