ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / ZILLION THE SPLENDID

Valid until 31 Dec 2026 Mixed Development project

ZILLION THE SPLENDID

By KESHAV KRUPA DEVELOPERS

RG-GJ-28975 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA10033/160422 · Last updated on GujRERA portal: 18 Nov 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2026Possession promisedno revision filed
14 of 18Construction stages doneacross 2 buildings; furthest along: Installation of lifts, 50%
22 of 207Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

ZILLION THE SPLENDID is a Mixed Development project by KESHAV KRUPA DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA10033/160422 on 16 Apr 2022. Possession is promised by 31 Dec 2026. 185 of the 207 units on this registration are recorded sold or booked, and 14 of 18 construction stages are filed complete.

At a glance

Project

  • NameZILLION THE SPLENDID
  • TypeMixed Development
  • Location
    • RS 606/2 606/3
    • TP 43 FP 58/1 MOJE BAPOD
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA10033/160422
  • ReraGenie IDRG-GJ-28975

Builder

  • NameKESHAV KRUPA DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2026
  • Registered on16 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed42 files

Current status

89%185 of 207 units booked
85.0%Of the estimated cost spent so far

Figures as on 18 Nov 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower B-C-D-E---13833171
Tower A---261036

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 18 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of lifts, at 50%.

Tower B-C-D-E86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
Tower A86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%

Progress on shared amenities19

As on 18 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes95%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes95%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,924 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 14.14 cr
Cost incurredRs 12.02 cr
Spent of the estimate85.0%
BuildingWingEstimatedIncurred
Tower ANARs 7.07 crRs 6.01 cr
Tower B-C-D-ENARs 7.07 crRs 6.01 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHM ASSOCIATES
EngineerZARNA ASSOCIATES

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA10033/160422 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)18 Nov 2024
Engineer's certificate (Form 2)18 Nov 2024
Engineer's certificate annexure18 Nov 2024
Accountant's certificate (Form 3)18 Nov 2024
Site photograph, Tower B-C-D-E18 Nov 2024
Site photograph, Tower A18 Nov 2024
RERA registration certificate16 Apr 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

89%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep ZILLION THE SPLENDID on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmZILLION THE SPLENDIDOther 202Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: KESHAV KRUPA DEVELOPERS

KESHAV KRUPA DEVELOPERS has 1 registration on GujRERA, including ZILLION THE SPLENDID. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if ZILLION THE SPLENDID is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ZILLION THE SPLENDID?

The registered promoter entity is KESHAV KRUPA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ZILLION THE SPLENDID?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ZILLION THE SPLENDID?

The professionals named in the filing: Architect: HM ASSOCIATES; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ZILLION THE SPLENDID?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ZILLION THE SPLENDID. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ZILLION THE SPLENDID to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.