ZENITH HEIGHTS

By DWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED

RG-KA-77555 · RERA PRM/KA/RERA/1251/446/PR/230626/008748 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 90%
123 of 140Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 105 documents Report an error

ZENITH HEIGHTS is a Residential/Group Housing project by DWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/230626/008748 on 23 Jun 2026. Possession is promised by 31 Dec 2029. 17 of the 140 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameZENITH HEIGHTS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560036
  • Pincode560036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/230626/008748
  • ReraGenie IDRG-KA-77555

Builder

  • NameDWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45309KA2016PTC098696
  • GSTIN29AAFCD9528E1ZF
  • Authorized SignatoryMUSUNURI KISHORE
  • DirectorsMUSUNURI KISHORE, Achanta Murali Venkata Krishna, MUSUNURI KISHORE, MUSUNURI SATYAVANI, VATRAPU RANGA REDDY
  • Project HeadMUSUNURI KISHORE
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2026PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Jun 2026
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed105 files

Current status

12%17 of 140 units booked
4.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ZENITH HEIGHTS---1400140

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 90%.

Building: 14% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work90%
Foundation footing work20%
Upto Plinth Level90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)50%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes10%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,157 sq m
Named landowners1
LandownerVillageDistrict
Dwarakamai housing & developers Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 186.76 cr
Cost incurredRs 8.56 cr
Spent of the estimate4.58%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 176.08 crRs 7.17 cr
Payment of taxesRs 6.50 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 2.00 crRs 89.70 lakh
On-site expenditure-Salaries of workersRs 1.00 crRs 37.21 lakh
On-site expenditure-Consultants FeesRs 80.00 lakhRs 42,500
On-site expenditure-Site OverheadRs 38.48 lakhRs 11.71 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPrasanth Nagireddy
EngineerS GANDHI
Chartered AccountantKAMBALA VINEETH REDDY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed105

As listed on the registration, under the names the promoter filed them with; the newest 80 of 105 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/230626/008748 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: DWARKAMAI RERA FORM 4.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5-15-10-2026.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6-15-10-2026.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Rera form 4 dwarakamai_compressed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ARCHITECTS CERTIFICATE_15-07-2026.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Zenith Heights - Engineer Certificate (PR).pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
EC from 1-4-2011 to till dateFile: ECC-08062026-2142728.pdf22 Jun 2026
Single Plot layout/Development plan DeclarationFile: Declaration letter single plot.pdf22 Jun 2026
Single Plot layout/Development oder DeclarationFile: Declaration letter single plot.pdf22 Jun 2026
commencement certificateFile: Commencement certificate declaration.pdf22 Jun 2026
Village mapFile: village map demarcation.pdf22 Jun 2026
fire fighting facilities, drinking water facilities, emergency services and use of renewable energyFile: infrastructure zeneeth.pdf22 Jun 2026
amenities declarationFile: declaration amenites zeneeth 2.pdf22 Jun 2026
Structural certificateFile: Stability Certificate Zenith Heights & License copy.pdf22 Jun 2026
Water sourceFile: water source zee.jpeg22 Jun 2026
Brochure declarationFile: Declaration single plot and brochure 2.pdf22 Jun 2026
Income Tax acknowledgmentsFile: ack all years.pdf16 Jun 2026
EC last 11 yearsFile: ECC-05062026-2058667 (1).pdf16 Jun 2026
ADLRFile: ADLR DPR 16 2022 23.pdf16 Jun 2026
PATA BADALWANEFile: SY 190 PATA BADALAVANE (1).pdf16 Jun 2026
Audit Report Fy 22-23File: Annexure 1.pdf16 Jun 2026
CDP Plan with demarcationFile: CDP_Map_Hagadur_ zenith.pdf16 Jun 2026
Village map with demarcationFile: village map demarcation.pdf16 Jun 2026
Location DemarcationFile: location demarcation.pdf16 Jun 2026
SEIAA NOCFile: SEIAA NOC.pdf16 Jun 2026
FIRE NOCFile: 137269.pdf16 Jun 2026
BWSSB NOCFile: dwaraka NOC.pdf16 Jun 2026
HAL NOCFile: Hal noc.pdf16 Jun 2026
Building LicenseFile: Building license.pdf16 Jun 2026
Directors ReportFile: DIRECTORS REPORT.pdf16 Jun 2026
Plan CopyFile: PRJ_8639_24-25.pdf16 Jun 2026
Proforma AgreementFile: agreement rera.pdf16 Jun 2026
Allotment letterFile: MODEL FORM OF ALLOTMENT LETTER[1].pdf16 Jun 2026
STP DrawingsFile: STP DRAWING NEW.pdf16 Jun 2026
STRUCTURAL STABILITYFile: PRESTABILITY CERTIFICATE.pdf16 Jun 2026
Reply LetterFile: KRERA_Reply_Letter final.pdf16 Jun 2026
water declarationFile: Water source declaration.pdf16 Jun 2026
borewellFile: borewell pic.jpeg16 Jun 2026
project picsFile: project2.jpeg16 Jun 2026
project pics2File: project3.jpeg16 Jun 2026
Audit reportFile: audit report.pdf16 Jun 2026
RTC, survey No.190-
Mutation, survey No.190-
Encumbrance Certificate, survey No.190-
Conversion/Alienation Order, survey No.190-
Sale/Title/Gift Deed, survey No.190-
Khatha, survey No.190-
Registration CertificateFile: Form INC-7_Certificate of Incorporation_21_12_2016.pdf-
Memorandum of AssociationFile: Form INC-7_Memorandum of association_21_12_2016.pdf-
Article of AssociationFile: Form INC-7_Articles of association_21_12_2016.pdf-
GST CertificateFile: GST Certificate.pdf-
Organization StructureFile: SEARCH REPORT_compressed.pdf-
Certificate issued by CA Form 1File: Form1 new_compressed.pdf-
Certificate issued by Architect Form 2File: ARCHITECT CERTIFICATE_ZENITH HEIGHTS.pdf-
Certificate issued by Engineer Form 3File: Form - 3, Engineer (PR).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit_0001.pdf-
Balance Sheet 2024 - 2025File: Financials _FY2024-25.pdf-
Balance Sheet 2023 - 2024File: DBDPL-B SHEET.pdf-
Balance Sheet 2022 - 2023File: dwarakamai ITR FY 2022-2023.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Financials _FY2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: DBDPL-P&L.pdf-
Audited Profit and Loss Statement 2022 - 2023File: dwarakamai ITR FY 2022-2023.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR V.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ACK680036921051124.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ACK318120771270923.pdf-
Director's Report 2024 - 2025File: 624271768_Annual Report 24-25.pdf-
Director's Report 2023 - 2024File: Annual report.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Dwarakamai Apex-3Sy No- 176/3 , Kannamangala Village, near water tankCompleted-No date filed

How this compares with Bengaluru Urban

12%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ZENITH HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmZENITH HEIGHTSOther 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 41 registered projects within 2 km.

Builder: DWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED

DWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED has 1 registration on RERA Karnataka, including ZENITH HEIGHTS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ZENITH HEIGHTS is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ZENITH HEIGHTS?

The registered promoter entity is DWARAKAMAI BUILDERS AND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45309KA2016PTC098696 and GSTIN 29AAFCD9528E1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ZENITH HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ZENITH HEIGHTS?

The professionals named in the filing: Architect: Prasanth Nagireddy; Engineer: S GANDHI; Chartered Accountant: KAMBALA VINEETH REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ZENITH HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ZENITH HEIGHTS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ZENITH HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.