Home / Browse projects / Vadodara, Gujarat / VRUNDAVAN TENAMENTS

Valid until 28 Sep 2023 Residential/Group Housing project

VRUNDAVAN TENAMENTS

By SHREE MARUTI DEVELOPERS

RG-GJ-80945 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA06645/EX1/131022 · Last updated on GujRERA portal: 27 Sep 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2023Possession promisedmoved 12 months from the original
40 of 40Construction stages doneacross 5 buildings; every applicable stage filed complete
11 of 37Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

VRUNDAVAN TENAMENTS is a Residential/Group Housing project by SHREE MARUTI DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA06645/EX1/131022 on 20 Jan 2020. Possession is promised by 28 Sep 2023. The completion date has moved by 12 months from the original filing. 26 of the 37 units on this registration are recorded sold or booked, and 40 of 40 construction stages are filed complete.

At a glance

Project

  • NameVRUNDAVAN TENAMENTS
  • TypeResidential/Group Housing
  • Location
    • Survey No-675
    • 669
    • 692/2B
    • Sherkhi-Koyli Canal Road
    • Near Gokuldham
    • Koyli
    • Koyli
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA06645/EX1/131022
  • ReraGenie IDRG-GJ-80945

Builder

  • NameSHREE MARUTI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations5 more →

Key dates

this monthRegisteredJan 2020First promiseSep 2022Revised toSep 2023

Key facts

Registration and timeline

  • StatusValid until 28 Sep 2023
  • Registered on20 Jan 2020
  • Promised completion28 Sep 2023
  • Revised completionRevised to 28 Sep 2023 (originally 30 Sep 2022)
  • Buildings5 building records
  • Documents filed45 files

Current status

70%26 of 37 units booked
150.8%Of the estimated cost spent so far

Figures as on 27 Sep 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Type B---303
Type C---808
Type D---808
Type E---909
Type A---909

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 27 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 40 construction stages are filed complete across 5 buildings.

Type B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Type A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 27 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,276 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1.59 cr
Cost incurredRs 2.40 cr
Spent of the estimate150.77%
BuildingWingEstimatedIncurred
Type ANARs 31.88 lakhRs 48.06 lakh
Type BNARs 31.88 lakhRs 48.06 lakh
Type CNARs 31.88 lakhRs 48.06 lakh
Type DNARs 31.88 lakhRs 48.06 lakh
Type ENARs 31.88 lakhRs 48.06 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNirmal S Shah
EngineerKishor L Patel (Pramukh Associates)

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA06645/EX1/131022Applied Aug 2022; approved Oct 2022

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA06645/EX1/131022 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)27 Sep 2023
Engineer's certificate (Form 2)27 Sep 2023
Engineer's certificate annexure27 Sep 2023
Accountant's certificate (Form 3)27 Sep 2023
Site photograph, Type B27 Sep 2023
Site photograph, Type C27 Sep 2023
Site photograph, Type D27 Sep 2023
Site photograph, Type E27 Sep 2023
Site photograph, Type A27 Sep 2023
RERA registration certificate20 Jan 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

70%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep VRUNDAVAN TENAMENTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Koyli2,900+ in Vadodara

2 kmVRUNDAVAN TENAMENTSOther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: SHREE MARUTI DEVELOPERS

SHREE MARUTI DEVELOPERS has 6 registrations on GujRERA, including MARUTI HIGHTS and MARUTI APARTMENT. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if VRUNDAVAN TENAMENTS is delayed beyond 28 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of VRUNDAVAN TENAMENTS?

The registered promoter entity is SHREE MARUTI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in VRUNDAVAN TENAMENTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VRUNDAVAN TENAMENTS?

The professionals named in the filing: Architect: Nirmal S Shah; Engineer: Kishor L Patel (Pramukh Associates). Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VRUNDAVAN TENAMENTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VRUNDAVAN TENAMENTS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VRUNDAVAN TENAMENTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.