ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / WESTGATE NOBELLA

Valid until 15 Apr 2027 Mixed Development project

WESTGATE NOBELLA

By LANDMARK REALTY

RG-GJ-99451 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA10062/210422 · Last updated on GujRERA portal: 25 Aug 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
13 of 18Construction stages doneacross 2 buildings; furthest along: Internal walls, 70%
55 of 173Units unsoldnot recorded sold or booked
Jump to the 42 documents Report an error

WESTGATE NOBELLA is a Mixed Development project by LANDMARK REALTY in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA10062/210422 on 21 Apr 2022. Possession is promised by 15 Apr 2027. 118 of the 173 units on this registration are recorded sold or booked, and 13 of 18 construction stages are filed complete.

At a glance

Project

  • NameWESTGATE NOBELLA
  • TypeMixed Development
  • Location
    • WESTGATE NOBELLA
    • Near Barsana Residency
    • Undera-Koyali Road
    • Undera-391330
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA10062/210422
  • ReraGenie IDRG-GJ-99451

Builder

  • NameLANDMARK REALTY
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2022PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 15 Apr 2027
  • Registered on21 Apr 2022
  • Promised completion15 Apr 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed42 files

Current status

68%118 of 173 units booked
100.0%Of the estimated cost spent so far

Figures as on 25 Aug 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Triplex---32032
TOWER-A+B+C+D---11328141

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 25 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 70%.

Triplex100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TOWER-A+B+C+D72%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats70%
Sanitary fittings within the flats35%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing35%

Progress on shared amenities19

As on 25 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,310 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 17.87 cr
Cost incurredRs 17.87 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
TOWER-A+B+C+DNARs 11.62 crRs 11.62 cr
TriplexNARs 6.25 crRs 6.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR.PARESH PATEL
EngineerZARNA ASSOCIATES

Documents filed42

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA10062/210422 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)25 Aug 2026
Engineer's certificate (Form 2)4 Aug 2026
Engineer's certificate annexure4 Aug 2026
Architect's certificate (Form 1)18 Apr 2026
Site photograph, Triplex17 Apr 2026
Site photograph, TOWER-A+B+C+D17 Apr 2026
RERA registration certificate21 Apr 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

68%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one has not

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep WESTGATE NOBELLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vadodara2,900+ in Vadodara

2 kmWESTGATE NOBELLAOther 70Dot size: filed unitsN

Filed coordinates, straight-line distance. 70 registered projects within 2 km.

Builder: LANDMARK REALTY

LANDMARK REALTY has 2 registrations on GujRERA, including WESTGATE NOBELLA and WestGate Majestique. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if WESTGATE NOBELLA is delayed beyond 15 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of WESTGATE NOBELLA?

The registered promoter entity is LANDMARK REALTY, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in WESTGATE NOBELLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at WESTGATE NOBELLA?

The professionals named in the filing: Architect: AR.PARESH PATEL; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WESTGATE NOBELLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WESTGATE NOBELLA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WESTGATE NOBELLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.